Court of Appeal Shines Light on Collusive Settlement Agreements
October 21, 2015 —
Kristian B. Moriarty & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Diamond v. Reshko, (filed 8/20/2015, No. A139251) the California Court of Appeal, First District, held that a defendant was entitled to introduce evidence at trial reflecting amounts paid by co-defendants in settlement of a plaintiff’s claim.
Plaintiff, Christine Diamond, was injured during an automobile accident that occurred while she was a passenger in a taxi driven by Amir Mansouri. Christine, and her husband Andrew, filed suit against Mr. Mansouri, the Yellow Cab Collective (“Yellow Cab”), and the driver of the vehicle that collided with the taxi, Serge Reshko. Before trial, Mansouri and the Yellow Cab Collective settled with Plaintiffs, but agreed to appear and participate as defendants at the jury trial of the action. Mansouri and Yellow Cab paid a total of $400,000 to Plaintiffs in settlement.
Reshko filed a pre-trial motion seeking an order permitting Reshko to admit evidence of the settlement between Plaintiffs and the other defendants. The trial court refused to rule on the motion before trial. Ultimately, evidence of the settlement between Plaintiffs, Mansouri and Yellow Cab was excluded during trial. The jury returned a verdict in favor of Plaintiffs in the total amount of $745,778, finding Mansouri 40 percent at fault, and Reshko 60 percent at fault. The Trial Court entered judgment against Reshko in the sum of $406,698.
Reshko appealed the judgment. The First District Court of Appeal reversed, holding that evidence of the settlement should have been admitted at trial because the settling defendant’s position should be revealed to the court and jury to avoid committing a fraud on the court, and in order to permit the trier of fact to properly weigh the settling defendant’s testimony.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Issues of Fact Prevent Insurer's Summary Judgment Motion in Collapse Case
January 17, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's effort to dismiss the insured's collapse case by motion for summary judgment failed. Bitters v. Nationwide Gen. Ins. Co., 2021 U.S. Dist. LEXIS 228523 (E.D. Pa. Nov. 30, 2021).
The insured alleged that there was a "sudden and accidental direct physical loss" to his home caused by collapse due to hidden insect damage to the foundation. The insured came home to find the floor of a bedroom dropped down to the cement slab below. He filed a claim with Nationwide, but coverage was denied. Suit was filed and Nationwide moved for summary judgment.
The policy provided coverage for a sudden and accidental collapse caused by hidden insect damage. A building or part of a building was not considered in the state of collapse if it was standing, even if it was in danger of falling low or caving in.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Equities Favor Subrogating Insurer Over Subcontractor That Performed Defective Work
August 04, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Valley Crest Landscape v. Mission Pools (No. G049060, filed 6/26/15, ord. pub. 7/2/15), a California appeals court held that equities favor an insurer seeking equitable subrogation over a subcontractor that agreed to defend and indemnify claims arising out of its performance of work under the subcontract.
Valley Crest contracted to build a pool at the St. Regis Hotel in Dana Point. Valley Crest subcontracted with Mission Pools to perform the work. The master contract contained an indemnity clause in favor of St. Regis, and the subcontract contained an indemnity clause in favor of Valley Crest. An intoxicated guest who was rendered quadriplegic after diving in the shallow end of the pool sued the hotel, Valley Crest, Mission and others involved in the design, construction and operation of the pool. The suit included allegations that the pool depth was improperly marked; there was inadequate warning signage; and the pool finish caused the pool to appear deeper than it was. Valley Crest tendered its defense to Mission Pools under the subcontract’s indemnity agreement. When Mission did not respond, Valley crest filed a cross-complaint for indemnity. All parties ultimately reached a settlement with the injured plaintiff, leaving Valley Crest’s cross-complaint against Mission Pools.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Floating Crane on Job in NYC's East River Has a Storied Past of Cold War Intrigue
January 04, 2018 —
Nadine M. Post - Engineering News-RecordOriginally Published by CDJ on March 22, 2017
The complex maneuver of lifting heavy prefabricated modules out of New York City's East River to build a university laboratory took careful planning and the work of one particular floating crane with a complicated past.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Identifying and Accessing Coverage in Complex Construction Claims
September 29, 2021 —
Jeffrey J. Vita & Michael V. Pepe - Saxe Doernberger & Vita, P.C.I. Introduction
First-party, third-party, builder’s risk, professional liability, commercial general liability, wrap-ups, and additional insured status are all potential sources of insurance coverage for a large construction loss. Therefore, it is critical for construction industry participants, from owners and developers to general contractors and their subcontractors, to have a functional knowledge of the different types of insurance coverage available to them and how those coverages intersect to respond to a loss. This paper presents a brief overview of the various types of coverage available to contractors, construction managers, and owners in a large construction loss and the risks each coverage is designed to insure.
In general, there are two forms of coverage: (1) First-party liability coverage, which protects an insured’s own losses on a project during construction; and (2) Third-party liability coverage, which insures the project participants for losses that become the subject of claims or suits brought against the project participants by third parties. When a loss occurs, such as property damage, both types of coverage can be implicated. For example, if a fire burns down a building under construction, the contractor likely would incur first-party losses such as cleanup costs. The contractor may also have third-party exposure if the owner alleges that the contractor was responsible for the fire. On the other hand, when a bodily injury occurs, all losses to the contractor will be third-party losses. A broad overview of each of these policies is provided below.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita and
Michael V. Pepe, Saxe Doernberger & Vita
Mr. Vita may be contacted at JVita@sdvlaw.com
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Acord Certificates of Liability Insurance: What They Don’t Tell You Can Hurt You
June 28, 2013 —
David McLainAs anyone involved in construction knows, one of the most heavily used forms for tracking insurance information during the subcontracting phase of a project is the Acord Certificate of Liability Insurance. General contractors often require subcontractors to provide these ubiquitous forms as evidence that the subcontractor maintains adequate insurance or insurance which complies with the requirements of the subcontract. Unfortunately, experience has shown that the Acord forms being used today are insufficient sources of the information needed by the developer and general contractor.
Historically, developers and GCs would require Acord forms to ensure that a subcontractor had a CGL insurance policy, with sufficient limits, and which named them as additional insureds. More recently, developers and GCs took the additional step of requiring a confirmation on the Acord forms that they were named as additional insureds for both ongoing and completed operations. This is important because coverage for ongoing operations only provides coverage during the construction process. Once the homes are put to their intended use, developers and GCs must be named as additional insureds for completed operations also in order to avail themselves of the benefits of the policy. Unfortunately, this is where the evolution of the use of the Acord forms ended, resulting in a failure to provide sufficient information to protect developers and GCs from the unknown.
My firm has had a rash of recent experience where our clients have not obtained the benefit of additional insured coverage for which they bargained because they relied on Acord forms which failed to provide sufficient information to allow them to protect themselves from insufficient insurance coverage on the part of the subcontractors with which they did business. For example, in one recent case a homeowners association alleged insufficient grading and drainage away from the homes within a development built by one of our clients. In reviewing the insurance information from the construction files, we found the Acord forms from the excavating company that performed all of the grading work around the homes. To our delight, the Acord form listed our client as an additional insured for both ongoing and completed operations.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainDavid M. McLain can be contacted at
mclain@hhmrlaw.com
Got Licensing Questions? CSLB Licensing Workshop November 17th and December 15th
November 15, 2017 —
Garret Murai - California Construction Law BlogA rare opportunity to hear it straight from the folks who process the applications . . .
CSLB Licensing Workshop Offers Helpful Information for Applicants
The Contractors State License Board (CSLB) is hosting free workshops for those looking to become a licensed contractor. Current licensees are encouraged to pass this information along to their workers and to those who might be interested in learning more about the application process.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLP Mr. Murai may be contacted at
gmurai@wendel.com
Courthouse Reporter Series: Nebraska Court of Appeals Vacates Arbitration Award for Misconduct
November 18, 2024 —
Brendan J. Witry - The Dispute ResolverVacating an arbitration award is often seen as an uphill battle. Indeed, the U.S. Supreme Court has stated that “courts may only vacate an arbitrator’s decision ‘only in very unusual circumstances.’” Oxford Health Plans, LLC v. Sutter, 569 U.S. 564, 568 (2013). The Federal Arbitration Act provides limited grounds to seek the vacatur of an arbitration award. In Lund-Ross Constructors v. Duke of Omaga, LLC, ___ N.W.3d ___, 33 Neb.App.73, the Nebraska Court of Appeals found that an arbitrator’s conduct warranted the partial vacatur of the award, which granted relief to a subcontractor who filed a counterclaim after the arbitration hearing had closed.
Lund-Ross contracted with Duke of Omaha to build an apartment complex in Omaha. Lund-Ross, in turn, sub-contracted with A Raymond Plumbing. Following completion of the building, Owner withheld payment from Lund-Ross, who in turn, withheld payment from Raymond. Both Lund-Ross and Raymond filed mechanics liens and initiated suits; Raymond’s suit ultimately was dismissed for want of prosecution. Lund-Ross proceeded to arbitration with Owner, naming Raymond as a respondent. Raymond did not participate in the arbitration as a claimant at the time of the hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at