Don’t Let Construction Problems Become Construction Disputes (guest post)
October 01, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaTo start our week off right, today we have another important article from guest blogger Christopher G. Hill, LEED AP. Chris is a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. He authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals. His practice concentrates on mechanic’s liens, contract review and consulting, occupational safety issues (VOSH and OSHA), and risk management for construction professionals. [His blog was also one of the first construction law blogs I found and followed, even if he is a Duke alum!] Take it away, Chris!
First and foremost, thanks to Melissa for inviting me back to post here at her great blog. She continues to invite me back despite my being a Blue Devil (and I try not to hold her Tar Heel status against her).
So much of discussion relating to construction law and construction lawyers centers on the litigation of disputes. This discussion comes in many forms from avoidance of such litigation through the early intervention of good counsel prior to getting into a project to what sort of resolution mechanism to use. Another branch of this discussion is essentially the right way to pursue your claim (or as some may read it start the dispute ball rolling). Sometimes a payment bond claim is the best method while others a straight up contractual suit is the best way to go.
Of course, all of this discussion presumes that there will be disputes. While I agree to some degree that in the Murphy’s Law riddled world of commercial construction, problems will arise. These problems need not rise to the level of a dispute that requires outside (read court or arbitrator) intervention. A few tips that are easy to write, but admittedly hard to practice at times can hopefully keep problems from blossoming into disputes. I’ve listed three big ones here:
1.Use “in house counsel.” Yes, I know that most of you engineers, architects, commercial general contractors and subcontractors out there aren’t big enough to either want or need a full time attorney on the payroll. What I mean by this is that when problems occur (or preferably before doing so), give your friendly local construction lawyer a call. As I learned from my dad, an ounce of prevention and all that. That 10 minute phone call may help avoid many hours of time and bills from your attorney later down the road.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
No Trial Credit in NJ Appellate Decision for Non-Settling Successive Tortfeasors – Must Demonstrate Proof of Initial Tortfeasor Negligence and Proximate Cause
January 11, 2021 —
Kevin C. Cottone, Robert Wright, & Monica Doss - White and Williams LLPWhere an initial tortfeasor settles in a successive negligence case, the non-settling tortfeasors do not get a credit at trial, says the New Jersey Appellate Division. The court held in Glassman v. Friedel [1], that non-settling successive tortfeasors are not entitled to a pro tanto credit after the initial tortfeasor settles and its negligence is undetermined. Rather, successive tortfeasors have the burden at trial to demonstrate that (1) the initial tortfeasor was negligent, and (2) the initial tortfeasor’s negligence was the proximate cause of the second event.
In Glassman, the plaintiff, as executor of his deceased wife’s estate, sued a restaurant and property owner of the site where his wife fell and fractured her ankle. Afterwards, the plaintiff added defendants including the doctors and the medical center that cared for his wife after she fractured her ankle. The plaintiff alleged that they had been negligent during his wife’s surgery, which led to postoperative complications and injuries to his wife’s leg, ultimately resulting in a fatal pulmonary embolism.
Reprinted courtesy of
Kevin C. Cottone, White and Williams LLP,
Robert Wright, White and Williams LLP and
Monica Doss, White and Williams LLP
Mr. Cottone may be contacted at cottonek@whiteandwilliams.com
Mr. Wright may be contacted at wrightr@whiteandwilliams.com
Ms. Doss may be contacted at dossm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Keep Your Construction Claims Alive in Crazy Economic Times
May 25, 2020 —
Christopher G. Hill - Construction Law MusingsCoronavirus is dominating the news. Construction in Virginia is facing what is at best an uncertain future and at worst a series of large scale shutdowns due to COVID-19. The number of cases seem to grow almost exponentially on a daily basis while states and the federal government try and patch together a solution. All of this adds up to the possibility that owners and other construction related businesses could shutter and importantly payment streams can slow or dry up. Aside from keeping your contractual terms in mind and meeting the notice deadlines found in your contract, these uncertain economic times require you to be aware of the claims process.
Along with whatever claims process is set out in the contract and your run of the mill breach of contract through non-payment type claims, in times like this payment bond and mechanic’s lien claims are a key way to protect your payment interest. The law has differing requirements for each of these unique types of payment claims.
Mechanic’s liens are technical and statute based with very picky requirements. The form and content of a memorandum of lien will be strictly read and in most cases form will trump substance. Further, among other requirements best discussed with a Virginia construction lawyer, you must keep in mind two numbers, 90 and 150. The 90 days is the amount of time that you have in which to record a lien. This deadline is generally calculated from the last date of work (or possibly the last day of the last month in which you did work). File after this deadline and your lien will be invalid because the right to record a lien has expired. The 150 days is a look back from the last day of work or the date of lien filing, whichever is sooner in time. The 150 days applies to the work that can be captured in the lien. In other words, it dictates the amount of the lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hawaii Federal District Rejects Another Construction Defect Claim
November 30, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court, District of Hawaii, continued it long line of cases finding no coverage for claims of faulty workmanship. Nautilus Ins. Co. v. Summary Judgment RMB Enters., 2020 U.S. Dist. LEXIS 200468 (D. Haw. Oct. 28, 2020).
Property owners entered a construction contract with RMB Enterprises to develop and construct residential structures and a pond. The pond walls enclosed residential spaces, providing structural foundations for the walls of the building. After completion of the project, the pond leaked into its pump room. RMB performed remedial work by injecting epoxy into cracks. Later, water from the pondleaked into the interior of a residence near a staircase. Water also leaked into the master bedroom area causing musty odor, mood growth, and increased humidity.
The owners sued RMB asserting breach of contract, breach of warranty, misrepresentation, and negligence claims. Nautilus denied coverage. The policy provided that faulty workmanship did not constitute an "occurrence." But when faulty workmanship caused property damage to property other than "your work," then such property damage would be considered caused by an occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Navigate the New Health and Safety Norm With Construction Technology
August 03, 2020 —
Jeremy Larsen - Construction ExecutiveSafety has always been a pressing issue in construction, and as states reopen and construction projects pick up steam once again, the industry will become even more closely scrutinized than before. Construction safety looks a lot different than it did six months ago. In addition to the concerns around keeping workers safe on construction sites, today’s contractors are faced with a whole new category of risk, and with new health and safety measures that may vary by county, state or region. New requirements range from social distancing and limits on the size of crews, to requiring masks and temperature checks for all workers.
OPERATING IN THE NEW NORM
This sudden onset of COVID-19 put otherwise healthy businesses into a state of chaos that, months later, is still hard to navigate. By March of 2020, reports indicated that nearly one-third of construction projects had come to a halt. Now, as the industry emerges, balancing business continuity efforts with trying to get crews back to work and jobsites moving again will no doubt present challenges. New health and safety measures, plus the fact that no one wants to touch paper in the field, will add another layer of administrative and procedural oversight to the construction process. Of course, these measures are absolutely needed, but construction businesses can’t ignore the fact that it changes the very way projects and jobsites are managed. And, without the right tools in place, it may be a bumpy ride.
Reprinted courtesy of
Jeremy Larsen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Larsen may be contacted at
jeremy.larsen@viewpoint.com
CDJ’s #7 Topic of the Year: The Las Vegas Harmon Hotel Year-Long Demolition & Trial Begins
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFThe 26-story tower in MGM’s $9 billion Las Vegas, Nevada CityCenter project, is being demolished piece by piece after a structural engineer reported that an earthquake of 7.7 could bring it down. While litigation began as early as 2010, the trial didn’t begin until October of 2014, and expectation is it will last through almost all of 2015 as well, according to Carri Geer Thevenot of the Las Vegas Review-Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Toward Increased Citizen Engagement in Urban Planning
November 14, 2018 —
Aarni Heiskanen - AEC BusinessDigitalization creates new opportunities for citizen engagement in urban planning. I gave a short presentation on the topic at the Digitalization in Urban Planning event in Helsinki.
The event was organized by CHAOS Architects, a tech company. Its AI cloud platform allows citizens to share ideas about their city and co-create it with their community. The platform contains engagement-driven applications and third-party APIs that process business intelligence for better interaction and decision-making.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Insurer Must Indemnify Additional Insured After Settlement
October 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that Target was an additional insured under its supplier's policy and the insurer had a duty to indemnify Target after it settled the underlying suit. Selective Ins. Co. v. Target Corp., 2015 U.S. Dist. LEXIS 123230 (E.D. Ill. Sept. 15, 2015).
Angela Brown sued Target when she was allegedly injured by a door to a fitting room that came unhinged and fell on her head. Harbor Industries, Inc. supplied Target with its fitting rooms. Pursuant to the "Supplier Qualification Agreement" (SQA), Harbor named Target as an additional insured under its policy with Selective Insurance Company. The SQA became effective and was to remain in effect until terminated by either party. A second agreement, the "Program Agreement," set forth the terms under which Harbor sold the fitting rooms to Target. The Program Agreement went into effect on April 23, 2009, and expired on July 1, 2010. Brown's injury occurred on December 17, 2011, while the SQA and the policy were in effect, but after the Program Agreement expired.
After Brown's injury, Target tendered to Selective, who denied coverage, contending Target was not an additional insured. The policy's endorsement expanded insureds to any additional insured whom Harbor agreed in a written contract to add as an additional insured. Selective filed suit and the parties filed cross-motions for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at