Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Nevada Bill Would Bring Changes to Construction Defects
February 21, 2013 —
CDJ STAFFIf Nevada Senate Republicans get there way, changes are afoot for construction defect law in Nevada. Senate Minority Leader Michael Roberson has introduced a bill that, according to the Las Vegas Sun, “redefines what constitutes a construction defect, reduces the time in which lawsuits can be filed, and removed automatic awarding of attorney fees.” Roberson notes that over the last six years, construction defect claims have more than tripled.
Read the court decisionRead the full story...Reprinted courtesy of
“Incidental” Versus “Direct” Third Party Beneficiaries Under Insurance Policies in Which a Party is Not an Additional Insured
April 18, 2023 —
Garret Murai - California Construction Law BlogAs they say, when it rains, it pours. Indemnity and insurance are the “Big Two” when it comes to risk avoidance on construction projects. The next case,
LaBarbera v. Security National Security Company, 86 Cal.App.5th 1329 (2022), involves both. It’s an interesting case, which I think could have gone either way, involving claims by a higher-tiered party that they were a third party beneficiary under an insurance policy in which they were not named as an additional insured.
The LaBarbera Case
The Indemnity Provision and Insurance Policy
In June 1016, Chris LaBarbera hired Richard Knight doing business as Knight Construction to remodel his house in Carmichael, California. The construction contract included an indemnity provision which provided that Knight would defend and indemnify LaBarbera from all claims arising out the remodeling work except for claims arising from LaBarbera’s sole negligence and willful misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Homebuyers Aren't Sweating the Fed
December 17, 2015 —
Rani Molla – BloombergGadflyHome prices are escalating, but the culprit isn't the Federal Reserve.
The Fed is expected to raise its benchmark rate for the first time since 2006, meaning mortgage rate hikes are likely to follow. Small mortgage-rate increases and, by extension, incrementally higher monthly mortgage payments, usually won't undermine sales because buyers aren't sensitive to small payment changes.
Mortgage rates, still at historic lows, have already baked in an expected rate increase of 25 basis points, according to PwC Real Estate Advisory Leader Mitch Roschelle. The National Association of Home Builders Chief Economist David Crowe agrees, adding that the housing market could even digest a cumulative 50 basis point hike by the end of 2016.
The real stress in the housing market is coming from somewhere else: labor shortages.
Read the court decisionRead the full story...Reprinted courtesy of
Rani Molla, BloombergGadfly
Worker’s Compensation Exclusivity Rule Gets “Trumped” by Indemnity Provision
October 27, 2016 —
Garret Murai – California Construction Law BlogSorry, I couldn’t help myself with the title.
The next case, Aluma Systems Concrete Construction of California v. Nibbi Bros., Inc., California Court of Appeals for the First District, Case No. A145734 (August 16, 2016), discusses the interplay between indemnity provisions and the worker’s compensation exclusivity rule.
The worker’s compensation exclusivity rule generally provides that worker’s compensation insurance is the exclusive remedy of employees for injuries or death arising out of the course and scope of their employment.
In the Aluma case, the California Court of Appeals, addressed what happens when a subcontractor’s employees are injured on a project, sue the general contractor, and the general contractor, pursuant to an indemnity provision in its subcontract, tenders the claim to the subcontractor whose worker’s compensation insurance has already paid the employees.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Windows and Lawsuits Fly at W Hotel
July 05, 2011 —
CDJ STAFFAn Austin, Texas lawyer has filed a lawsuit against Starwood Hotels and Resorts, the operator of the W Hotel Austin, after two people were struck by glass which fell from the hotel’s balconies. YNN in Austin reports that the hotel has been closed indefinitely as construction workers removed panels. An additional three panels fell before work started. Randy Howry, the lawyer representing the injured parties, notes that in May glass falling from the W Hotel in Atlanta killed one woman and injured another. “Seventeen days pass and we put them on notice, our clients have put them on notice, yet nothing has been done an only after the glass fell yesterday did they do something about it,” YNN quotes Howry.
The hotel released a statement that they will be replacing all of the balcony glass to ensure safety for their guests and the general public. They relocated all hotel guests and coordinated with Austin officials to close adjacent sidewalks and roads. The statement identifies the firms involved with the design and construction of the balconies.
Read the full story …
Read the court decisionRead the full story...Reprinted courtesy of
So a Lawsuit Is on the Horizon…
August 10, 2021 —
Sean Donoghue - Construction ExecutiveAs certain as death and taxes, documents will need to be exchanged in the event of a lawsuit. Here is what to expect and a few tips for reducing costs and protecting the case.
What Needs to Be Produced?
Discovery is broad, but proportional to the needs (i.e., usually the dollar value) of the case. Cost reports, bid back up and scheduling information are often at the heart of damages issues in construction disputes. Thus, while it will depend on the nature of the dispute, these items will generally need to be produced.
It is no secret that electronically stored information (ESI) can be a big part of discovery in litigation, particularly in a document intensive industry like construction. In addition to electronically stored project files, expect that the inboxes of employees who are close to the dispute will need to be searched. How many will depend on the size of the dispute and the number of players involved. Hard-drives and text messages of those employees may also be discoverable.
Reprinted courtesy of
Sean Donoghue, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Donoghue may be contacted at
sdonoghue@eckertseamans.com