1 De Haro: A Case Study on Successful Cross-Laminated Timber Design and Construction in San Francisco
November 06, 2023 —
Cait Horner, Adam J. Weaver & Allan C. Van Vliet - Gravel2Gavel Construction & Real Estate Law BlogAt the intersection of San Francisco’s SOMA, Potrero Hill and Showplace Square districts, a first-of-its-kind building offers an example of the potential widespread success of mass timber construction in the United States. 1 De Haro, a 134,000-square-foot, 4-story office and light industrial project built by Bay Area developer
SKS Partners is not only the first cross-laminated timber (CLT) building in the San Francisco, it is also the first multistory mass timber building of its type to be fully executed in California and the first CLT project in the United States to be delivered via railways. We recently sat down with Yvonne Fisher and Lee Ishida of SKS to discuss the unique design process, marketing success and overall industry buzz surrounding one of their latest
projects.
Reprinted courtesy of
Cait Horner, Pillsbury,
Adam J. Weaver, Pillsbury and
Allan C. Van Vliet, Pillsbury
Ms. Horner may be contacted at cait.horner@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Mr. Van Vliet may be contacted at allan.vanvliet@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Leaky Wells Spur Call for Stricter Rules on Gas Drilling
September 17, 2014 —
Jim Snyder, Jim Polson and Bradley Olson – BloombergA study that found natural gas drilling polluted drinking water is fueling calls for stricter standards for well construction that could increase costs for energy companies.
The analysis by academic researchers backed the oil and gas industry in one respect: the authors said “fracking” wasn’t to blame for harmful methane seeping into groundwater studied in Texas and Pennsylvania. Some environmentalists contend that by blasting underground rock with a mix of water, chemicals and sand, producers can force the gas into drinking water near the surface.
The bigger concern, according to the analysis published yesterday by the peer-reviewed Proceedings of the National Academy of Sciences, are leaks in the steel-and-cement casings surrounding the well bore. They let gas escape before it gets to the surface, making water undrinkable and in some cases explosive.
Reprinted courtesy of Bloomberg journalists
Jim Snyder,
Jim Polson and
Bradley Olson
Mr. Snyder may be contacted at jsnyder24@bloomberg.net; Mr. Polson may be contacted at jpolson@bloomberg.net; Mr. Olson may be contacted at bradleyolson@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Continuity and Disaster Recovery Plans for Contractors: Lessons From the Past
November 28, 2022 —
Rich Sghiatti - Construction ExecutiveThere is no shortage of natural disasters to illustrate the importance of being prepared. Wildfires, hurricanes, winter storms and floods can hit a construction job site hard. Appropriate property-casualty insurance and surety bonds are necessary protections for a contractor and project owner. But the addition of well-thought-out continuity and disaster recovery plans will better position the contractor to deal with whatever Mother Nature brings.
Consider Hurricane Katrina, the costliest hurricane to hit the United States. Pummeling Florida, Louisiana and Mississippi in August 2005, the storm led to 1,833 fatalities and an estimated $108 billion in damages. Levees meant to protect New Orleans from Lake Pontchartrain did not hold, flooding 80% of the city.
Utilities including power, water and sanitary sewers were severely damaged. Homes were destroyed. Roadways were closed. Communications systems were down.
Contractors who had good business continuity and disaster recovery plans fared better than those who did not.
Reprinted courtesy of
Rich Sghiatti, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Wildfire Smoke Threatens to Wipe Out Decades of Air Pollution Progress
August 28, 2023 —
Linda Poon & Immanual John Milton - BloombergThe US is on track to experience its worst year for smoke exposure in decades, after wildfires in Canada sent toxic plumes drifting across the border to the Midwest and the East Coast earlier this summer.
In June and July, New York and Chicago saw more “very unhealthy” and “hazardous” air quality days for fine particle pollution (PM2.5) than in the same months every year since the Environmental Protection Agency began tracking PM2.5 nationally in 2000, a Bloomberg CityLab analysis of federal data found. In Washington, DC, the number of “very unhealthy” days reached the highest in over a decade.
On the EPA’s air quality index scale, these days correspond with the highest levels of public health concern. Extensive exposure to PM2.5 particles, the main pollutant found in smoke, can increase the risk of a variety of problems, including heart and respiratory disease, as well as premature death.
Reprinted courtesy of
Linda Poon, Bloomberg and
Immanual John Milton, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Builder Survey Focuses on Green Practices of Top 200 Builders
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder magazine reported that the 2013 Builder 100/Next 100 survey provided data on how many builders constructed homes using a certified third-party green rating system. They discovered that nearly half of the 200 top U.S. builders constructed 100% of its homes to a third-party standard, while 38.5% reported that some of the homes were constructed using a third-party standard, while 12.5% stated that none of their homes were built to a third-party standard.
“The decision to offer homes that are high-performance, energy-efficient, non-toxic, sustainable--whatever the preferred term--involves many considerations and builders must weigh expenses and impediments against potential benefits,” according to Builder magazine.
Read the court decisionRead the full story...Reprinted courtesy of
Final Furnishing Date is a Question of Fact
November 10, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction liens need to be recorded within 90 days from the lienor’s final furnishing date on the project. This date is exclusive of punchlist or warranty work. The final furnishing date needs to be proven at trial to establish that the construction lien was timely recorded. If there is an evidentiary dispute as the final furnishing date (the contractor claims the date was “x” to establish the lien was timely and the owner claims the date was “y” to establish the lien was untimely), then the date is a question of fact to be determined by the jury.
For instance, in Best Drywall Services, Inc. v. Blasczyk, 2016 WL 6246701 (Fla. 2d DCA 2016), a contractor and owner entered into an oral agreement for a residential renovation project. The contractor recorded a construction lien after its final two invoices went unpaid. During trial, the contractor offered conflicting evidence as to when its final furnishing date on the project was. Numerous dates were offered in the record including dates that were more than 90 days prior to the date the contractor recorded its lien, meaning the lien was arguably untimely. As a result, the trial judge entered a directed verdict in favor of the owner and against the contractor on the contractor’s lien claim finding the lien was untimely recorded.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Additional Insured Not Entitled to Coverage for Named Insured's Defective Work
September 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the Seventh Circuit determined there was no duty to defend or to indemnify the additional insured for the named insured's defective work. St. Paul Guardian Ins. Co., et al. v. Walsh Construction Co., 99 F. 4th 1035 (7th Cir. 2024).
The City of Chicago contracted with Walsh Construction Company to manage the construction of a canopy and curtain wall system at O'Hare International Airport. Walsh entered into a contract with Carlo Steel Corporation, which in turn subcontracted with LB Steel, LLC to fabricate and install steel columns to support the wall and canopy. LB Steel listed Walsh as an additional insured in its commercial general liability policies. LB Steel's insurers were St. Paul, Travelers, and Charter Oak Fire Insurance Company.
Several years into the project, the City discovered cracks in the welds of the steel columns and sued Walsh. Walsh, in turn, sued LB Steel under its subcontract. Walsh also asked LB Steel's insurers to defend it in the City's lawsuit, but they refused to do so. Walsh eventually secured a judgment against LB Steel, but LB Steel declared bankruptcy. Walsh then sued LB Steel's insurers to recover the costs of defending against the City's lawsuit and indemnification for any resulting losses.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Denver Condo Development Increasing, with Caution
January 21, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Aldo Svaldi of The Denver Post, condo development has increased in the Denver metro area, though builders stated they are carefully documenting each step of construction as well as vetting contractors and materials.
"We are being ultra-careful about everything," Roy Kline, a managing director at Western Development Group, told the Denver Post. Western Development is behind the 250 Columbine development. Svaldi reported that Western Development Group has been “photographing or filming every step of construction.”
Brian Levitt and Trevor Hines of NAVA Real Estate Development “have spent the past year crafting a detailed three-page, 18-point action plan to deal with any contingency they could think of arising from the state's constructions-defects law.” Levitt told Svaldi that he “estimates all the safeguards being put in place will add 5 percent to 10 percent to the costs of the units at NAVA Sloan Lake, whose final price points are being determined.”
Read the court decisionRead the full story...Reprinted courtesy of