California Subcontractor Gets a Kick in the Rear (or Perhaps the Front) for Prematurely Recorded Mechanics Lien
October 21, 2019 —
Garret Murai - California Construction Law BlogCalifornia provides three statutorily recognized construction payment remedies: (1) mechanics liens; (2) stop payment notices; and (3) payment bond claims. Each is intended to provide payment protections for those who furnish labor, materials and services on a construction project. However, each is also different in important ways.
One of those differences has to do with timing. Specifically, when the statutory payment remedy may be used by a claimant. Stop payment notices can be served at any time during a project even before a claimant has completed its work. However, mechanics liens may only be recorded and payment bond claims may only be made after a claimant has completed or ceased performing its work.
In Precision Framing Systems, Inc. v. Luzuriaga, Case No. E069158 (August 29, 2019), the 4th District Court of Appeal examined whether a subcontractor had prematurely recorded a mechanics lien and, thereby, was prevented from filing a lawsuit to foreclose on its mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Proposed Bill Provides a New Federal Tax Credit for the Conversion of Office Buildings
September 06, 2021 —
Emily K. Bias & Brittany Griffith - Gravel2Gavel Construction & Real Estate Law BlogAt the end of July 2021, a bill was introduced in the House and Senate, which, if enacted, would create a federal tax credit to fund the conversion of unused office buildings into residential, commercial, or mixed-use properties. The Revitalizing Downtowns Act (S. 2511), which is modeled after the federal historic rehabilitation tax credit, would provide a federal tax credit equal to 20 percent of “qualified conversion expenditures” with respect to a “qualified converted building.”
A “qualified converted building” means any building that (i) was nonresidential real property for lease to office tenants, (ii) has been “substantially converted” from an office use to a residential, retail, or other commercial use, (iii) in the case of conversion to residential units, is subject to a state or local affordable housing agreement or has at least 20 percent of the units rent restricted and set aside for tenants whose income is 80 percent or less of area median gross income, (iv) was initially placed in service at least 25 years before the beginning of conversion, and (v) may be depreciated or amortized.
Reprinted courtesy of
Emily K. Bias, Pillsbury and
Brittany Griffith, Pillsbury
Ms. Bias may be contacted at emily.bias@pillsburylaw.com
Ms. Griffith may be contacted at brittany.griffith@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Supreme Court Declares Subcontractor Not Required to Provide Pre-Litigation Notice to Supplier
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Traub Lieberman Straus & Shrewsberry LLP blog on Construction Law, even though the Nevada Revised Statutes Annotated (NRS) Chapter 40 requires a general contractor “to provide pre-litigation notice (followed by an opportunity to repair) to a subcontractor or supplier the general contractor believes to be responsible” for the issue prior to filing suit, the Nevada Supreme Court “determined that NRS Chapter 40 imposes no such requirement upon a subcontractor.”
In Barrett v. Eighth Judicial District Court, “the court reasoned that ‘while the statutes’ and, indeed, chapter’s purpose is, in part, to allow defendants an initial opportunity to repair, the Legislature chose to carry out that purpose in the manner provided by the statutes, and [the Supreme Court] will not read into the statutes a notice requirement between a subcontractor and another subcontractor or supplier where none exist.’”
Read the court decisionRead the full story...Reprinted courtesy of
The Latest News on Fannie Mae and Freddie Mac
May 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Federal Housing Finance Agency released a report on April 30th, which stated that in a severe economic downturn Fannie Mae (FNMA) and Freddie Mac (FMCC) “could require an additional bailout of as much as $190 billion… according to the results of stress tests,” according to Clea Benson writing for Bloomberg.
“These results of the severely adverse scenario are not surprising given the company’s limited capital,” FNMA Senior Vice President Kelli Parsons said in a statement, as reported by Benson published in Bloomberg. “Under the terms of the senior preferred stock purchase agreement, Fannie Mae is not permitted to retain capital to withstand a sudden, unexpected economic shock of the magnitude required by the stress test.”
Furthermore, in another Bloomberg article, Cheyenne Hopkins and Clea Benson reported that Democrats remain divided on how to replace FNMA and FMCC. “If we don’t get this right, we’ll create major disturbances in the housing market which will have a profound impact on families, on homeownership and certainly on our national economy,” Oregon Democrat Jeff Merkley said in an interview, as reported by Cheyenne and Benson. “Merkley described himself as ‘still in negotiations’ with the bill’s sponsors.”
Read the full story, Clea Benson Article...
Read the full story, Cheyenne Hopkins & Clea Benson Article... Read the court decisionRead the full story...Reprinted courtesy of
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the court decisionRead the full story...Reprinted courtesy of
Robinson + Cole
Bankruptcy on a Construction Project: Coronavirus Edition
May 25, 2020 —
Garret Murai - California Construction Law BlogExperts are warning of a wave of bankruptcies in the wake of the coronavirus pandemic. In some industries, such as the hard hit retail sector, that rising tide has already begun as J. Crew and Neiman Marcus filed for bankruptcy protection this past week.
While the federal government’s stimulus package, including the $660 billion Paycheck Protection Program which is part of the larger 2.2 trillion CARES Act, may help to stem the tide of bankruptcies, Chapter 11 bankruptcy filings increased 26% in April over the same period last year.
How the pandemic will impact the construction industry is uncertain. Anecdotally, we’ve been hearing from clients that some project owners are stalling projects that are still in the planning stages as they evaluate the situation, which suggests long term impacts that can be ridden out rather than short term impacts that can devastate on-going construction projects.
Nevertheless, with 24-7 coverage of the pandemic, project owners, contractors, material suppliers, and equipment lessors are understandably concerned with the impact a bankruptcy might have on a construction project. So, here’s a primer on bankruptcies on a construction project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Traub Lieberman Partner Eric D. Suben and Associate Laura Puhala Win Summary Judgment in Favor of Insurer, Determining it has No Duty to Defend
September 18, 2023 —
Traub LiebermanIn a declaratory judgment action brought before the United States District Court, Eastern District of New York, Traub Lieberman Partner Eric D. Suben and Associate Laura Puhala won summary judgment in favor of Plaintiff Foremost Signature Insurance Co. (“Foremost”), obtaining a declaration that it has no obligation to defend or indemnify Defendant 170 Little East Neck Road LLC (“Little East”) in an underlying state court personal injury action.
In the underlying action, a self-employed financial advisor leasing a suite for her business on the second floor of the property at 170 Little East Neck Road (the “Property”), sued Little East in New York Supreme Court, Suffolk County, alleging injuries resulting from slipping on ice on a walkway near an exterior door at the Property.
Reprinted courtesy of
Eric D. Suben, Traub Lieberman and
Laura S. Puhala, Traub Lieberman
Mr. Suben may be contacted at esuben@tlsslaw.com
Ms. Puhala may be contacted at lpuhala@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Contractor Entitled to Continued Defense Against Allegations of Faulty Construction
November 01, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe U.S. District Court found that the contractor was entitled to a defense in the underlying state court action. Pa. Nat'l Mut. Cas. Ins. Co. v. Zonko Builders, 2021 U.S. Dist. LEXIS 168855 (D. Del. Sept. 7, 2021).
Zonko was the general contractor for building the Salt Meadows Townhomes Condominium. This included supervising subcontractors in the installation of siding, house wrap, and flashing in five buildings between 2005 and 2007. In 2016, Salt Meadows and its individual members ("Association") found property damage in the condominiums.
The Association sued Zonko in state court, alleged that resulting damages included drywall damage in ceilings or walls, flooring and carpet, water damage around window trim, rot on window frames, incorrect flashing around roofs and windows, possible ridge vent leaks, and possible foundation issues.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at