HB 20-1046 - Private Retainage Reform - Postponed Indefinitely
May 04, 2020 —
David M. McLain – Colorado Construction LitigationOn Tuesday, February 18th, the Colorado House Business Affairs & Labor Committee voted 10-0 to postpone indefinitely House Bill 1046. If it had been enacted, HB 1046 would have required, for all for all construction contracts of at least $150,000:
- A property owner to make partial payments to the contractor of any amount due under the contract at the end of each calendar month or as soon as practicable after the end of the month;
- A property owner to pay the contractor at least 95% of the value of satisfactorily completed work;
- A property owner to pay the withheld percentage within 60 days after the contract is completed satisfactorily;
- A contractor to pay a subcontractor for work performed under a subcontract within 30 calendar days after receiving payment for the work, not including a withheld percentage not to exceed 5%;
- A subcontractor to pay any supplier, subcontractor, or laborer who provided goods, materials, labor, or equipment to the subcontractor within 30 calendar days after receiving payment under the subcontract; and
- A subcontractor to submit to the contractor a list of the suppliers, sub-subcontractors, and laborers who provided goods, materials, labor, or equipment to the subcontractor for the work.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Eleventh Circuit Vacates District Court Decision Finding No Duty to Defend Faulty Workmanship Claims
November 02, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit vacated the district court's grant of summary judgment to the insurer finding there was no duty to defend. Southern-Owners Ins. Co. v. Mac Contractors of Florida, LLC, 2020 U.S. App. LEXIS 23918 (11th Cir. July 29, 2020).
Mac Contractors entered into a contract with homeowners to serve as general contractor for the construction of a custom residence. Problems arose during construction and Mac eventually led the job site before completing the project. The home owners sued, alleging that Mac and its subcontractors had left the residence "replete with construction defects." Damages were sought for having to repair and remediate all defective work performed by Mac.
Mac tendered under its CGL policy to its insurer, Southern-Owners. A defense was granted, but later withdrawn when Southern-Owners filed suit seeking a declaration that it owed no duty to defend or indemnify Mac. On cross-motions for summary judgment, the district court found in favor of Southern-Owners based on the exclusion for "Damage to Your Work." The Eleventh Circuit vacated on appeal, concluding that the underlying complaint could fairly be construed to allege damages that fell outside of the exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Progress, Property, and Privacy: Discussing Human-Led Infrastructure with Jeff Schumacher
August 30, 2021 —
Aarni Heiskanen - AEC BusinessWe sat down with Jeff Schumacher, Microsoft’s Global Workplace Services Regional Lead Ireland, UK, and MEA, in the run-up to his keynote speech at WDBE 2021. Our conversation covered how technical innovation has changed the sector, the dangers of assumption, and why retaining a human-centred perspective is vital in a data-driven business.
As we leave lockdown, the conversation shifts from measuring the impact on society to the positive change that our urban spaces and built environment can provide. But when it comes to contemporary professional working spaces and the habits of the people working within them, it can be difficult to find a solution that works.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Justin Clark Joins Newmeyer & Dillion’s Walnut Creek Branch as its Newest Associate
May 03, 2017 —
Newmeyer & Dillion LLPWALNUT CREEK, Calif. – APR. 28, 2017 – Up and coming associate and insurance attorney
Justin Clark is the newest associate to join the ever-growing litigation practice at Newmeyer & Dillion LLP’s Walnut Creek office. Clark brings experience in the areas of insurance litigation, construction defect litigation, and business transactions.
Walnut Creek’s managing partner Brian Morrow explained why he is so excited by the addition of Clark: “We are thrilled to have Clark on board, as his emphasis on insurance coverage will assist in a key area for our clients, and further expand our capabilities in our northern California office.”
Clark has a background in a variety of practice areas, including insurance coverage, products liability, and asbestos litigation. He advocates for manufacturers, suppliers, distributers, and contractors in all phases of litigation. Clark represents developers, builders, and general contractors in construction and insurance disputes. He also helps small business clients draft commercial contracts to better serve their growing business needs. Clark can be reached at justin.clark@ndlf.com or 925-988-3263.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Additional Insured Not Entitled to Coverage for Post-Completion Defects
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe general contractor, an additional insured on the subcontractor's policy, was not entitled to coverage for construction defect claims that arose after completion of the project. Weitz Co. v. Acuity, 2016 U.S. Dist. LEXIS 150433 (S.D. Ohio Oct. 31, 2016).
Weitz was the general contractor hired by Twin Lakes for construction of a residential community. One of the subcontractors, Miter Masonry, was insured by Acuity under a CGL policy. Work on the project began in 2002 and was substantially completed in 2005. In 2011, Twin Lakes notified Weitz that there were moisture infiltration issues at the project that may be related to work during the project.
Twin Lakes filed a Demand for Arbitration against Weitz on November 30, 2012. Twin Lakes alleged that the defects included the building wrap, windows, doors, wood trim, aluminum wrap, vinyl siding, flashing and brick veneer not being installed in accordance with contract documents and/or industry standards. The arbitration panel awarded damages to Twin Lakes in the amount of $2,775,771.86. The panel found that Weitz breached sections of the contract which caused moisture intrusion and damage to all the units. The panel ultimately held that Weitz could recover from the subcontractors 100% of the $2,775,771.86 awarded. Acuity's insured, Miter Masonry, was determined to be 4% at fault for the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Measures Landlords and Property Managers Can Take in Response to a Reported COVID-19 Infection
May 18, 2020 —
Kyle Janecek & Jason Morris - Newmeyer DillionMost landlords and property managers are now familiar with steps they should be taking to reduce the spread of COVID-19. But what if a tenant or employee has tested positive with COVID-19? Unfortunately, many landlords and property managers are grappling with this very question. While there’s some clarity as it pertains to evictions in the landlord-tenant context, other considerations like disinfection, required notices, and maintenance, are evolving or unclear. Here are steps landlords and property managers can take in response to an employee or tenant testing positive with COVID-19.
Measures Landlords Can Take for Employees
For workplaces, there is a large variety of guidelines and procedures that are generally available to review. The Centers for Disease Control and Prevention (CDC) has valuable guidance available online here and here. The Occupational and Safety Health Administration (OSHA) has valuable guidance available online here. In short, if there is an incident where one employee may have exposed others to COVID-19, here are five steps employers should take:
- Send the affected employee home and instruct them not to return to work until the criteria to discontinue home isolation are met in consultation with healthcare providers, and state and local health departments. Make sure to maintain all information about employee illnesses as a confidential medical record.
- Ask the affected employee whether they have had close contact with any other workers.
Reprinted courtesy of
J. Kyle Janecek, Newmeyer Dillion and
Jason L. Morris, Newmeyer Dillion
Mr. Janecek may be contacted at kyle.janecek@ndlf.com
Mr. Morris may be contacted at jason.morris@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
The 2017 ASCDC and CDCMA Construction Defect Seminar and Holiday Reception
November 21, 2017 —
Beverley BevenFlorez-CDJ STAFFThe annual Construction Defect Seminar and Holiday Reception presented jointly by the Association of Southern California Defense Counsel (ASCDC) and the Construction Defect Claims Managers Association (CDCMA) takes place this November 30th at the Hilton Costa Mesa. This one-day seminar includes two sessions: Session 1, Recent developments in Insurance Coverage and Related Impacts on Case Resolution; Session 2, Impact of Design Claims in Construction Defect Actions. A holiday reception will immediately follow the seminar.
The keynote speaker this year is Hon. Charles Margines, Presiding Judge of the Orange Superior Court. Other speakers include David Napper, Esq., of Chapman Glucksman Dean Roeb & Barger, Adrienne Cohen, Esq., Law Offices of Adrienne D. Cohen, Blenda Eyvazzadeh, Chub North American Claims, and many others. This activity has been approved for Minimum Continuing Legal Education Credit by the State Bar of California in the amount of 3.0 hours.
November 30th, 2017
Hilton Costa Mesa
3050 Bristol Street
Costa Mesa, California 92626
United States
PDF Registration...
Online Registration...
Read the court decisionRead the full story...Reprinted courtesy of
Mechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
January 04, 2021 —
William L. Porter - Porter Law GroupMechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
California law entitles unpaid contractors, subcontractors, and material suppliers to record a mechanics lien on property where they performed work or supplied materials. The mechanics lien attaches to the real property as a legal interest and secures the right to payment for the work performed and materials supplied. If payment is not forthcoming the mechanics lien allows the property where the work was performed and materials supplied to be sold under court order to satisfy the debt. It is a powerful remedy against owners and their agents who do not pay for work performed and materials supplied to improve the owner’s property.
A Mechanics Lien Release Bond Frees Property from a Mechanics Lien
Owners typically do not wish to have their property sold out from under them. Fortunately for owners, there is a method by which a mechanics lien can be substituted for another interest and sale of the property thereby avoided. This method is through the use of a mechanics lien release bond. California Civil Code §8424 allows a property owner or contractor effected by a mechanics lien to record a mechanics lien release bond equal to 125 percent of the lien amount with the County Recorder where the mechanics lien has been recorded. The effect of this is to substitute the mechanics lien release bond for the mechanics lien itself, thereby relieving the property from the possibility of that property being sold to satisfy the debt. Instead, any payment made will come from the release bond.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at