Be Careful How You Terminate: Terminating for Convenience May Limit Your Future Rights
January 19, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLC BlogMany construction contracts contain a termination clause that allows a contractor to be terminated either for convenience or for cause. Termination for convenience and termination for cause clauses have been discussed previously on the blog
here,
here and
here. The distinction between a termination for convenience or for cause is an important one.
If a contractor is terminated for convenience, the rights of the party who has terminated the contractor for convenience could be limited in the future. This is specifically true as to any defects in the terminated contractor’s work that are discovered after the termination for convenience.
This issue was addressed in an Oregon Court of Appeals case where a general contractor attempted to recover costs incurred in correcting a terminated subcontractor’s work after the subcontractor was terminated for convenience. Shelter Prods. v. Steel Wood Constr., Inc., 257 Or. App 382 (2013). In that case, the subcontractor sued the general contractor for its termination expenses. The general contractor asserted an offset/backcharge claim for damages incurred by the general contractor in correcting the subcontractor’s defective work. The general contractor had incurred the costs after it had terminated the subcontractor. The general contractor did not notify the subcontractor that its work was defective and did not give the subcontractor an opportunity to cure before the repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Excessive Corrosion Cause of Ohio State Fair Ride Accident
August 10, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.The manufacturer of the Fire Ball ride at the Ohio State Fair claims that excessive corrosion “led to the accident that killed a teenager and injured seven others…in July.”
According to a statement by KMG International, reported by ABC News, “Corrosion on the interior of the support beam reduced the beam's thickness, which led to the accident at the fair.” Furthermore, “The company said it conducted an investigation into the incident, which included a visit to the scene and a review of video footage of the incident. The company also conducted a metallurgical inspection of the ride.”
A U.S. Consumer Product Safety Commission (CPSC) spokesperson said “it is aware of 22 deaths associated with amusement attractions since 2010, including Wednesday's incident, but excluding water park and work-related fatalities.”
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Supreme Court Confirms a Prevailing Homeowner Can Recover Fees on Implied Warranty Claims
August 30, 2017 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogOn August 9th, in Sirrah Enterprises, L.L.C. v. Wunderlich, the Arizona Supreme Court settled the question about recovery of attorneys’ fees after prevailing on implied warranty claims against a residential contractor. The simple answer is, yes, a homeowner who prevails on the merits can recover the fees they spent to prove that shoddy construction breached the implied warranty of workmanship and habitability. Why? Because, as Justice Timmer articulated, “[t]he implied warranty is a contract term.” Although implied, the warranty is legally part of the written agreement in which “a residential builder warrants that its work is performed in a workmanlike manner and that the structure is habitable.”
In other words, a claim based on the implied warranty not only arises out of the contract, the claim is actually based on a contract term. Since, in A.R.S. § 12-341.01, Arizona law provides for prevailing parties to recover their fees on claims “arising out of contract” and because the implied warranty is now viewed by the courts as a contract term, homeowners can recover their fees after successfully proving breach of the implied warranty.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr Erickson may be contacted at
rerickson@swlaw.com
Ohio Court Refuses to Annualize Multi-Year Policies’ Per Occurrence Limits
June 19, 2023 —
Patricia Santelle, Adam Berardi & Lynndon Groff - White and Williams LLPWhite and Williams recently obtained summary judgment against an insured on behalf of an insurer and a guarantor, establishing that two multi-year insurance policies provide per occurrence limits on a per policy rather than a per year basis, which shielded potential exposure by over $100 million.
The insured had previously sought and obtained coverage under two policies in connection with a single occurrence arising out of massive environmental contamination claims involving a large industrial site. The issue of whether the policies provide per occurrence limits on a policy term or annual basis was not resolved in this earlier litigation.
The first policy was effective for three years and provides per occurrence limits of $40 million. The second policy was effective for up to three years and provides per occurrence limits of $15 million.
Reprinted courtesy of
Patricia Santelle, White and Williams LLP,
Adam Berardi, White and Williams LLP and
Lynndon Groff, White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Berardi may be contacted at berardia@whiteandwilliams.com
Mr. Groff may be contacted at groffl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Eleventh Circuit Reverses Attorneys’ Fee Award to Performance Bond Sureties in Dispute with Contractor arising from Claim against Subcontractor Performance Bond
February 27, 2019 —
CDJ STAFFOn October 26, 2018, the United States Court of Appeals for the Eleventh Circuit (the “Eleventh Circuit”) issued a decision which reversed an award of prevailing party attorneys’ fees to performance bond sureties in their dispute with a contractor arising from the contractor’s claim against a subcontractor’s performance bond. Had the lower court’s decision been affirmed, the performance bond sureties would have been able to recover prevailing party attorneys’ fees against the contractor even though they were not parties to the underlying subcontract and the subcontract did not contain a prevailing party attorneys’ fee provision.
The underlying case is complicated and arose from the construction of Brickell CityCentre in Miami. Americaribe-Moriarty JV (the “Contractor”) asserted a claim against a performance bond procured by a defaulted subcontractor and issued by International Fidelity Insurance Company and Allegheny Casualty Company (collectively, the “Sureties”). The Sureties filed a declaratory judgment action against the Contractor in the United States District Court for the Southern District of Florida (the “District Court”), seeking a declaration that the Contractor failed to perfect its claim against the performance bond.
Reprinted courtesy of
Gary M. Stein, Peckar & Abramson and
K. Stefan Chin, Peckar & Abramson
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Chin may be contacted at kschin@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Turkey to Start Building 200,000 Homes in March, Erdogan Says
February 20, 2023 —
Taylan Bilgic - BloombergPresident Recep Tayyip Erdogan has announced that Turkey will begin constructing almost 200,000 homes as early as March in areas devastated by twin earthquakes that hit the southeast of the country two weeks ago.
Erdogan emphasized the severity of the earthquake’s impact, drawing parallels to historical events that wreaked havoc in Anatolia, the heartland of modern Turkey. “With faith, courage and patience, we have resisted numerous political and social upheavals for centuries, such as the Crusades and the Mongol invasions,” he said.
The construction of 199,739 new homes will begin in 11 provinces, including the hardest-hit Hatay and Kahramanmaras, Erdogan said. The death toll from the earthquakes has risen to 41,156 while over 114,000 people have been rescued from the rubble.
Read the court decisionRead the full story...Reprinted courtesy of
Taylan Bilgic, Bloomberg
Digitalizing the Hospital Design Requirements Process
April 02, 2019 —
Aarni Heiskanen - AEC BusinessDecisions made at the early stages of a hospital project can have a huge impact on its life cycle value. To make sure that a hospital will be a good investment, its future users should be involved in helping set out the design requirements. A Finnish team of experts wanted to see if they could improve the process and set up an experiment to see how it could be done digitally.
Currently, over one billion euros are budgeted to hospital construction and renovation in Finland. Globally, the sum is around US$400 billion. You would imagine that the design for such large investments would be very efficient from the start. Unfortunately, that is not the case.
During the design phase, doctors, specialists, nurses, and other stakeholders take part in workshops in which they express their needs and requirements. For a large hospital project, 40 to 100 workshops are the norm. The work is done with a variety of tools, with sticky notes being the predominant technique.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
U.S. Judge Says Wal-Mart Must Face Mexican-Bribe Claims
October 01, 2014 —
Jef Feeley – BloombergWal-Mart Stores Inc. (WMT) was ordered by a federal judge in Arkansas to face a pension fund’s claims the retailer defrauded shareholders by concealing corruption tied to bribes allegedly paid by officials of its Mexican unit.
U.S. District Judge Susan Hickey in Fayetteville rejected Wal-Mart’s bid to throw out the Michigan-based fund’s lawsuit accusing it of making misleading statements to regulators about claims it paid bribes to facilitate Mexican real-estate deals.
The world’s largest retailer has said it’s spent $439 million since 2012 in connection with investigations into allegations that employees paid bribes in Mexico, China, India and Brazil. Both U.S. and Mexican prosecutors have said they are probing whether executives of Wal-Mart’s Mexican unit were paying off local officials to clear the way for construction of new stores and warehouses.
Read the court decisionRead the full story...Reprinted courtesy of
Jef Feeley, BloombergMr. Feeley may be contacted at
jfeeley@bloomberg.net