Understanding the Details: Suing Architects and Engineers Can Get Technical
November 02, 2017 —
Steven M. Cvitanovic & Stephen M. Tye - Haight Brown & Bonesteel LLPBefore suing an architect or engineer for professional negligence, a plaintiff must obtain a “certificate of merit” (“Certificate”) under Code of Civil Procedure section 411.35. Boiled down to the basics, the Certificate declares that the attorney consulted with and received an opinion from an expert that a reasonable and meritorious case exists against said design professional. The Certificate must be filed before serving the complaint on any defendant, but can be filed within 60 days under certain circumstances. This rule was recently analyzed against another long-standing rule in California, known as the “relation-back doctrine.” Under the relation-back doctrine, a court will deem a later-filed pleading, such as an amended complaint, to be deemed filed at the time of an earlier complaint.
In Curtis Engineering Corp. v. Superior Court of San Diego County, No. D072046, (Cal. Ct. App. 10/23/17), the Fourth Appellate Court considered the interplay between section 411.35 and the relation-back doctrine, holding that a Certificate filed more than 60 days after filing the original pleading does not relate back to the filing of the original pleading.
Reprinted courtesy of
Steven Cvitanovic, Haight Brown & Bonesteel LLP and
Stephen Tye, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Expert Medical Science Causation Testimony Improperly Excluded under Daubert; ID of Sole Cause of Medical Condition Not Required
April 15, 2014 —
R. Bryan Martin & Whitney L. Stefko - Haight Brown & Bonesteel LLPOn April 4, 2014, in Messick v. Novartis Pharmaceuticals Corp., the United States Court of Appeals for the Ninth Circuit reversed the district court's summary judgment in favor of Defendant Pharmaceutical Corporation because the district court improperly excluded expert testimony. The three-judge panel held that the district court erred by excluding causation testimony offered by Plaintiff's expert it found to be irrelevant and unreliable.
Plaintiff was diagnosed with breast cancer in 2000. In response to her development of osteoporosis after chemotherapy, Plaintiff treated with the drug Zometa for several months in 2002. Zometa is a bisphosphonate, a class of drug commonly used to treat multiple myeloma. Such drugs are generally used to reduce or eliminate the possibility of skeletal-related degeneration and injuries to which cancer patients are particularly susceptible. Novartis Pharmaceuticals Corporation produces Zometa, which was approved by the FDA in 2001 and 2002. In 2005 after encountering issues with her jaw, it was discovered that Plaintiff had osteonecrosis near three of her teeth. The oral specialists treating Plaintiff did so under the assumption that she was suffering from bisphosphonate-related osteonecrosis of the jaw ("BRONJ"), a condition recognized by the American Association of Oral and Maxillofacial Surgeons ("AAOMS"). Plaintiff's BRONJ healed in 2008 - three years after beginning treatment.
Thereafter, Plaintiff brought suit against Novartis for strict products liability, negligent manufacture, negligent failure to warn, breach of express and implied warranty, and loss of consortium. In support of her claims, Plaintiff offered her expert's testimony on ONJ and BRONJ, and on the causal link between plaintiff's bisphosphonate treatment and later development of BRONJ. Novartis filed a Daubert motion to exclude the specific causation testimony of Plaintiff's experts and a motion seeking summary judgment. The district court granted both motions on the basis that Plaintiff's expert testimony was irrelevant and unreliable.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Proposed House Green New Deal Resolution
February 27, 2019 —
Anthony B. Cavender - Gravel2GavelA Resolution has been proposed to the House for consideration that would recognize the Federal Government’s duty “to create a Green New Deal.” It sets forth a very ambitious 10-year program to mobilize and transform every aspect of American life to combat the threats of climate change by transitioning to an economy based upon 100% clean and renewable energy.
In doing so, millions of new jobs would be created, and everyone who wants a job would be guaranteed a job. The sponsors’ talking points declare that there is no time to lose, that Americans love a challenge, and “this is our moonshot.” The obvious goal is to eliminate the generation and use of fossil fuel and nuclear energy—they are simply not part of the solution.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
BHA has a Nice Swing Benefits the Wounded Warrior Project
May 20, 2015 —
Beverley BevenFlorez-CDJ STAFFBert L. Howe & Associates (BHA) would like to congratulate the winners of the BHA Has a Nice Swing golf game for charity at the 2015 West Coast Casualty Construction Defect Seminar. With the help of the participants, BHA was able to raise $1925 to benefit the Wounded Warrior Project. BHA would also like to congratulate the raffle winners. Prizes included a DJI Phantom 2 Vision+ Drone and Dodger baseball tickets.
The Wounded Warrior Project’s purpose is to raise awareness and enlist the public’s aid for the needs of injured service members; to help injured service members aid and assist each other; and to provide unique, direct programs and services to meet the needs of injured service members.
Learn more about the Wounded Warrior Project...
Read the court decisionRead the full story...Reprinted courtesy of
Let’s Get Surety Podcast – #126 Building the Future: AI, Construction and Law
December 31, 2024 —
Denis Serkin - Peckar & Abramson, P.C.Denis Serkin, partner in P&A’s New York and New Jersey offices, joins the latest episode of the NASBP podcast “
Let’s Get Surety” to delve into the transformative impact of AI on the construction industry and construction law.
In this insightful discussion, Denis explores how AI tools are already enhancing design and supply chains and shares his vision for AI’s eventual integration across every facet of the industry.
Read the court decisionRead the full story...Reprinted courtesy of
Denis Serkin, Peckar & Abramson, P.C.Mr. Serkin may be contacted at
dserkin@pecklaw.com
Atlanta Hawks Billionaire Owner Plans $5 Billion Downtown Transformation
May 01, 2023 —
Brett Pulley & Eliza Ronalds-Hannon - BloombergTony Ressler, the billionaire co-founder of Ares Management and Atlanta Hawks owner, said he’s undeterred by the recent property downturn and is moving forward with his partners to transform downtown Atlanta by turning a vacant railyard into a $5 billion mix of hotels, restaurants and offices.
Fears about the stability of commercial real estate aren’t affecting development of Centennial Yards, a 50-acre, gritty subterranean swath of land now under development by CIM Group, in which Ressler is an investor, he said in an interview.
“We’re not worried about any of that,” Ressler said. “Higher or lower interest rates may change your rate of return but will not determine the success or failure of a project. For us, the project is funded and we’re full steam ahead.”
Reprinted courtesy of
Brett Pulley, Bloomberg and
Eliza Ronalds-Hannon, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Update: Lawyers Can Be Bound to Confidentiality Provision in Settlement Agreement
January 13, 2020 —
Danielle Ward, Esq. - Balestreri Potocki & HolmesIn July 2019, the California Supreme Court ruled that an attorney’s signature under the often-used phrase “approved as to form and content” does not preclude a finding that the attorney could be bound to the terms of a settlement agreement. (Monster Energy Co. v. Schechter (2019) 7 Cal.5th 781.) This decision marks a reversal of the Fourth District Court of Appeal’s 2018 ruling that approval of a contract is not tantamount to an agreement to be bound by that contract.
The underlying action stemmed out of a wrongful death suit by Wendy Crossland and Richard Fournier, parents of the decedent, against Monster Energy Company. The parties negotiated a settlement, a critical of element of which was a confidentiality provision aimed at keeping the the settlement secret.
The confidentiality provision prohibited plaintiffs and their counsel of record from disclosing both the existence of the settlement, or the terms thereof, to any person, entity, or publication, including the legal website Lawyers & Settlements. The attorneys signed the agreement under the phrase “approved as to form and content.”
Shortly after the settlement agreement was executed, the Plaintiffs’ attorney Bruce Schechter disclosed his clients’ settlement with Monster in an interview with Lawyers & Settlements. Monster filed suit against Mr. Schechter for breach of contract, among other causes of action. Mr. Schechter challenged the lawsuit with a SLAPP motion, essentially arguing that the lawsuit was meritless and merely an attempt to thwart freedom of speech.
The trial court denied Mr. Schechter’s motion as to the breach of contract cause of action finding that the settlement clearly contemplated that the attorneys were subjected to the terms of the agreement, and Schechter’s claim that he was not a party because he merely approved as to form and content was “beyond reason.”
The Fourth District Court of Appeal reversed, concluding that Mr. Schechter was not a party to the agreement by virtue of his signature approving the form and content, and the Plaintiffs had no authority to bind their attorney to the terms of the agreement. The Court of Appeal found that by affixing his signature to the agreement Mr. Schechter was merely manifesting his “professional thumbs up” in line with legal industry’s customary understanding.
In its reversal, the California Supreme Court did not disturb the legal community’s understanding of the phrase “approved as to form and content.” Rather, the Court concluded that an attorney’s signature under that often-used phrase does not preclude as a matter of law that the attorney intended to be bound by the agreement. The entire agreement, including the substantive provisions, need to be examined to determine the attorney’s intent in affixing his/her signature to the agreement.
Turning to the Crossland/Fournier Monster settlement agreement, the Court was unpersuaded by Mr. Schechter’s argument that he was not bound to the agreement because counsel was not included in the definition of “party”. The Court stated that it’s the substance of the agreement that determines whether counsel is a party to the contract, as opposed to a party to the lawsuit.
The Court was persuaded, in part, by the important role that confidentiality plays in brokering settlements. It noted that public disclosure of private settlements would serve to “chill” parties’ ability to resolve matters short of trial, and there was little doubt that confidentiality was an important term of the Crossland/Fournier Monster settlement. In concluding that Monster had met its burden to defeat an anti-SLAPP motion, the Court pointed to the numerous references to counsel in the substantive provisions of the agreement which a trier of fact could conclude bound Mr. Schechter to the confidentiality terms.
Danielle Ward has concentrated her law practice on defending developer, general contractor, and subcontractor clients in a variety of construction matters. She has been an attorney with Balestreri Potocki & Holmes since 2010 and can be reached at dward@bph-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Properly Trigger the Performance Bond
January 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesOriginally Published by CDJ on January 5, 2017
A performance bond is a valuable tool designed to guarantee the performance of the principal of the contract made part of the bond. But, it is only a valuable tool if the obligee (entity the bond is designed to benefit) understands that it needs to properly trigger the performance bond if it is looking to the bond (surety) to remedy and pay for a contractual default. If the performance bond is not properly triggered and a suit is brought upon the bond then the obligee could be the one materially breaching the terms of the bond. This means the obligee has no recourse under the performance bond. This is a huge downside when the obligee wanted the security of the performance bond, and reimbursed the bond principal for the premium of the bond, in order to address and remediate a default under the underlying contract.
A recent example of this downside can be found in the Southern District of Florida’s decision in Arch Ins. Co. v. John Moriarty & Associates of Florida, Inc., 2016 WL 7324144 (S.D.Fla. 2016). Here, a general contractor sued a subcontractor’s performance bond surety for an approximate $1M cost overrun associated with the performance of the subcontractor’s subcontract (the contract made part of the subcontractor’s performance bond). The surety moved for summary judgment arguing that the general contractor failed to property trigger the performance bond and, therefore, materially breached the bond. The trial court granted the summary judgment in favor of the performance bond surety. Why?
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com