Midview Board of Education Lawsuit Over Construction Defect Repairs
February 04, 2014 —
Beverley BevenFlorez-CDJ STAFFMidview Local Schools Board of Education in Grafton, Ohio, “filed a lawsuit asking Lorain County Common Pleas Court to order the Ohio School Facilities Commission to help pay for repairs on three new schools,” according to The Morning Journal. Scott Goggin, Midview’s Superintendent, told The Morning Journal: “Water-stained ceilings and weeping windows in three new elementary schools, built with financial help and cooperation of the OSFC Expedited Local Partnership Program, irritated the district for months.”
“The lawsuit,” as reported by The Morning Journal “claimed other school districts received financial help from the state when correcting repairs to their schools built through the same program.” Furthermore, the lawsuit stated that “OSFC failed to assess the total classroom facilities needs of the school district, and to share the costs of repairing defects.”
The Morning Journal reported, “The lawsuit asks for restitution of the state’s share of correcting the construction defects, the costs of the lawsuit and reasonable attorney’s fees, and further relief the court decides is just and fair.”
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Issues Guidance on Mitigating, Preventing Spread of COVID-19 in the Workplace
February 22, 2021 —
Amy R. Patton & Blake A. Dillion - Payne & FearsOn January 29, 2021, the Occupational Safety and Health Administration (“OSHA”) issued new employer guidance on mitigating and preventing the spread of COVID-19 in the workplace. This guidance is intended to help employers and workers outside the healthcare setting to identify risks of being exposed to and of contracting COVID-19 and to determine any appropriate control measures to implement. While this guidance is largely duplicative of prior OSHA and Centers for Disease Control and Prevention (“CDC”) guidance and recommendations, it contains a few new and updated recommendations that employers should note:
Face Coverings
OSHA recognizes that face coverings, either cloth face coverings or surgical masks, are simple barriers that help prevent the spread of COVID-19, and are beneficial for the wearer as well as others. OSHA recommends that employers should provide all workers with face coverings, unless their work task requires a respirator. These face coverings should be provided at no cost and should be made of at least two layers of tightly woven breathable fabric, and should not have exhalation valves or vents. Employers should also require any other individuals at the workplace (i.e., visitors, customers, non-employees) to wear a face covering unless they are under the age of 2 or are actively consuming food or beverages on site. Wearing a face covering does not eliminate the need for physical distancing of at least six feet apart.
Employers must discuss the possibility of “reasonable accommodations” for any workers who are unable to wear or have difficulty wearing certain types of face coverings due to a disability. In workplaces with employees who are deaf or have hearing deficits, employers should consider acquiring masks with clear coverings over the mouth.
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Blake A. Dillion, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Mr. Dillion may be contacted at bad@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Appellate Court Lets Broad General Release Stand in SB 800 Case
February 26, 2015 —
Steven M. Cvitanovic and Colin T. Murphy – Haight Brown & Bonesteel LLPUnder California's SB 800 "Right to Repair Act," a builder may obtain a "reasonable release" to resolve a construction defect claim in exchange for a cash payment. So, what's a "reasonable release" under SB 800? This question was answered by the Second Appellate District in the case of Belasco v. Wells (filed 2/17/2015, No. B254525).
Plaintiff David Belasco ("Plaintiff") purchased a newly constructed residence in 2004 from the builder defendant Gary Loren Wells ("Wells"). In 2006, Plaintiff filed a complaint against Wells with the Contractors' State License Board (the "Board") regarding certain alleged construction defects. The parties settled the 2006 action through written agreement that required Wells to pay Plaintiff $25,000 in consideration for Plaintiff executing a release and a Civil Code §1524 waiver of all known or unknown claims. In 2012, Plaintiff filed a subsequent action against Wells and Wells’ surety, American Contractors Indemnity Company ("American Contractors") (collectively "Defendants"), alleging a defect in the roof that was discovered by Plaintiff in 2011.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Colin T. Murphy, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Murphy may be contacted at cmurphy@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Notice and Claims Provisions In Contracts Matter…A Lot
February 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesTechnical contractual provisions in contracts can carry the day. Whether you like it or not, and whether you appreciate the significance of the provisions, they matter. Notice provisions in a contract mean something. Following the claims procedure in a contract means something. The moment you think they don’t mean anything is the moment they will be thrown in your face and used as a basis to deny your position for additional money or time. You may think these provisions are being used as a “gotcha” tactic. They very well might be. But these are provisions included in the contract you agreed to so you know this risk before any basis for additional money or time even arises.
The recent bench trial opinion in Metalizing Technical Services, LLC v. Berkshire Hathaway Specialty Ins. Co., 2023 WL 385413 (S.D.Fla. 2023) illustrates the reality of not properly complying with such provisions. The keys when dealing with any notice or claims provision, or really any technical provision in your contract, is to (a) negotiate the risk before you sign the contract, (b) chart the provisions so your team know how to ensure compliance, and (c) make sure you comply with them. Period!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor Jailed for Home Repair Fraud
November 27, 2013 —
CDJ STAFFAn Illinois man has received his third prison sentence for construction fraud, this time for five and a half years. Perry Porter was arrested in October and plead guilty to aggravated home repair fraud. Mr. Porter had charged a homeowner $1,000 per hour for a home repair that should have cost a total of $500. Mr. Porter has also been ordered to pay $6,700 in restitution to the victim.
Read the court decisionRead the full story...Reprinted courtesy of
Vacation during a Project? Time for your Construction Documents to Shine!
October 09, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHappy Lazy Day Everyone! What’s that? You didn’t know that August 10th is considered National Lazy Day? Well, it is. And it ties nicely in with today’s theme: how to take a vacation during the thick of the construction project.
Everyone needs a break. You are no different. It can seem, however, that it is impossible to disconnect from the ongoing onslaught of questions, requests for information, change orders, pay applications, and the like. But you can. The key to taking–and enjoying–your vacation is to plan ahead. This is the time for your construction documents to shine. Make sure that your designs are on schedule; make sure that the change orders and RFIs have been processed so there is no backlog. And make sure that your second in command is familiar enough with the day to day details to step into your shoes for the duration.
Then– be sure to give everyone notice. Is it any of their business that you are taking some time off? No. However, everyone procrastinates. So, if you give the entire team advance notice that you will be “off grid” starting on X date, they will be more inclined to get pending issues to you sooner rather than later. They won’t want to be stalled on progress, and with a heads up on when you are out of pocket, they will make it a priority to get requests to you ahead of your departure date.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
GE to Repay $87 Million for Scaled-Back Headquarters Plan
February 27, 2019 —
Rick Clough - BloombergGeneral Electric Co. will reimburse the state of Massachusetts for funds used to develop the manufacturer’s future headquarters, a project that is now being scaled back under Chief Executive Officer Larry Culp.
GE and the state will jointly sell the property in Boston’s Fort Point neighborhood where the company will make its future home, according to an agreement revealed Thursday. GE still plans to move into the campus later this year -- as a tenant rather than owner -- but it’s scrapping plans to build an adjacent 12-story tower.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Clough, Bloomberg
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of