Differing Site Conditions Produce Differing Challenges
February 18, 2019 —
Sarah E. Carson - Smith CurrieThe saying “The best laid plans of mice and men often go awry” can too often apply in the construction industry. A contractor may receive a description of site conditions that is ultimately found flawed or misleading. The costs associated with addressing these surprise conditions often fall on the contractor to pay. The following article details proactive steps to avoid costly obstacles that may cause a project’s success to go awry.
What are Differing Site Conditions?
There are generally two recognized types of differing site conditions. The first, often referred to as a “Type I Changed Condition,” exists when a specification in the conditions indicated in the contract documents varies from what is represented. The second category, generally referred to as a “Type II Changed Condition,” is a variance so unusual in its nature that it materially differs from conditions ordinarily encountered in performing the type of work called for in the geographic area where the project is located.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah E. Carson, Smith CurrieMs. Carson may be contacted at
secarson@smithcurrie.com
Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Covenant of Good Faith and Fair Dealing Applied to Pass-Through Agreements
June 19, 2023 —
Scott D. Cessar - Construction ExecutivePass-through claims are claims by a party that has suffered damages but does not have a contractual relationship with the entity that caused the damages. In the construction industry, subcontractors commonly have claims for additional costs based on actions or inactions by the owner. However, since the subcontractor is not in privity of contract with the owner, it has no direct cause of action against the owner other than, perhaps, on a nongovernment project, a lien claim. In such cases, subcontractors may seek to pass the claim through the general contractor, who is in privity with the owner, to the owner.
Indeed, many construction contracts require the subcontractor, in such cases of owner-caused damages, to pass the claim through the general contractor to the owner. And since the harm visited on a subcontractor by the owner usually also affected the general contractor, the subcontractor’s claim is packaged together with the general contractor’s claim, which is usually greater, for presentation to the owner and, if not resolved, litigation with the owner.
Reprinted courtesy of
Scott D. Cessar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 09, 2011 —
CDJ STAFFConstruction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
What You Don’t Know About Construction Law Can Hurt Your Engineering Firm (Law Note)
January 28, 2019 —
Melissa Dewey Brumback - Construction Law in North CarolinaWelcome to a new year! By now, you’ve eaten the last of the Christmas cookies, opened all of your presents, and rung in 2019. Back to business, right? The new year is always a good time to remind your employees, and yourself, that there are no shortcuts on the success train.
Sure, you can sometimes skate by for awhile, but karma has a way of catching up with you.
One thing to keep in mind is that if you practice in multiple states: be sure you are well aware of the rules and regulations concerning your license in each state. Each state does things a little differently, and what may be perfectly acceptable in one state may not be in another state.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Weyerhaeuser Leaving Home Building Business
November 13, 2013 —
CDJ STAFFThe Washington-based timber giant, Weyerhaeuser, has announced that has sold off its homebuilding business. The division went by the name of WRECO (Weyerhaeuser Real Estate Company) and comprised five home builders, Maracay Homes, Pardee Homes, Quadrant Homes, Trendmaker Homes, and Winchester Homes. The division was bought by TRI Pointe Homes for about $2.7 billion of which $700 million was paid in cash.
Weyerhaeuser intends to focus on their core business of timber products.
Read the court decisionRead the full story...Reprinted courtesy of
Court Rules that Collapse Coverage for Damage Caused “Only By” Specified Perils Violates Efficient Proximate Cause Rule and is Unenforceable
January 26, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Vardanyan v. Amco Ins. Co. (No. F069953, filed 12/11/15) a California appeals court held that policy wording that the collapse coverage for damage “caused only by” certain specified perils did not mean “solely” by those specified perils, but that coverage may nonetheless apply even if excluded causes contributed to the loss, under the Insurance Code section 530 and the efficient proximate cause rule.
In Vardanyan, the insured made a claim for water damage from unknown origin to a rental house. An engineer concluded that the various sources of moisture—roof leaks, gutters and downspouts that did not channel the water away from the house, a faucet spraying water on the exterior of the house, leaking toilet and bathtub, and humidity—contributed to the damage to the house, along with poor construction, termite damage and decay.
The insurer denied coverage citing multiple policy exclusions, including damage caused by seepage or leakage of water from a plumbing system; deterioration; mold, wet or dry rot; settling of foundations, walls or floors; earth movement; water damage; neglect; weather conditions; acts or decisions of any person; and faulty or defective design, workmanship, repair, construction, or maintenance. The insured retained a public adjuster who disagreed, in particular citing the policy’s “Other Coverage 9” coverage for collapse of a building or part of a building “caused only by one or more” of a list of perils, including hidden decay, hidden insect damage, and weight of contents, equipment, or people.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com