Contractual Setoff and Application When Performance Bond Buys Out of its Exposure
July 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe theory of “setoff” is an important theory in construction disputes. Florida’s Fourth District Court of Appeal recently provided worthy discussion on contractual setoffs:
Setoffs in contract claims are governed by [Florida Statute] section 46.015(2), which provides that if a plaintiff has released “any person in partial satisfaction of the damages sued for, the court shall [setoff] this amount from the amount of any judgment to which the plaintiff would be otherwise entitled at the time of rendering judgment.” The setoff statute intends to prohibit plaintiffs from getting double recoveries.
A setoff requires that settling and non-settling parties be jointly and severally liable. The settled damages must also be the same damages for which the setoff is sought; stated differently, a setoff is not proper where the trial damages to be setoff are separate and distinct from the settled damages.
Close Construction, LLC v. City of Riviera Beach Utility Special District, 49 Fla.L.Weekly D1184d (Fla. 4th DCA 2024) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Intricacies of Business Interruption Claim Considered
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiReaching into the weeds to analyze a business interruption claim, the Massachusetts Court of Appeals determined the cost of ordinary payroll could be included in the calculation of net profit or loss in determining business loss income when business is resumed quickly after a fire. Verrill Farms, LLC v. Farm Family Cas. Ins. Co., 2014 Mass. App. LEXIS 145 (Mass. App. Ct. Nov. 4, 2014).
The insured suffered a fire loss at its farm store. Within two days, the business was reopened at alternate locations at reduced capacity. Within a month, the business had resumed nearly full capacity in temporary locations. No employees were laid off. This allowed the insured to maintain its business and generate income.
The insured submitted a claim for loss of business income, based on its loss of net income in the year after the fire. The insurer paid a sum considerably less than the claim based upon its interpretation of what expenses could be included in a calculation of net profit or loss in order to determine loss of business income. The trial court held that the insurer did not have to pay the cost of ordinary payroll beyond the sixty-day limit, and granted summary judgment in the insurer's favor.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Excess Must Defend After Primary Improperly Refuses to Do So
August 13, 2014 —
Tred R. Eyerly - Insurance Law HawaiiThe excess insurer had a duty to defend after the primary carrier improperly refused its defense obligations. IMG Worldwide, Inc. v. Westchester Fire Ins. Co., 2014 U.S. App. LEXIS 13703 (6th Cir. July 15, 2014).
IMG was sued for over $300,000,000 for alleged fraud, conversion, civil theft and violations of the Florida Deceptive and Unfair Trade Practice Act (FDUTPA). The lawsuit stemmed from a real estate development project. The plaintiffs had invested in the project and alleged that the developer had sold them undeveloped properties with the promise they would be developed. IMG was a consultant on the project and also licensed to the developer the use of the IMG name and logo in marketing materials. IMG had no contractual obligation to actually develop the property or finance the project.
IMG sought coverage from its primary carrier, Great Divide, and from its excess carrier, Westchester. Both denied coverage and refused to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Inverse Condemnation and Roadwork
October 09, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe following case, issued yesterday by the Georgia Supreme Court, addresses the accrual of the statute of limitations on a claim of inverse condemnation based on nuisance.
Wise Bus. Forms, Inc. v. Forsyth Cnty., S22G0874, 2023 WL 6065278 (Ga. Sept. 19, 2023)
We granted certiorari in this case to clarify the standards for determining when a claim for inverse condemnation by permanent nuisance accrues for purposes of applying the four-year statute of limitation set forth in OCGA § 9-3-30 (a).
[. . .]
Permanent nuisance cases vary in relation to when the alleged harm to a plaintiff’s property caused by the nuisance becomes “observable” to the plaintiff. Forrister, 289 Ga. at 333 (2), 711 S.E.2d 641. In some cases, the harm to the plaintiff’s property is immediately observable “upon the creation of the nuisance.” Id. For example, where a landowner or governmental agency “erects a harmful structure such as a bridge or conducts a harmful activity such as opening a sewer that pollutes a stream,” and it is immediately obvious that the structure or activity interferes with the plaintiff’s interests, the plaintiff must file “one cause of action for the recovery of past and future damages caused by [the] permanent nuisance” within four years of the date the structure is completed or the harmful activity is commenced. Id. at 333-336 (2) and (3), 711 S.E.2d 641 (citing Restatement (Second) of Torts §§ 899 and 930). Phrased another way, where the “construction and continuance” of the permanent nuisance at issue is “necessarily an injury, the damage is original, and may be at once fully compensated. In such cases[,] the statute of limitations begins to run upon the construction of the nuisance.” City Council of Augusta v. Lombard, 101 Ga. 724, 727, 28 S.E. 994 (1897).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Colorado Supreme Court Issues Decisions on Statute of Limitations for Statutory Bad Faith Claims and the Implied Waiver of Attorney-Client Privilege
July 11, 2018 —
Jennifer Arnett-Roehrich - Gordon & Rees Insurance Coverage Law BlogThe Colorado Supreme Court has been busy the past two weeks, issuing a couple rulings that should be of interest to the insurance industry:
Statute of Limitations for Bad Faith Statute: In Rooftop Restoration, Inc. v. American Family Mutual Insurance Co., 2018 CO 44 (May 29, 2018), the Colorado Supreme Court held that the one-year statute of limitations that applies to penalties, does not apply to claims brought under C.R.S. 10-3-1116, Colorado’s statutory cause of action for unreasonable delay or denial of benefits. Section 10-3-1116 provides that a first-party claimant whose claim for payment of benefits has been unreasonably delayed or denied may seek to recover attorney fees, costs, and two times the covered benefit, in addition to the covered benefit. A separate Colorado statute, CRS 13-80-103(1)(d) provides a one-year statute of limitations for “any penalty or forfeiture of any penal statutes.” To arrive at the conclusion that the double damages available under section 10-3-1116 is not a penalty, the Court looked at yet another statutory provision, governing accrual of causes of action for penalties, which provides that a penalty cause of action accrues when “the determination of overpayment or delinquency . . . is no longer subject to appeal.” The Court stated that because a cause of action under 10-3-1116 “never leads to a determination of overpayment or delinquency . . . the claim would never accrue, and the statute of limitations would be rendered meaningless.” Para. 15. Presumably, the default two-year statute of limitations, provided by CRS 13-80-102(1)(i), will now be found to apply to causes of action seeking damages for undue delay or denial of insurance benefits.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer Arnett-Roehrich, Gordon & Rees Scully MansukhaniMs. Arnett-Roehrich may be contacted at
jarnett-roehrich@grsm.com
Nine ACS Lawyers Recognized as Super Lawyers – Two Recognized as Rising Stars
August 26, 2024 —
Ahlers Cressman & Sleight PLLCGoing outside the norm of our blogs, which usually discuss construction related issues, Ahlers, Cressman, & Sleight is pleased to announce that nine members of our firm have been selected to the 2024 Washington Super Lawyers list.
Each year, a rigorous process that involves a nomination by peers and a third-party verification of honors, awards, verdicts, settlements, and other criteria relating to their work as an attorney, aims to select no more than five percent of the lawyers in Washington state from no more than seventy practice areas for this distinction. As mentioned, the first step in the process is to be evaluated on their work as an attorney, next candidates are evaluated by their peers and given ratings based on the information known about their work. Finally, candidates are grouped into four firm-size categories and final selections are made. The grouping process is done so that candidates are compared fairly to their peers by firm size, eliminating the potential unfairness that comes with comparing large and small firm outcomes and attorney practices.
The Rising Star list involves an even narrower criteria than the Super Lawyers list. The initial process is the same, however, candidates for the Rising Stars list must be under the age of forty or have less than ten years of experience. For this category less the two and a half percent of lawyers in Washington are selected, making this quite a feat for those who have accomplished the honor.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
The Private Works: Preliminary Notice | Are You Using the Correct Form?
August 20, 2019 —
William L. Porter, Esq. - Porter Law GroupThe Private Works – Preliminary Notice form which contractors, subcontractors and suppliers had become accustomed to using for many years changed in 2004. Despite this change in law, many in the construction industry have still not started using the correct new form. Changes in the law, championed by the American Subcontractors’ Association, gave a significant new benefit to subcontractors and suppliers by giving the subcontractor or supplier some expectation of actually receiving notice of when a Notice of Completion or a Notice of Cessation has been recorded on many private works projects. The law also changed the language of the California Preliminary Notice that subcontractors and suppliers must use to protect their mechanics’ lien, bond claim and stop payment notice rights. If Owners do not send out the Notice of Completion as required by law they incur a diminishing of the protections afforded to them when they record a Notice of Completion or Notice of Cessation on many private works projects.
The revised law requires private project owners to notify all subcontractors and suppliers within 10 days after recording a Notice of Completion or Notice of Cessation that a Notice of Completion or a Notice of Cessation has actually been recorded. In order to receive such notice, the subcontractor or supplier must properly serve the new form of Preliminary Notice. If this properly occurs and the private project owner provides the required notice, then the subcontractor or supplier will have 30 days to record a Mechanics’ Lien. However, if an owner under such circumstances fails to properly notify a subcontractor or supplier within 10 days after recording a Notice of Completion or Notice of Cessation, then the Subcontractor or supplier will have 90 days to record a Mechanics’ Lien. The details of the law can be found in California Civil Code sections 8190, 8414 and 8416.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Esq., Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Construction Litigation Roundup: “Ursinus is Cleared!”
March 11, 2024 —
Daniel Lund III - LexologyUrsinus University in Pennsylvania – a “private, nonprofit liberal arts college” – funded a construction project for a new building utilizing monies loaned by the Montgomery County Health and Higher Education Authority, a public economic development authority “formed by the Board of County Commissioners… authorized to issue bonds relative to projects for eligible educational institution such as Ursinus.”
Loans up to the amount of $23,000,000 became available to the University, and construction proceeded using the loans as construction funds. At issue: whether a project was to be considered publicly funded project such that prevailing wage rates were required to be paid. IBEW filed a related grievance with the Pennsylvania Department of Labor and Industry’s Bureau of Labor Law Compliance, which was refused by the Bureau, on the basis that because work was “financed completely by loans from the Authority, which Ursinus was required to repay in their entirety, the Project was ultimately funded through private sources and exempt from coverage under the [Pennsylvania Prevailing Wage Act].” A grievance to the Prevailing Wage Appeals Board ensued, and the Board took a different position.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com