New York Revises Retainage Requirements for Private Construction Contracts: Overview of the “5% Retainage Law”
January 22, 2024 —
Levi W. Barrett, Patrick T. Murray, Skyler L. Santomartino & Mark A. Snyder - Peckar & Abramson, P.C.On November 17, 2023, the State of New York enacted the “5% Retainage Law.” This legislation effectively limits the amount of retainage that can be held from general contractors and subcontractors to no more than 5%. It applies to many but not all construction contracts. In addition, the new law revises late stage billing requirements, enabling contractors to invoice for retainage at substantial completion. Previously, the parties to a construction contract were free to negotiate any retainage amount, limited only by an unspecified “reasonable amount” that would be released as the parties contractually set forth.
Summary
The new law amends Sections 756-a and 756-c of the General Business Law (part of Article 35E of the GBL, known as the “Prompt Pay Act”), and applies to private construction contracts “where the aggregate cost of the construction project, including all labor, services, materials and equipment to be furnished, equals or exceeds one hundred fifty thousand dollars.”
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Patrick T. Murray, Peckar & Abramson, P.C.,
Skyler L. Santomartino, Peckar & Abramson, P.C. and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Murray may be contacted at pmurray@pecklaw.com
Mr. Santomartino may be contacted at ssantomartino@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA ETS Heads to Sixth Circuit
December 13, 2021 —
George Morrison - White and Williams LLPOn November 16, 2021, the U.S. Court of Appeals for the Sixth Circuit was selected during the Judicial Panel on Multidistrict Litigation’s lottery to hear the multiple consolidated challenges to the recent COVID-19 Emergency Temporary Standard (ETS) issued by the Occupational Safety and Health Administration (OSHA). OSHA is permitted to issue an ETS if the agency arrives at the conclusion that a “grave danger” to worker safety exists. An ETS does not go through the typical notice-and-comment period that federal regulations usually follow.
Inheriting the Fifth Circuit’s recent nationwide stay on implementation and enforcement of the ETS, the Sixth Circuit will decide whether the stay should be “modified, revoked, or extended” in the short term. Early this morning, OSHA filed an emergency motion to dissolve the Fifth Circuit’s stay of the vaccine mandate with the Sixth Circuit. OSHA argued, among other things:
- The Fifth Circuit erred in holding “that OSHA lacked statutory authority to address the grave danger of COVID-19 in the place on the ground that COVID-19 is caused by a virus and also exists outside of the workplace” because “[t]hat rationale has no basis in the statutory text.”
- The Fifth Circuit erred in finding the ETS both over- and underinclusive because “OSHA recounted extensive empirical data showing that all employees can transmit COVID-19 in the workplace and that COVID-19 has spread in a vast variety of workplace.”
- The “petitioners have not shown that their claimed injuries outweigh the interests in protecting employees from a dangerous virus while this litigation proceeds . . . . These claimed injuries do not justify delaying the [ETS] that will save thousands of lives and prevent hundreds of thousands of hospitalizations.”
Read the court decisionRead the full story...Reprinted courtesy of
George Morrison, White and Williams LLPMr. Morrison may be contacted at
morrisong@whiteandwilliams.com
Sinking Buildings on the Rise?
July 01, 2019 —
Jason M. Adams - Gibbs GidenBy now everyone in the construction and insurance industries is familiar with the 58-story Millennium Tower building in San Francisco that has sunk 17 inches and tilted another 14 inches to the northwest. Another recent New York lawsuit alleges that a 58-story luxury Manhattan condo high-rise is also sinking and causing significant damage. With construction booming in the Southeast and other areas with questionable soils, sinking building cases may be on the rise. Given this reality, the issue of subsidence should be of paramount importance to every construction and insurance professional when insuring a project.
Most insurance carriers will include a subsidence and/or other earth movement exclusion on a commercial general liability ("CGL") quote for insurance as a matter of course. Construction professionals (owners/developers, general contractors, and subcontractors) or their brokers may be under the mistaken impression that they have no choice but to accept these subsidence exclusions as part of a standard construction policy. This is not the case. To the contrary, most insurance carriers are willing to remove subsidence exclusions if the underwriters are provided with acceptable geotechnical/soils reports when considering the project.
The insured construction professional often pushes back on the insurance carrier's request for soils reports because the insured sees the request as an unnecessary hassle, expense or unwelcome interference in the job. However, the carrier's soils review is designed to benefit everyone. If potential soils issues are discovered during the underwriting process they can be addressed at the outset of the project rather than after the project is built, which will typically cost substantially more to remedy. Moreover, a thorough analysis of the condition of the soils at the outset of the project allows the risk management team to recognize any potential issues and ensure that the proper coverage is obtained in order to provide protection down the road. Even if the insurance carrier charges more money to sign off on questionable soils after a review of the reports, the slight increase in premium is likely a worthwhile investment in the event of a subsidence loss.
The lesson is that the insured should not blindly accept a subsidence exclusion and should negotiate its removal. The insured should provide its broker and the insurance carrier the information they need in order to make a fully-informed decision as it pertains to the soils. Once the insurance carrier has had the opportunity to review and sign off on the condition of the soil, the carrier should feel comfortable enough to remove any subsidence exclusions or other similar earth movement limitations.
Subsidence is a relatively straightforward issue to deal with as long as the project team’s lawyers, brokers, risk managers and insurance company underwriters are working together toward the common goal of properly evaluating the risk and adequately insuring the project. This simple cooperative process between the entire risk management team could mean the difference between being covered or not covered in the event of a loss related to earth movement.
Jason M. Adams, Esq. is Senior Counsel at Gibbs Giden representing construction professionals (owners/developers, contractors, architects, etc.) in the areas of Construction Law, Insurance Law and Risk Management, Common Interest Community Law (HOA) and Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms. Mr. Adams can be reached at jadams@gibbsgiden.com.
The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. The transmission of information by email, or any transmission or exchange of information over the Internet, or by any of the included links is not intended to create and does not constitute an attorney-client relationship. This publication may not be reproduced or used in whole or in part without written consent of the author. Copyright 2019 ©
Read the court decisionRead the full story...Reprinted courtesy of
Nonresidential Construction Employment Expands in August, Says ABC
December 16, 2019 —
Associated Builders and Contractors - Construction ExecutiveThe construction industry added 14,000 net new jobs in August, according to an Associated Builders and Contractors analysis of data released by the U.S. Bureau of Labor Statistics. On a year-over-year basis, industry employment has expanded by 177,000 jobs, or 2.4%.
Nonresidential construction employment increased by 11,600 net jobs in August and is up by 114,200 net jobs over the last 12 months, translating into 2.5% growth. The majority of job gains emerged from nonresidential specialty trade contractors, which added 5,400 jobs last month and nearly 103,000 positions over the past year. Heavy and civil engineering added 4,400 net new jobs, while nonresidential building added 1,800 jobs on a monthly basis.
The construction unemployment rate stood at 3.6% in August, up 0.2 percentage points from the same time last year. Unemployment across all industries stood at 3.7% in August, unchanged from the previous month.
“While job growth across all industries fell short of projections, today’s employment report was just about perfect,” said ABC Chief Economist Anirban Basu. “Yes, employment growth has been softening for quite some time, with average monthly job growth totaling 150,000 during the last six months after approaching 200,000 during the prior six-month period. And employment growth estimates were also revised lower for both June and July. That said, looking beyond the headline number, August’s labor market performance was more than respectable, even accounting for about 25,000 of the jobs being added for temporary Census work.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Death of Subcontractor’s Unjust Enrichment Claim Against Project Owner
April 12, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a previous article, I discussed a subcontractor’s
unjust enrichment claim against a project’s owner and the death of this equitable claim if the owner fully paid the general contractor or paid the general contractor for the subcontractor’s work. This can be best summarized from a very short 1995 opinion out of the Fourth District Court of Appeal: “Unjust enrichment is equitable in nature and cannot exist where payment has been made for the benefit conferred. [Owner] paid [General Contractor] the full amount of its contract for the construction project. Accordingly, there can be no unjust enrichment claim to support [Subcontractor’s] claim.” Gene B. Glick Co., Inc. v. Sunshine Ready Concrete Co., Inc., 651 So.2d 90 (Fla. 4th DCA 1995).
Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.
Mr. Adelstein may be contacted at dma@kirwinnorris.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Guam’s CERCLA Claim Allowed, a “Roundup” Verdict Upheld, and Judicial Process Privilege Lost
June 14, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief account of some of the important environmental and administrative law cases recently decided.
THE U.S. SUPREME COURT
BP PLC, et al. v Mayor and City of Baltimore
The issue the court confronted was a procedural matter: Can the defendant energy companies use the federal removal statutes (see 28 USC Section 1442) to remove a state law climate change lawsuit to federal court? Here, a group of energy companies were sued by the mayor and city council of Baltimore in state court, where they alleged that the defendants had concealed the adverse environmental effects of the fossil fuel products they promoted and sold in Baltimore City. Several similar lawsuits have been filed in many state courts, where typically it is alleged that the defendants can be sued on various common law theories. Rather than defend these cases in state court, the defendants have sought to remove these cases to federal court because climate change liability appears to be an issue that should be settled at the federal level. These efforts have been unsuccessful, with most federal trial and appellate courts holding that the reasons cited for removal (oftentimes the federal officer removal statute) have not been persuasive. In this case, both the Maryland federal district court and the U.S. Court of Appeals held they had no jurisdiction to authorize removal, and thus returned the case to the state court. Noting that the U.S. Court of Appeals for the Seventh Circuit ruled that a removal action could be countenanced under Section 1442, thus creating a circuit split, the Supreme Court held that a straightforward reading of the removal statute empowers the reviewing court to examine all theories for removal that a district court has rejected. Consequently, the Court remanded the case to the Fourth Circuit where it can decide, “in the first instance,” whether there actually exist grounds to remove this case to federal court.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Attention Contractors: U.S. Department of Labor Issues Guidance on Avoiding Discrimination When Using AI in Hiring
November 25, 2024 —
Matthew DeVries - Best Practices Construction LawI recently blogged about the use of
AI and ChatGBT in the construction industry. Today’s guest post by
Alexandra Shulman and
Leah Lively addresses the recent guidance by the USDOL on the issue of using AI when hiring in recruitment, which is applicable to those constructions who use AI in the recruitment process.
AI in hiring: About 80% of U.S. and almost all Fortune 500 companies use AI-powered hiring software. AI may be used to target online advertising for job opportunities and to match candidates to jobs on employment platforms (e.g., LinkedIn, Indeed). AI may also be used to reject or rank applicants using automated resume screening and chatbots based on knockout questions, keyword requirements, or specific qualifications or characteristics.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, BuchalterMr. DeVries may be contacted at
mdevries@buchalter.com
New Safety Requirements added for Keystone Pipeline
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAfter learning about construction defects on the “southern leg of the Canada-to-Texas project,” safety regulators have added two additional conditions “on construction of TransCanada Corp.’s Keystone XL oil pipeline,” according to Claims Journal. The defects, which have been fixed, included “high rates of bad welds, dented pipe and damaged pipeline coating.”
The first condition requires “TransCanada to hire a third-party contractor chosen by the pipeline safety agency to monitor the construction” and report to the U.S. government, while the second condition requires “TransCanada to adopt a quality management program.”
Both conditions were “buried near the end of the 26 appendices in a voluminous environmental impact statement on Keystone XL released by the State Department on Jan. 31.”
Read the court decisionRead the full story...Reprinted courtesy of