Shifting Fees and Costs in Nevada Construction Defect Cases
November 26, 2014 —
Casey J. Quinn - Newmeyer & Dillion LLPIn Nevada, homeowners who sue a builder for residential constructional defects may recover attorneys’ fees and costs caused by the defect. Many times, the request for attorneys’ fees can outpace the size of the actual claim for defects. However, Nevada provides builders with two ways to potentially shift the right to recover attorneys’ fees and costs away from the homeowner and to the builder.
The first arises during the Nevada Revised Statutes (NRS) Chapter 40 process (Nevada’s Right to Repair law). After a builder receives notice of construction defects, it is required to provide the claimant with a written response to each defect, which may include a proposal for monetary compensation (including contribution from a subcontractor, supplier, or design professional). See NRS 40.6472. If a claimant unreasonably rejects a reasonable written offer of settlement included in the response and decides to commence litigation, the court may deny the claimant’s attorneys’ fees and costs and award attorneys’ fees and costs to the builder. See NRS 40.650. Thus, by including a reasonable offer of monetary compensation in a Chapter 40 response, a builder could possibly avoid paying any fees and costs and even recover its own fees in defending against the claim.
A second method for shifting fees and costs is through a written offer of judgment (OOJ). See NRS 17.115 and NRCP 68. Not limited solely to construction defect matters, an OOJ is a useful tool in all kinds of litigation. OOJs are designed to facilitate and encourage pre-trial settlement by incentivizing parties to make reasonable settlement offers that—when unreasonably rejected—have the consequence of shifting the right to recover attorneys’ fees. Basically, when a party rejects an OOJ and fails to obtain a more favorable judgment, the court cannot award any attorneys’ fees and costs to the rejecting party and may award attorneys’ fees incurred from the date of the offer to the entry of judgment, as well as all reasonable costs, to the party who made the offer. In a recent decision, the Nevada Supreme Court affirmed that when a homeowner rejects an OOJ and fails to obtain a more favorable judgment, it can wipe out that homeowner’s right to Chapter 40 fees and costs. See Gunderson, et al. v. D.R. Horton, 130 Nev. Adv. Op. 9 (Feb. 27, 2014). In other words, “While NRS Chapter 40 permits an award of reasonable attorney fees proximately caused by a construction defect, it does not guarantee it.” Id.
Because of the potentially harsh consequences of rejecting an OOJ, there are specific requirements that must be met to trigger them. An offer of judgment must be made in writing, can be made at any time at least 10 days before trial, and is irrevocable for 10 days with no provision for withdrawal before the 10 days expire. See Nava v. Second Judicial Dist. Court, 118 Nev. 396, 46 P.3d 60 (2002). A party may make successive offers of judgment, but the most recent offer extinguishes previous offers and is controlling for determining the date from which attorneys’ fees may be awarded. See Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006).
In Beattie v. Thomas, 99 Nev. 579, 668 P.2d 268, 274 (1983), the Nevada Supreme Court explained that the purpose of OOJs are not to cause plaintiffs to unfairly forego legitimate claims. However, when a valid offer of judgment is made, the offer is rejected, and the party rejecting the offer fails to obtain a more favorable judgment, a court must evaluate whether the plaintiff's claim was brought in good faith; whether the offer of judgment was reasonable and in good faith in both its timing and amount; whether the plaintiff's decision to reject the offer and proceed to trial was grossly unreasonable or in bad faith; and whether the fees sought by the offer are reasonable and justified. “After weighing the foregoing factors, the district judge may, where warranted, award up to the full amount of fees requested.” Id.
It is worth noting that in Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006), the Nevada Supreme Court held that when a party rejects a reasonable OOJ and is foreclosed from recovering fees and costs, the party is likewise foreclosed from an award of fees and costs under Chapter 40. This means that even if a builder fails to include a monetary settlement offer as part of a Chapter 40 response, it may still avoid paying the claimant’s fees and costs with a reasonable and timely OOJ.
Finally, it is important to remember that OOJs are a powerful tool that can cut both ways. If an OOJ is not reasonable and timely, or if it fails to contemplate all the potential recovery of an offeree, the OOJ may have no effect on the outcome of a case. Moreover, if a party rejects an OOJ and fails to obtain a more favorable judgment, that party could end up paying the offeror’s costs and attorney’s fees incurred from the date of the offer. Given this powerful impact, OOJs should be an integral part of pre-litigation planning and overall litigation strategy.
About the Author
Casey J. Quinn is an associate in the Las Vegas office of
Newmeyer & Dillion LLP. His practice focuses on complex commercial, construction, and insurance litigation and appellate work. Casey can be reached by email at Casey.Quinn@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Judge Gives Cintra Bid Protest of $9B Md. P3 Project Award New Life
March 21, 2022 —
Jim Parsons - Engineering News-RecordThe Maryland Dept. of Transportation will have to reconsider a protest lodged by the losing bidder for the initial phase of its $9-billion Express Lanes project, according to a Feb. 17 state circuit court judge's ruing. The decision likely stalls the state's ambitious plan to add capacity along portions of the I-495/Beltway and I-270 west of Washington, DC, using a progressive public-partnership.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Appellate Court Finds Appraisers Limited to Determining Amount of Loss
April 25, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Hawaii Intermediate Court of Appeals determined that appraisers cannot decide what amount is owed by the insurer after loss, but are limited to finding the amount of the loss. Krafchon v. Dongbu Ins. Co., Ltd., 2023 Haw. App. LEXIS 43 (Haw. Ct. App. Feb. 17, 2023).
The insureds owned three structures on the property on Maui: the Villa; the Cottage; and the Garage. The three structures were insured under homeowners and dwelling fire policies issued by Dongbu. When the structures were damaged by wildfire, Dongbu tendered over $300,000 under a reservation of rights, pending preparation of a final settlement. There was disagreement over the total amount of the loss.
The insureds invoked the appraisal provision of the policies. When Dongbu failed to appoint an appraiser, the insureds sued. The trial court granted the insureds' motion to compel appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hawaii Federal District Court Denies Title Insurer's Motion for Summary Judgment
February 01, 2022 —
Tred R. Eyerly - Insurance Law HawaiiIn a rare title insurance dispute before the federal district court in Hawaii, the court denied the insurer's motion for summary judgment while granting the insured's motion for summary judgment. First Am. Title Ins. Co. v. GS Industries, LLC, 2021 U.S. Dist. LEXIS 240601 (D. Haw. Dec. 16, 2021).
GS Industries, LLC took ownership of a parcel of real property located fronting Waipa Lane in Honolulu. The property used four buildings and a parking area for 50 cars. GS obtained a title insurance policy from First American. The policy insured GS' fee simple interest in the property in the amount of $3,500,000. The policy insured GS "against loss or damage, not exceeding $3,500,000, sustained or incurred by GS by reason of . . . not right of access to and from the land,." The policy did not identify any issues with access to the property and did not define "access."
A portion of Waipa Lane was owned by the City and County of Honolulu. Parcel 86 and Parcel 91 on Waipa Lane were privately owned. (Private Waipa Lane Parcels). Vehicular access to (ingress) and from (egress) the property was via Waipa Lane. Ingress was made via the publicly owned portion of Waipa Lane. Vehicular egress was made via the Private Waipa Lane Parcels. The City of Honolulu maintained the Private Waipa Lane Parcels and considered them to be pubic. None of the owners of Parcels 86 or 91 notified GS of their intent to block the use of Waipa Lane.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
ACS Obtains Overwhelming Jury Trial Victory for General Contractor Client
March 28, 2022 —
Scott R. Sleight - Ahlers Cressman & Sleight PLLCACS is pleased to share news of our recent $19.2 million victory for a general contractor client after a lengthy virtual jury trial involving the Nexus condominium project in downtown Seattle. On Tuesday March 22, 2022, ACS obtained a jury verdict awarding significant damages to our general contractor client and denying nearly all damages claimed against our client by the project owner. The 28-day jury trial commenced via Zoom on January 24 and involved testimony from more than two dozen witnesses on more than 185 discrete change issues and subcontractor pass-through claims as well as counterclaims from the owner for liquidated damages and other damages. Amazingly, after only two days of deliberating the jury reached a verdict resolving all claims overwhelmingly in favor of our general contractor client.
Our client was awarded $19.5 million on its claims totaling $20.6 million and largely defeated the owner’s counterclaims of $4.3 million, with the jury awarding only $318,000 to the owner. This results in a net judgment of $19.2 million in favor of our client. The ACS team, along with the client, worked incredibly hard on this case. The team includes lawyers Scott Sleight, Saki Yamada, Kristina Southwell, Cam Sheldon and paralegals Christina Granquist, Cydney Fermstad, Auzree Hightower, Amy Capell, Samina Helsley and Bernadette Bresee.
Read the court decisionRead the full story...Reprinted courtesy of
Scott R. Sleight, Ahlers Cressman & Sleight PLLCMr. Sleight may be contacted at
scott.sleight@acslawyers.com
Real Estate & Construction News Round-Up (11/03/21)
December 06, 2021 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogAmenity-rich buildings become a key focus in enticing employees back into the office, supply chain links are strained by a lack of storage capacity in warehouses and port areas, green lease signings are on the uptick, and more.
- In an effort to draw employees back into the office and retain talent in a tight labor market, businesses are spending more than ever on upscale workspaces, paying high rents for modern, amenity-rich buildings. (Peter Grant, The Wall Street Journal)
- As sustainability and ESG factors become increasingly important, net-zero carbon commitments are emerging as the next big “must-have” for commercial real estate owners, as more than 100 businesses and organizations have signed on to the World Green Building Council’s Net Zero Carbon Buildings Commitment, which seeks to decarbonize the buildings sector by 2050 and get halfway there by 2030. (Elsa Wenzel, GreenBiz)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Compliance Doesn’t Pay: Compliance Evidence Inadmissible in Strict Liability Actions
February 05, 2024 —
Kyle Rice - The Subrogation StrategistIn Sullivan v. Werner Co., No. 18 EAP 2022, 2023 Pa. LEXIS 1715 (Dec. 22, 2023), the Supreme Court of Pennsylvania (Supreme Court) clarified that in light of its decision in Tincher v. Omega Flex, Inc., 628 Pa. 296 (2014), evidence that a product complied with industry standards is inadmissible in an action involving strict product liability.
In Tincher, the Supreme Court overruled prior case law and reaffirmed that Pennsylvania is a Second Restatement Jurisdiction. As stated in Sullivan, discussing Tincher, under the Restatement (Second) of Torts § 402A, a “seller of a product has a duty to provide a product that is free from ‘a defective condition unreasonably dangerous to the consumer or [the consumer’s] property.’ To prove breach of this duty, a ‘plaintiff must prove that a seller (manufacturer or distributor) placed on the market a product in a “defective condition.””
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com
Five Issues to Consider in Government Contracting (Or Any Contracting!)
September 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe appeal of Appeals of – Konecranes Nuclear Equipment & Services, LLC, ASBCA 62797, 2024 WL 2698011 (May 7, 2024) raises interesting, but important, issues that should be considered. In this case, the government (in a supply contract) procured four portal cranes from the claimant. After an initial test of one of the cranes failed, the government refused to accept delivery even after the issue was addressed by the claimant. The government did not accept the manner in which the claimant addressed the issue and would only accept cranes if the claimant employed “an unnecessary alternative solution [that] caused further delay and increased [claimant’s] costs.” On appeal, it was determined the government’s decision to delay delivery based on its demand for the alternative solution was not justified, i.e., constituted a breach of contract. Below are five issues of consideration in government contracting, or, for that matter, any contracting.
Issue #1- Patently Ambiguous Specifications
The government argued that the specifications were patently ambiguous and because the claimant failed to inquire regarding the ambiguous specifications prior to performance, its interpretation of the ambiguous specifications should govern. The contractor countered that the specifications were unambiguous and it met the specifications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com