Construction Litigation Roundup: “The Jury Is Still Out”
October 30, 2023 —
Daniel Lund III - Lexology“The Seventh Amendment guarantees the right to a trial by jury for a legal claim in a civil action.” So, isn’t the law, well, the law?
Well, perhaps.
Some axioms to remember in contracting are that parties are typically able to agree in a contract to anything that is lawful, and that all such lawful agreements essentially become the “law” between the parties. It is on these principles that courts issue jurisprudence which becomes binding on future litigants – for example, concerning waiver of any right to trial by jury.
Hence, when a second-tier subcontractor on a federal project sought a jury for a lawsuit it had against a general contractor’s sureties, the sub was successfully rebuffed by the sureties based upon a waiver to trial by jury contained in the relevant subcontract. The court noted various matters to be considered in connection with the generally enforceable jury waiver – including the conspicuousness of the waiver (and, therefore, whether the subcontractor “knowingly” agreed to the waiver), as well as the relative bargaining power of the parties to the agreement (here, the sub was self-proclaimed to be a “leader in the construction contracting field”) – and affirmed the legality of the waiver.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Detroit Craftsmen Sift House Rubble in Quest for Treasured Wood
March 19, 2015 —
Chris Christoff and Alexandra Mondalek – Bloomberg(Bloomberg) -- Detroit’s 70,000 abandoned homes are proving to be a trove for entrepreneurs who recycle century-old lumber, glass and brick into everything from terrariums to $4,500 guitars.
“It’s like a treasure hunt,” said Craig Varterian, executive director of Reclaim Detroit, a nonprofit group that’s stripped and sold materials from almost 70 demolished homes. Floorboards and joists of early 20th century maple, walnut, hickory, fir and even chestnut are prized for their density and fine grain.
As Detroit ramps up demolitions of vacant dwellings, Mayor Mike Duggan plans a reclamation center in a city-owned building to keep tons of rubble out of landfills and create jobs and merchandise. Recycling would become a centerpiece of the city’s blight-removal effort, which is struggling to maintain funding.
Reprinted courtesy of
Chris Christoff, Bloomberg and
Alexandra Mondalek, Bloomberg
Mr. Christoff may be contacted at cchristoff@bloomberg.net
Ms. Mondalek may be contacted at amondalek@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Don MacGregor of Bert L. Howe & Associates Awarded Silver Star Award at WCC Construction Defect Seminar
May 24, 2018 —
CDJ STAFFThe staff of the Construction Defect Journal would like to extend their congratulations to Don MacGregor of Bert L. Howe & Associates, Inc., in recognition of his receipt of the Silver Star Award as “Best Expert” at the 25th Anniversary of the West Coast Casualty Construction Defect Seminar, hosted at the Disneyland Resort Hotel, in Anaheim CA.
Recipients of the Silver Star Awards were nominated and voted on by their peers, colleagues, and the Construction Defect Community at large, as represented by the 25,000 members who received emails on the subject.
Along with “Best Expert,” recognition was also given to the best judge, mediator, plaintiff attorney, developer attorney, subcontractor attorney, coverage counsel, and insurance claims professional. Awards were handed out last Thursday during a special ceremony at this year’s Seminar.
To Don, and all the worthy awardees, congratulations again!
Read the court decisionRead the full story...Reprinted courtesy of
Franchisors Should Consider Signing a Conditional Lease Assignment Rather Than a Franchisee’s Lease
November 17, 2016 —
Richard H. Herold – Real Estate Litigation BlogIn Franchise & High Properties, LLC v. Happy’s Franchise, LLC, a 2015 decision issued by the Court of Appeals in Michigan, the franchisor, Happy’s Pizza Franchise, LLC, signed a five-year lease for the commercial space to be occupied by its franchisee, Happy’s Pizza #19, Inc. The franchisor did so to secure a right of first refusal to purchase the property and to enforce the franchise agreement to have the lease assigned to the franchisor if the franchisee defaulted.
The issue in the case was whether the term “tenant” referred solely to Happy’s Pizza #19 or whether it also included Happy’s Franchise as a co-tenant. “Tenant” was defined as follows: “Happy’s Pizza #19, Inc., 29102 Telegraph Road, Suite 607, Southfield, MI 48034, the lessee, and Happy’s Pizza Franchise, LLC, a Michigan limited liability company (hereinafter referred to as `Franchisor’), hereinafter designated as the Tenant.”
Read the court decisionRead the full story...Reprinted courtesy of
Richard H. Herold, Real Estate Litigation BlogMr. Herold may be contacted at
rherold@swlaw.com
Construction Termination Issues for the Architect and Engineer: Part 1– Introduction to the Series
July 24, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaEarlier this year, I was asked to talk to other construction lawyers on the topic of termination. My first question was– whose termination are we talking about here– the architect / engineer? The contractor? Is someone wanting to “fire” the owner? The answer, as it turns out, is — yes. That is, yes, any and all of the above termination topics were on the table.
As you may have suspected, even the threat of a termination is bad, bad news. It is the “nuclear option” for a construction project. Everyone risks getting harmed. As the design professional administering a contract, you run a risk of being dragged into litigation no matter what you do. So, how should you proceed? Carefully.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
The Anatomy of a Construction Dispute- The Claim
December 02, 2015 —
Christopher G. Hill – Construction Law MusingsA new year brings with it promise and challenges. The promise is a relatively clean slate and the thought that 2015 will be a great year for construction professionals and those that assist them. The challenges come from the almost inevitable issues that can arise on a construction site with its many moving parts and enough potential pitfalls to make even the most optimistic construction attorney, contractor, subcontractor or supplier think that Murphy was an optimist.
In order to assist with the potential challenges, this post will be the first in a series of “musings” on the best way to handle a payment dispute arising from a construction contract. This week’s post will discuss what the first steps should be once a payment dispute or claim arises. We’ll assume that you, as a construction contractor, have taken early advantage of the services of a construction lawyer and have carefully reviewed your contract for issues before signing that contract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
ASCE Statement on Hurricane Milton and Environmental Threats
October 15, 2024 —
Feniosky Peña-Mora, P.E., President - American Society of Civil EngineersWASHINGTON, DC. – On the heels of the tragic damage caused by Hurricane Helene throughout the Southeast, Floridians were struck by another major hurricane, Milton, less than two weeks later. Our hearts go out to those impacted again by this storm through property damage, lack of water access, power outages, or worse, loss of life, all before getting a chance to recover from Helene. Civil engineers are dedicated to protecting the public with projects that can lessen the impacts of these storms, and we are eager to help communities rebuild as quickly as possible following events like Milton and Helene.
Although we do not yet know the full scope of destruction caused by Hurricane Milton, severe weather, including compound flooding events, are increasing regularly and pose a great risk to our safety and economic vitality. While so many eyes are fixated on hurricanes impacting the Southeast, wildfires are burning across several western states, including the Elk Fire in Wyoming, the largest wildfire the Bighorn National Forest has experienced in more than a century, now spanning over 75,000 acres as the region is experiencing unusually hot and dry weather and strong winds that are helping this fire to spread rapidly. The climate impacts we are accustomed to – wildfires in the West and hurricanes in the Southeast – are getting stronger, and now environmental challenges are occurring in areas we wouldn't suspect, such as Hurricane Helene striking mountain communities in Western North Carolina that have been labeled as "climate safe-havens," and Texas dealing with annual winter storms.
ASCE is a leader in codes and standards development and has created an
easy-to-understand toolkit for legislators and the public to learn the benefits of these up-to-date standards and determine when and how to adopt them, making our built environment more resilient to natural catastrophes. ASCE's flagship standard,
ASCE/SEI 7-22, recently underwent the most significant update to its
flooding chapter to ensure structures following this standard are prepared for 500-year flood events.
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of Wisconsin Applies Pro Rata Allocation Based on Policy Limits to Co-Insurance Dispute
February 18, 2019 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Steadfast Insurance Company v. Greenwich Insurance Company, 2019 WL 323702 (Wis. Jan. 25, 2019), the Supreme Court of Wisconsin addressed the issue of contribution rights as among co-insurers.
Steadfast and Greenwich issued pollution liability policies to different entities that performed sewer-related services for the Milwaukee Metropolitan Sewerage District (MMSD) at different times. MMSD sought coverage under both policies in connection with underlying claims involving pollution-related loss. Both insurers agreed that MMSD qualified as an additional insured under their respective policies, but Greenwich took the position that its coverage was excess over the coverage afforded under the Steadfast policy, at least for defense purposes, and that as such, it had no defense obligation.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub LiebermanMr. Margolies may be contacted at
bmargolies@tlsslaw.com