Harmon Towers Duty to Defend Question Must Wait, Says Court
March 01, 2012 —
CDJ STAFFThe Harmon Towers project in Las Vegas was eventually halted short of the planned forty-seven stories after “it was determined that there was substantial defective construction, including defective installation of reinforcing steel throughout the Harmon.” The American Home Insurance Company and Lexington Insurance Company put forth a claim that they had no duty to defend Perini Construction, the builder of the defective Harmon Towers. Further, American Home seeks to recover the monies American reimbursed Perini. The United States District Court of Nevada ruled in the case of American Home Assurance Co. v. Perini Building on February 3, 2012.
The two insurance companies covered Perini and its subcontractors, Century Steel, Pacific Coast Steel, and Ceco Concrete Construction. Century Steel was the initial subcontractor for the reinforcing steel; they were later acquired by Pacific Coast Steel. In this current case, Perini Construction is the sole defendant.
Perini sought a dismissal of these claims, arguing that without the subcontractors joined to the case, “the Court cannot afford complete relief among existing parties.” The court rejected this claim, noting that the court can determine the duties of the insurance companies to Perini, which the court described as “separate and distinct from those of the subcontractors.” The subcontractors “have not claimed an interest in the subject matter of the action.” The court concluded that it could determine whether Perini was entitled or not to coverage without affecting the subcontractors. The court rejected Perini’s claim.
Perini also asked the court to abstain from the case, arguing that it was better heard in a state court. The court noted that several considerations cover whether a case is heard in state or federal courts. The court noted that if the case weighed heavily on state law, the state courts would be the obvious location. Further, if there were a parallel action in the state courts, “there is a presumption that the whole suit should be heard in state courts.” This is, however, no parallel state suit, although the court noted that Perini has “threatened” to do so.
However, the issue of who is to blame for the problems at Harmon Towers has not been resolved. The court concluded that until the “underlying action” was concluded, it was premature to consider the issues raised in this case while the earlier lawsuit was still in progress. The court denied Perini’s motion to dismiss the case. Given that the outcome of the earlier construction defect case may lead to further litigation in state court, the District Court granted Perini’s motion to abstain, but staying their judgment until the construction defect case is resolved.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
New-Home Sales in U.S. Unexpectedly Fall to Four-Month Low
January 07, 2015 —
Victoria Stilwell – BloombergPurchases of new U.S. homes unexpectedly declined in November to a four-month low, underscoring a lack of momentum this year in residential real estate.
Sales dropped 1.6 percent to a 438,000 annualized pace last month following a 445,000 rate in October that was weaker than previously estimated, Commerce Department figures showed today in Washington. The median estimate of 73 economists surveyed by Bloomberg called for a 460,000 pace in November.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Duty To Defend Construction Defect Case Affirmed, Duty to Indemnify Reversed In Part
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Eleventh Circuit affirmed the district court's finding of a duty to defend, but reversed, in part, the insurer's duty to indemnify. Carithers v. Mid-Continent Cas. Co., 2015 U.S. App. LEXIS 5540 (11th Cir. April 7, 2015).
After discovering a number of defects in their home, the Carithers sued their homebuilder, Cronk Duch Miller & Associates. Cronk Duch's insurer, Mid-Continent Casualty Company, refused to defend.The parties entered into a consent judgment for $90,000 in favor of the Carithers. Cronk Duch then assigned to the Carithers the right to collect the judgment from Mid-Continent.
The Carithers then sued Mid-Continent. Florida law applied. Mid-Continent has issued four policies to Cronk Duch from March 2005 to October 2008. The parties filed cross-motions for summary judgment on the duty to defend issue. The underlying complaint alleged that the defects could not have been discovered until 2010, after the last policy period. The district court rejected Mid-Continent's argument that property damage occurred when it was discovered or when it reasonably could have been discovered. Therefore, summary judgment on the duty to defend was granted to the Carithers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Mezzanine Financing
March 29, 2017 —
Tim Davis & Steven Coury - White and Williams LLPConstruction mezzanine lending is on the rise and more development deals are getting done with a capital stack that includes mezzanine debt in addition to the traditional components of sponsor equity and senior mortgage debt. Below are important issues and concepts to bear in mind when structuring the financing of a construction project that includes a mezzanine debt component.
Funding Sequence
Funding Sequence
When will the proceeds of the mezzanine loan be advanced? In some instances, the mezzanine loan proceeds will be advanced only after all of the borrower’s equity has been contributed to the construction of the project. In other instances, the borrower’s equity and the mezzanine loan proceeds go in either pari passu or simultaneously at another ratio. If the equity is not entirely contributed in advance, the mezzanine lender may require that the uncontributed equity be held by the mezzanine lender or held in a pledged account. The mezzanine lender may also further mitigate the risk of non-funding of the equity by requiring an equity funding guaranty (as discussed below).
Additionally, when will the mezzanine loan proceeds be advanced in relation to the senior mortgage loan proceeds? Will the entire mezzanine loan be advanced prior to any senior mortgage loan advance or will they be advanced pari passu? Depending on the business deal, the mezzanine loan agreement will need to reflect how and when the equity, the mezzanine debt, and the mortgage debt will be advanced.
Reprinted courtesy of
Tim Davis, White and Williams LLP and
Steven Coury, White and Williams LLP
Mr. Davis may be contacted at davist@whiteandwilliams.com
Mr. Coury may be contacted at courys@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Supreme Court: Breach of Contract Not Required to Prevail on Statutory Bad Faith Claim
June 06, 2018 —
Bethany L. Barrese - Saxe Doernberger & Vita, P.C.In USAA Texas Lloyds Company v. Menchaca, the Supreme Court of Texas clarified long-standing confusion regarding whether damages for bad faith are recoverable in the absence of a breach of contract under Texas law. The Menchaca case takes an in-depth dive into decades’ worth of Texas precedent and concludes that, under certain circumstances, an insured can recover policy benefits as damages for bad faith without finding that the insurer was in breach of contract.
The story of this case begins with Hurricane Ike in September 2008. Homeowner Gail Menchaca contacted her homeowner’s insurance company, USAA Texas Llloyds Company (“USAA”) to report that the storm had damaged her home. USAA sent an adjuster to investigate the claim, and USAA determined that although the policy covered some of the damage, no benefits would be paid under the policy because the repair estimate did not exceed the policy deductible. Five months later, at Ms. Menchaca’s request, another USAA adjuster inspected the property and reached the same conclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
blb@sdvlaw.com
HUD Homeownership Push to Heed Lessons From Crisis, Castro Says
January 14, 2015 —
Clea Benson – BloombergNow that regulators have fixed the worst abuses of the 2008 credit crisis, it’s time to start promoting homeownership again, according to the top U.S. housing official.
The Department of Housing and Urban Development will do its part, spending this year focusing on ways to help more Americans buy homes, HUD Secretary Julian Castro said today in a Washington speech outlining the agency’s priorities.
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson, BloombergMs. Benson may be contacted at
cbenson20@bloomberg.net
Gloria Gaynor Sues Contractor over Defective Deck Construction
October 22, 2013 —
CDJ STAFFGloria Gaynor, known for her 1978 disco hit, “I Will Survive” is suing the firm that renovated her second-floor deck, alleging that the work lead to water intrusion into her home. Ms. Gaynor also accuses the company of consumer fraud, alleging that Diaz Landscape Design & Tree Service LLC lacked registration as a home improvement contractor and failed to obtain a building permit for the structure.
Ms. Gaynor paid about $38,000 for the replacement of her deck and other renovations to her property in 2007. Subsequently, the singer noticed “ponding of water on the deck, water damage to wood sills and supports, and the formation of mold,” according to the lawsuit. Diaz Landscape attempted repairs, but “the problems persisted and continue to persist causing further damage.”
The lawsuit claims that the cost of replacing the defective deck construction would cost about $120,000.
Read the court decisionRead the full story...Reprinted courtesy of
Four Companies Sued in Pool Electrocution Case
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in April of this year, a seven-year old boy was electrocuted while swimming in his family’s pool in North Miami, Florida, according to CBS Miami. Now, the family is suing four companies in a wrongful death suit.
The complaint claims that the victim “was electrocuted due to a faulty pool light and electrical grounding and bonding on the pool’s lighting system.”
Pentair Water Pool and Spa, Inc., manufactured and designed the pool light. Florida Pool & Spa Center “provided periodic cleaning, maintenance and inspections of the pool,” while Gary B Electric and Construction Consultant is being sued for “improper bonding and grounding.” Also, Jorge Perez Enterprises Inspection Company is listed in the lawsuit since they conducted the inspection when the family purchased the home.
Read the court decisionRead the full story...Reprinted courtesy of