No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Amazon Can be Held Strictly Liable as a Product Seller in New Jersey
August 07, 2022 —
Michael L. DeBona - The Subrogation StrategistOn June 29, 2022, in N.J. Mfrs. Ins. Grp. a/s/o Angela Sigismondi v. Amazon.com, Inc., 2022 U.S. Dist. LEXIS 115826 (Sigismondi), the United States District Court for the District of New Jersey held that Amazon.com, Inc. (Amazon) is a “seller” under New Jersey’s product liability statute and can thus face strict liability for damages caused by products sold on its platform. Although the analysis is state-specific, Sigismondi may serve as an important decision for allowing product defect claims to proceed against Amazon when so often the third-party vendor that lists the product is unlocatable, insolvent, or not subject to the jurisdiction of United States courts.
In recent years, Amazon has been fighting product liability claims across the country. Amazon argues it is not a “seller” under states’ product liability laws but is merely an online marketplace that facilitates the sale of products by third-party vendors. What constitutes a “seller” in a particular state must be evaluated state-by-state, but various courts have accepted Amazon’s argument that it is not a “seller.” These decisions are based on Amazon’s level of control in the product sale and often focus on a finding that Amazon did not convey possession of the product or transfer its title.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and WilliamsMr. DeBona may be contacted at
debonam@whiteandwilliams.com
Exponential Acceleration—Interview with Anders Hvid
December 01, 2017 —
Aarni Heiskanen - AEC BusinessAnders Hvid is a Danish consultant, speaker, and author. He talks about digital disruption, exponential acceleration, and paradigm shifts that are taking place in a world that is moving from local and linear into global and exponential.
“I have a background in social studies. My interest is in humans, and systems in which they work together. I’ve always had a deep fascination with technology and how it influences our society, our jobs, our democracies, and systems,” Anders says. He visited Singularity University back in 2010, and that experience made a lasting impression on him. “It freaked me out, to be honest, and it opened my eyes to how important technology is.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Federal Judge Rips Shady Procurement Practices at DRPA
October 07, 2016 —
Wally Zimolong – Supplemental ConditionsIn an opinion overturning a $17,000,000 bridge painting contract for the Commodore Barry Bridge, a United States Federal Judge called the procurement practices of the Delaware River Port Authority “a black box . . . obscure and unexplained, and lacking any indicia of transparency or the hallmarks of a deliberative process.”
The case involved lead paint remediation and repainting of the Pennsylvania span of the Commodore Barry. Seven contractors submitted bids. Alpha Painting was the apparent low bidder. Corcon was the second low bidder. Corcon was also the contractor that was perform the painting work on the New Jersey span of the bridge. Like most agencies engaged in public bidding, the DRPA requires contracts to be awarded to the lowest responsible and responsive bidder.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Negligent Failure to Respond to Settlement Offer Is Not Bad Faith
May 03, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit found that the insurer's negligent failure to respond to a settlement offer did not constitute bad faith. McDaniel v. Gov't Employees Ins. Co., 2017 U.S. App. LEXIS 4029 (9th Cir. March 7, 2017).
McDaniel was the assignee of claims against GEICO assigned by the insured after settling a wrongful death suit. McDaniel alleged that GEICO unreasonably refused to accept a $100,000 policy limits offer. The case went to trial and a jury awarded McDaniel over $3 million against the insured.
On August 7, 2009, McDaniel's attorney Steven Nichols extended a $100,000 policy limits settlement offer with a fifteen day acceptance deadline to GEICO's attorney Michael Griott. The parties subsequently agreed to extend the acceptance deadline to ten days following MacDaniel's service of responses to outstanding interrogatories, which Nichols hand-delivered to Griott on August 27, 2009. On September 1, 2009, Griott emailed GEICO claims adjuster Aldin Buenaventura with a letter attachment indicating that Nichols had submitted the requested interrogatories and, in bold and underlined text, that "[o]ur response to Plaintiff's policy limits demand is due on or before September 11, 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Owners Should Serve Request for Sworn Statement of Account on Lienor
August 10, 2017 —
David Adelstein - Florida Construction Legal UpdatesWhen an owner receives a construction lien, an owner should serve the lienor with a Request for Sworn Statement of Account. The Request for Sworn Statement is authorized by Florida Statute s. 713.16(2) and should be in the following form:
REQUEST FOR SWORN STATEMENT OF ACCOUNT
WARNING: YOUR FAILURE TO FURNISH THE REQUESTED STATEMENT, SIGNED UNDER OATH, WITHIN 30 DAYS OR THE FURNISHING OF A FALSE STATEMENT WILL RESULT IN THE LOSS OF YOUR LIEN.
To: (Lienor’s name and address)
The undersigned hereby demands a written statement under oath of his or her account showing the nature of the labor or services performed and to be performed, if any, the materials furnished, the materials to be furnished, if known, the amount paid on account to date, the amount due, and the amount to become due, if known, as of the date of the statement for the improvement of real property identified as (property description) .
(name of contractor)
(name of the lienor’s customer, as set forth in the lienor’s Notice to Owner, if such notice has been served)
(signature and address of owner)
(date of request for sworn statement of account)
From both an owner and lienor’s perspective, the bolded, capitalized language is key. It states that if the lienor fails to respond under oath within 30 days, it will LOSE its lien. That is a very punitive measure for a lienor’s failure to respond, meaning a lienor should absolutely respond, no questions asked. Plus, a lienor’s response to a Request for Sworn Statement of Account is not a burdensome ordeal.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Summary Judgment Granted to Insurer for Hurricane Damage
January 24, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment, contending there was no coverage for hurricane damage, was granted. Laurence v. Liberty Ins. Corp., 2021 U.S. Dist. LEXIS 227807 (S.D. Texas Nov. 29, 2021).
When Hurricane Harvey hit, Mike Laurence held a homeowner's policy from Liberty Insurance Corporation and a contractor policy for his business, Pride Plumbing, Inc., issued by State Farm Lloyds. Laurence's property suffered water damage during the storm. State Farm investigated and concluded that all but a small amount, within the policy's deductible, was from flood damage and excluded. Laurence sued.
The property covered by the State Farm policy included Laurence's home, Pride Plumbing's office and two sheds. Pride Pluming did not own or lease any of the buildings on the property. Laurence testified in his deposition that the only damage to his property not caused by flood water was to three buildings from fallen tree limbs and equipment from his business.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Green Energy Can Complicate Real Estate Foreclosures
November 30, 2016 —
Bob L. Olson – Snell & Wilmer Real Estate Litigation BlogA quick drive through almost any newer residential community in the Southwest will show that a lot of residents are embracing “Green Energy” or renewable energy by placing solar panels on their properties. While most people would agree that increasing the use of alternative energy is socially responsible, there are a number of real estate investors that may view it as an opportunity to make additional profits by purchasing distressed properties with solar panels and then reselling those properties for more than they would be worth without solar panels. The theory is relatively straight forward as many believe that foreclosure of a deed of trust that was recorded before the solar panels were installed would extinguish any liens in favor of the vendor that sold or financed the sale of the solar panels. After all, it is generally held that “a valid foreclosure of a mortgage terminates all interest in the foreclosed real estate that are junior to the mortgage being foreclosed.” See SFR Investments Pool 1, LLC v. U.S. Bank, N.A., 130 Nev. Adv. Op. 75, 334 P.3d 408, 412 (2014) (quoting Restatement (Third) of Property, Mortgages §7.1 (1997)).
NOT SO FAST! While the general rule is that foreclosure of a senior lien terminates junior liens, most purveyors of solar panels do not encumber the property with mortgages or deeds of trust to secure payment of amounts they are owed. Rather, they typically either lease the solar panels to the property owner or secure repayment of the purchase price of the solar panels with a fixture filing under the Uniform Commercial Code (the “UCC”).
Read the court decisionRead the full story...Reprinted courtesy of
Bob L. Olson, Snell & WilmerMr. Olson may be contacted at
bolson@swlaw.com