Government’s Termination of Contractor for Default for Failure-To-Make Progress
July 10, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhenever you elect to terminate the other party for cause or for default, you need to JUSTIFY the basis of the cause or default. The reason being is that a termination for default or cause is the harshest contractual remedy. This is why the other party will typically either (i) convert the termination for default into one for convenience, or (ii) if there is no termination for convenience provision in the contract, argue the terminating party breached the contract by terminating the contract without rightful justification.
The key is if you are going to terminate a party for cause of default, make sure you have memorialized the persuasive reasons for exercising the termination, and can otherwise reasonably support the justification. Do not, and I repeat, do not haphazardly exercise a termination for default and think you do not have to justify the basis for the termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
How California’s Construction Industry has dealt with the New Indemnity Law
October 22, 2014 —
Mark S. Himmelstein, Esq. - Newmeyer & DillionIt has been almost two years since the California legislature enacted changes to the state’s indemnity law affecting commercial construction contracts. Although we do not yet have any court opinions analyzing the new statutes, the attorneys at
Newmeyer & Dillion now have real world experience in negotiating such indemnity provisions. It is time to evaluate how the construction community has reacted to the changes. In this article, we examine the practical applications of the new law to various construction agreements.
Enacted on January 1, 2013, the new legislation was the latest in a series of efforts by subcontractors and their insurers to eliminate “Type I” indemnity clauses. Under a Type I provision, a subcontractor has a duty to indemnify the developer or general contractor for the negligence of the developer or general contractor or other subcontractors, in addition to the negligence of the subcontractor itself. In 2006, the law was changed to preclude Type I provisions regarding “For Sale” residential construction defect claims. At that time, there was no such restriction enacted for commercial construction contracts. However, since then, commercial subcontractors have been seeking similar legislation. Their efforts culminated in the 2013 revisions regarding commercial contracts.
Commercial Subcontracts
Pursuant to the new indemnity statute — Civil Code section 2782.05 — we have revised our clients’ commercial subcontracts to:
(a) Eliminate the requirement that the subcontractor indemnify the general contractor for the general contractor’s “active negligence;” and
(b) Include the subcontractor’s options for defending claims for which they have an indemnity obligation.
Many subcontractors have responded: “Hey, wait a minute, the new legislation eliminated Type I indemnity so you (general contractor) cannot still require any indemnification for the general contractor’s negligence”. Well, that might be the rumor in subcontractor circles, but the new statute does not eliminate indemnity for the general contractor’s passive fault. In addition, the Civil Code lists 13 instances where the new indemnity restrictions do not apply.
Residential Subcontracts
The legislature did not make anyone’s job easier by drafting a different indemnity provision for commercial subcontracts than for residential subcontracts. In fact, the residential and commercial statutes are different in several critical respects. First, the restrictions on indemnity in the residential statute apply only to construction defect claims in newly constructed “For Sale” houses. The statute does not preclude Type I indemnity provisions for any other claims arising out of residential subcontracts. In contrast, the indemnity restrictions in the commercial statute apply to all claims arising out of commercial subcontracts. In addition, the commercial statute allows indemnity for the general contractor’s passive fault. Since some subcontractors on “residential” projects perform off-site “commercial” work as well, we have amended even residential subcontracts to address the subcontractors’ various indemnity obligations for different parts of their work (e.g., residential work versus commercial work).
Owner-Contractor Agreements
The January 1, 2013 new indemnity provisions apply not only to subcontracts, but also to owner-contractor agreements. Civil Code section 2782(c)(1) precludes indemnity for an owner’s active negligence. Interestingly, the exclusions contained in Civil Code section 2782.05 for subcontracts do not apply, and the statute does not provide contractors with the option of defending claims set forth in the sections concerning subcontracts. Therefore, we have revised the indemnity provisions in owner-contractor agreements to exclude indemnity for the owner’s active negligence.
Design Professional Agreements
The 2007 revisions with respect to “For Sale” residential contracts (discussed above), and the 2013 revisions for commercial contracts do not apply to design professionals. The new indemnity statute concerning commercial subcontracts specifically excludes design professionals from the “anti-indemnity” benefits provided to subcontractors. Therefore, Type I indemnity provisions are fair game and can still be included in design professional contracts.
Conclusion
In sum, Civil Code sections 2782 et seq. now contain an increasingly complex framework for indemnity rules in construction contracts. For example, there is one set of rules for “For Sale” residential construction defect claims (no indemnity for the developer’s active or passive negligence), another for any other claims arising out of residential construction (Type I indemnity is permitted), another for commercial subcontracts (no indemnity for the general contractor’s active negligence, but indemnity for the general contractor’s passive negligence unless any of the exceptions apply, in which case Type I indemnity is permitted), and yet another for commercial owner contractor agreements (no indemnity for the owner’s active negligence, but indemnity for the owner’s passive negligence with no exceptions).
California’s indemnity laws are complex, and rumors as to the impact of the new legislation have made it even more difficult to negotiate these provisions. It is imperative that indemnity clauses in construction contracts clearly delineate the obligations for the specific type or types of work contemplated by the contract. The legislature’s attempt to simplify indemnity obligations has actually made such provisions lengthier and more cumbersome. As experienced construction attorneys, our task is to draft indemnity provisions that comply with the laws, address potential claims, and are understandable.
Mr. Himmelstein is a partner in the Newport Beach office of Newmeyer & Dillion and practices in the areas of construction, real estate, business and insurance litigation. He also specializes in drafting and negotiating construction and real estate contracts. Mark can be reached at mark.himmelstein@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part I
March 22, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Here’s a helpful comparison of and analysis of some important contract sections in the
AIA 201 (2007 and 2017 versions) and
ConsensusDocs (2014 and 2017 versions). While not intended to be all inclusive, this summary comparison of the contract documents will run as a three-part series. Part I covers Financial Assurances, Design Risk, Project Management and Contract Administration. Part II will cover Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR. Part III will cover Insurance and Indemnification and Payment.
FINANCIAL ASSURANCES
- What assurances are there that the owner can pay for the project?
- The Contractor should have the right to request and obtain proof that the Owner has funding sufficient to pay for the Work. The provision should also provide that the Contractor may terminate the Contract if the Owner refuses to allow a review of funding documents, or should the Contractor reasonably determine that the Owner does not have sufficient funds to pay for the Work.
Relevant Sections:
- A201 2007 Section 2.2.1; 2017 Section 2.2.1-2.2.2 A201
- 2014 & 2017 ConsensusDocs 200: Section 4.2
AIA:
- Section 2.2.1 A201 2007 & 2017: Both editions require the Owner, upon Contractor’s written request, to provide, “reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract.” Thereafter, the Contractor may only request such evidence if (1) the Owner fails to make payments; (2) a change in the Work materially changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due. If the Owner does not comply, the Contractor may stop work.
- Additionally, A201 2017 Section 2.2.2 awards costs to the Contractor for demobilization and remobilization.
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Mr. Sams may be contacted at mpsams@KandSlegal.com
Ms. Cox may be contacted at ajcox@KandSlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Public Works Bid Protests – Who Is Responsible? Who Is Responsive?
December 14, 2020 —
Eric Divine - Porter Law GroupMost Public Works Solicitations Are Low Bid
The process for awarding public works projects in California is controlled by the Public Contract Code. Generally, regardless of whether the public agency is the State, a county, a city or a local district, the project is awarded to the contractor who is “responsible” and submits the least expensive “responsive” bid. This is generally known as a “low bid” contract. In the context of public works, the terms responsible and responsive have very important meanings. As a result, State and local governments have gotten into very expensive trouble for not following the law. So, to understand how to best present a bid protest on a low bid solicitation, you, as a contractor should have a good understanding of the meaning of these terms.
Note: There are other methods of contracting for public works that are not low bid, which are typically called “best value” contracts because the procurement process considers factors other than just price. These methods are typically used for large projects because the added complexity and expense of the procurement process only makes sense when the project is itself complex and expensive.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Divine, Porter Law GroupMr. Divine may be contacted at
edivine@porterlaw.com
Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Wells Fargo, JPMorgan Vexed by Low Demand for Mortgages
April 15, 2014 —
Zachary Tracer – BloombergSlack demand for home loans continued to drag on earnings at Wells Fargo & Co. (WFC) and JPMorgan Chase & Co. (JPM) as the two largest U.S. mortgage lenders grappled for pieces of a shrunken market.
Even as interest rates hovered near historically low levels, new home loans tumbled 67 percent to $36 billion in the first quarter at San Francisco-based Wells Fargo, the biggest originator. JPMorgan posted a 68 percent drop to $17 billion, and the bank predicted it would lose money on mortgage production for the full year.
Both lenders are paring staff to keep expenses in line with demand for loans, which has waned as investors and cash buyers dominate some sales. New York-based JPMorgan said jobs at its mortgage business declined 14,000, or 30 percent, since the start of last year. Wells Fargo set plans to cut 1,100 positions in the most recent three months, which ranked as its worst first quarter for mortgage revenue since 2008.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary Tracer, BloombergMr. Tracer may be contacted at
ztracer1@bloomberg.net
What Happens When a Secured Creditor Files a Late Claim in an Equity Receivership?
September 28, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogPitting a receivership court’s inherent equitable powers against pre-existing property rights can lead to some pretty interesting questions. In SEC v. Wells Fargo Bank, N.A., 848 F.3d 1339, 1343-44 (11th Cir. 2017), the Eleventh Circuit recently examined whether a district court’s inherent authority to establish a claims submission process allowed the court to extinguish a security interest in real property based solely upon an untimely proof of claim. Much to the relief of secured creditors, the Eleventh Circuit held that the district court erred, as a matter of law, by extinguishing the creditor’s pre-existing property rights under those circumstances.
Introduction
Equity vests a district court with “‘broad powers and wide discretion to determine relief in an equity receivership.’” Wells Fargo, 848 F.3d at 1343-44 (quoting SEC v. Elliot, 953 F.2d 1560, 1566 (11th Cir. 1992)). These powers include: (i) establishing procedures for the submission of claims to a receiver, and (ii) setting a claims bar date. Id. at 1344 (citing SEC v. Tipco, Inc., 554 F.2d 710, 711 (5th Cir. 1977)).
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Prison Contractors Did Not Follow the Law
October 15, 2013 —
CDJ STAFFUnder Iowa law, nearly ninety-percent of the construction workers for the new state prison in Fort Madison should have been Iowa residents. But according to reports obtained by the Des Moines Register, about fifty percent of the workers were from other states. The law responds to a similar one in Illinois that requires that most workers on public projects must be Illinois residents.
Many of the out-of-state employees live on the other side of the Mississippi River and, according to Ryan Drew of the Southeast Iowa Building and Construction Trades Council, are part of a broader Illinois-Iowa community, shopping at Iowa retailers.
Read the court decisionRead the full story...Reprinted courtesy of