You Are Your Brother’s Keeper. Direct Contractors in California Now Responsible for Wage Obligations of Subcontractors
January 31, 2018 —
Garret Murai – California Construction Law BlogIf there’s one law from the 2017 Legislative Session that’s garnered a lot of attention in the construction press, it’s
AB 1701. Under AB 1701, beginning January 1, 2018, for contracts entered into on or after January 1, 2018, direct contractors may be found liable for unpaid wages, fringe or other benefit payments or contributions, including interest, but excluding penalties or liquidated damages, owed by a subcontractor of any tier to their workers. Here’s what you need to know about AB 1701.
What code section did AB 1701 amend?
AB 1701 added a a new section 218.7 to the Labor Code.
To whom does AB 1701 apply?
AB 1701 applies to direct contractors only. A direct contractor is defined as a “contractor that has a direct contractual relationship with an owner.”
On what types of projects does AB 1701 apply?
AB 1701 applies to private works projects only.
When does AB 1701 take effect?
AB 1701 took effect on January 1, 2018 and applies to all contracts entered into on or after January 1, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
Garret, Murai, Wendel, Rosen, Black, Dean, LLPMr. Murai may be contacted at
gmurai@wendel.com
Haight Welcomes Robert S. Rucci
August 26, 2015 —
Robert S. Rucci – Haight Brown & Bonesteel LLPHaight Brown & Bonesteel LLP welcomes new partner Robert S. Rucci. Mr. Rucci joins Haight’s San Diego office in the Construction Law, General Liability and Risk Management & Insurance Law Practice Groups. For 25 years, Mr. Rucci has specialized in defending design professionals, businesses and their employees in addition to representing clients against declaratory relief, breach of contract and bad faith litigation. During his career, he has tried 60 cases to defense verdict and successfully resolved countless matters via mediation, arbitration and settlement conference. His extensive litigation experience is invaluable to our clients.
Haight Brown & Bonesteel LLP
402 West Broadway
Suite 1850
San Diego, CA 92101
www.hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Robert S. Rucci, Haight Brown & Bonesteel LLPMr. Rucci may be contacted at
rrucci@hbblaw.com
Insured's Claim for Replacement Cost Denied
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Illinois Appellate Court affirmed the trial court's ruling that the insured was only entitled to the actual cost value of his loss, not the replacement cost. Lytle v. Country Mutual Ins. Co., 2015 Ill. App. LEXIS 756 (Sept. 30, 2015).
The insured's home was built around 1903. On June 21, 2011, the insured discovered damage to his home because of a severe storm. He made a claim with his insurer, Country Mutual.
The policy contained a depreciation holdback provision. The provision said the insurer would not pay more than the actual cash value until the actual repair or replacement was complete. If the insured elected to accept actual cash value, he would have one year from the date of the loss to repair or replace the damaged property and request the difference between the actual cash value and the replacement cost.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Trial Credit in NJ Appellate Decision for Non-Settling Successive Tortfeasors – Must Demonstrate Proof of Initial Tortfeasor Negligence and Proximate Cause
January 11, 2021 —
Kevin C. Cottone, Robert Wright, & Monica Doss - White and Williams LLPWhere an initial tortfeasor settles in a successive negligence case, the non-settling tortfeasors do not get a credit at trial, says the New Jersey Appellate Division. The court held in Glassman v. Friedel [1], that non-settling successive tortfeasors are not entitled to a pro tanto credit after the initial tortfeasor settles and its negligence is undetermined. Rather, successive tortfeasors have the burden at trial to demonstrate that (1) the initial tortfeasor was negligent, and (2) the initial tortfeasor’s negligence was the proximate cause of the second event.
In Glassman, the plaintiff, as executor of his deceased wife’s estate, sued a restaurant and property owner of the site where his wife fell and fractured her ankle. Afterwards, the plaintiff added defendants including the doctors and the medical center that cared for his wife after she fractured her ankle. The plaintiff alleged that they had been negligent during his wife’s surgery, which led to postoperative complications and injuries to his wife’s leg, ultimately resulting in a fatal pulmonary embolism.
Reprinted courtesy of
Kevin C. Cottone, White and Williams LLP,
Robert Wright, White and Williams LLP and
Monica Doss, White and Williams LLP
Mr. Cottone may be contacted at cottonek@whiteandwilliams.com
Mr. Wright may be contacted at wrightr@whiteandwilliams.com
Ms. Doss may be contacted at dossm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Structural Failure of Precast-Concrete Span Sets Back Sydney Metro Job
February 23, 2017 —
Chris Webb - Engineering News-RecordA key component of Australia’s biggest public transport infrastructure project—Sydney’s $6.3-billion Metro North West—is the subject of a
critical and detailed technical report describing how an elevated viaduct span failed at a stitch joint between two precast segments during construction last September. Project officials say the affected span, which did not suffer a progressive collapse, has since been removed and its replacement fast-tracked to avoid further delays. Little additional detail was provided.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Webb, ENRENR may be contacted at
ENR.com@bnpmedia.com
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Kahana Feld Welcomes Six Attorneys to the Firm in Q4 of 2023
January 16, 2024 —
Linda Carter - Kahana FeldKahana Feld is pleased to announce the addition of six attorneys to the team in the fourth quarter of 2023. We are excited to have each of these individuals on the team.
In our Houston office, Kahana Feld welcomes Partner Donald Loving II and Attorney Elliott Wright. Mr. Loving is a member of the General Liability and Trucking & Transportation practice groups. He earned his Juris Doctor from the University of Houston and has over 30 years of litigation and trial experience, including working as staff & corporate counsel for several prominent insurance carriers including GEICO, Progressive, USAA and Travelers. Mr. Wright is a member of the Construction Defect, General Liability, and Trucking & Transportation practice groups. He earned his Juris Doctor from SMU Dedman School of Law, and has extensive litigation and insurance defense experience.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
$24 Million Verdict Against Material Supplier Overturned Where Plaintiff Failed to Prove Supplier’s Negligence or Breach of Contract Caused an SB800 Violation
March 16, 2017 —
Jon A. Turigliatto, Esq. & Chelsea L. Zwart, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinAcqua Vista Homeowners Assoc. v. MWL Inc. (2017) 2017 WL 371379
COURT OF APPEAL EXTENDS GREYSTONE HOMES, INC. v. MIDTEC, INC., HOLDING THAT CIVIL CODE §936 CREATES A NEGLIGENCE STANDARD FOR CLAIMS AGAINST MATERIAL SUPPLIERS BROUGHT UNDER SB800.
The Fourth District California Court of Appeal recently published its decision Acqua Vista Homeowners Assoc. v. MWI, Inc. (2017) 2017 WL 371379, holding that claims against a material supplier under SB800 (Civil Code §895 and §936) require proof that the SB800 violation was caused by the supplier's negligence or breach of contract.
Civil Code §936 states in relevant part, that it applies "to general contractors, subcontractors, material suppliers, individual product manufacturers, and design professionals to the extent that the general contractors, subcontractors, material suppliers, individual product manufacturers, and design professionals caused, in whole or in part, a violation of a particular standard as the result of a negligent act or omission or a breach of contract .... [T]he negligence standard in this section does not apply to any general contractor, subcontractor, material supplier, individual product manufacturer, or design professional with respect to claims for which strict liability would apply."
Acqua Vista Homeowners Association (the "HOA") sued MWI, a supplier of Chinese pipe used in the construction of the Acqua Vista condominium development. The HOA's complaint asserted a single cause of action for violation of SB800 standards, and alleged that defective cast iron pipe was used throughout the building. After trial, the trial court entered a judgment against MWI in the amount of $23,955,796.28, reflecting the jury's finding that MWI was 92% responsible for the HOA's damages.
MWI filed a motion for a directed verdict and motion for judgment notwithstanding the verdict on the grounds that the HOA had failed to present any evidence that MWI had caused an SB800 violation as a result of its negligence or breach of contract, and had therefore failed to prove negligence and causation as required by SB800, citing to Greystone Homes, Inc. v. Midtec, Inc.(2008) 168 Cal.App.4th 1194. The trial court denied both motions, relying on the last sentence of Civil Code §936, which states in part, "[T]he negligence standard in this section does not apply to any ... material supplier ... with respect to claims for which strict liability would apply."
The Court of Appeal reversed and ordered the trial court to enter judgment in favor of MWI. The Court of Appeal relied on the legislative history of S8800 and Greystone, which held that the first sentence of Civil Code §936 contains an "explicit adoption of a negligence standard" for S8800 claims against product manufacturers. The Court of Appeal reasoned that since §936 treats product manufacturers and material suppliers identically, the holding of Greystone must equally apply to material suppliers.
Because the complaint did not state a common law cause of action for strict liability, the HOA was required to prove that the damages were caused by MWI' s negligence or breach of contract. Although, the Court of Appeal found that while the HOA's evidence may have supported a finding that the manufacturer of the leaking pipes was negligent, the HOA had not provided any evidence that MWI, the supplier, had failed to supply the type of pipe ordered, acted unreasonably in failing to detect any manufacturing defects present in the pipe, or damaged it during transportation. Accordingly, the HOA could not prove that the alleged S8800 violation was caused, in whole or in part, by MWI' s negligence, omission, or breach of contract.
In light of the decision, homeowner and associations that allege only violations of SB800 standards without asserting a common law cause of action for strict liability cannot prevail by simply producing evidence of a violation, and are required to prove that violation was caused by the negligent act or omission, or breach of contract, of the defendant contractor, material supplier, and/or product manufacturer.
Reprinted courtesy of
Jon A. Turigliatto, Esq, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Esq., Chapman Glucksman Dean Roeb & Barger
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of