Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Voluntary Payments Affirmative Defense Does Not Apply in Contract Cases
July 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesIn certain matters, there is an affirmative defense referred to as the “voluntary payments” defense. This defense states, “where one makes a payment of any sum under a claim of right with knowledge of the facts such a payment is voluntary and cannot be recovered.” Avatar Properties, Inc. v. Gundel, 48 Fla.L.Weekly D1272c (Fla. 6th DCA 2023) quoting City of Miami v. Keton, 115 So.2d 547, 551 (Fla. 1959). This voluntary payments defense could be construed as a “gotcha” defense, right? Unfair! You voluntarily made the payment with knowledge of the facts; therefore, you are s**t out of luck when it comes to recovering the potentially wrongful payment.
Well, guess what? This voluntary payments affirmative defense does NOT apply in contract disputes. This is codified by Florida Statute s. 725.04 which states: “When a suit is instituted by a party to a contract to recover a payment made pursuant to the contract and by the terms of the contract there was no enforceable obligation to make the payment or the making of the payment was excused, the defense of voluntary payment may not be interposed by the person receiving payment to defeat recovery of the payment.” Fla.Stat. s. 725.04. See also Avatar Properties, supra (explaining voluntary payment defense does not apply in contract cases and even in non-contract cases it doesn’t apply if payment made under coercion or compulsion).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Indiana Court of Appeals Rules Against Contractor and Performance Bond Surety on Contractor's Differing Site Conditions Claim
April 03, 2013 —
Brian M. Falcon - Frost Brown Todd LLCEarlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Brian M. FalconBrian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html
Brown Act Modifications in Response to Coronavirus Outbreak
March 30, 2020 —
Gregory J. Rolen - Haight Brown & BonesteelGov. Gavin Newsom waived certain provisions of the Bagley-Keene Act and Ralph M. Brown Act to make state and local legislative bodies safer while allowing California public entities to conduct business.
In an effort to promote social distancing and slow the spread of the coronavirus pandemic Gov. Newsom issued Executive Order N-25-20. The Executive Order authorizes state and local legislative bodies, such as school district and county office of education governing boards, to more easily hold public meetings by way of teleconference. The order took further steps to make public meetings accessible to the public via electronic means, including telephone.
The Brown Act generally requires legislative body members, a clerk, or other personnel to be physically present in a meeting in order to participate or establish a quorum. Executive Order N-25-20 temporarily eliminates this requirement. Furthermore, standard Brown Act requirements such as publicly noticing the teleconference location for each meeting participant is also suspended. Clearly, this is an attempt to protect the public, as well as Board members and staff, by temporarily discouraging large group settings in the conduct of the public’s business.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory J. Rolen, Haight Brown & BonesteelMr. Rolen may be contacted at
grolen@hbblaw.com
Ethical Limits on Preparing a Witness for Deposition or Trial
October 28, 2024 —
Stu Richeson - The Dispute ResolverIn this week’s blog post, we are going to take a brief look at ethical issues associated with preparing a witness for a deposition or to testify at trial. Most attorneys would agree that it is permissible to meet with a witness before the witness’s deposition to discuss what to expect. On the other hand, there is no question that advising a witness to provide false testimony would be improper. But what about the area in between those two extremes? For instance, can an attorney suggest to a witness how to phrase answers to anticipated questions that, while true, might not be the way the witness would have answered the question absent the attorney’s coaching?
A little over a year ago, the American Bar Association Standing Committee on Ethics and Professional Responsibility issued ABA Formal Opinion 508: The Ethics of Witness Preparation. The opinion provides certain examples of things that are and are not permissible in preparing a witness for a deposition or trial.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Toll Brothers Named #1 Home Builder on Fortune Magazine's 2023 World's Most Admired Companies® List
February 06, 2023 —
Toll Brothers, Inc.FORT WASHINGTON, Pa., Feb. 01, 2023 (GLOBE NEWSWIRE) -- Toll Brothers, Inc. (NYSE:TOL) (www.TollBrothers.com), the nation's leading builder of luxury homes, has been named the #1 Most Admired Home Builder in the 2023 Fortune magazine survey of the World's Most Admired Companies, the eighth year the company has achieved this honor.
To determine the best-regarded companies, Fortune and its partner Korn Ferry conducted the 2023 survey with 645 of the world's highest-revenue companies across 52 industries and 27 countries. Executives, directors, and Wall Street analysts were asked to rate companies in their own industries on nine criteria, ranging from investment value, financial soundness and quality of management, to quality of products, innovation, social responsibility and people management.
"We are proud to once again be honored as the #1 Home Builder on the Fortune World's Most Admired Companies list," said Douglas C. Yearley, Jr., chairman and chief executive officer of Toll Brothers. "All of us at Toll Brothers are focused on upholding our reputation for quality, value, and service built over the past 56 years. I would like to thank every Toll Brothers employee for their commitment to excellence and to serving our customers. We appreciate this tremendous recognition within the home building industry and the larger business community."
ABOUT TOLL BROTHERS
Toll Brothers, Inc., a Fortune 500 Company, is the nation's leading builder of luxury homes. The Company was founded 56 years ago in 1967 and became a public company in 1986. Its common stock is listed on the New York Stock Exchange under the symbol "TOL." The Company serves first-time, move-up, empty-nester, active-adult, and second-home buyers, as well as urban and suburban renters. Toll Brothers builds in over 60 markets in 24 states: Arizona, California, Colorado, Connecticut, Delaware, Florida, Georgia, Idaho, Illinois, Maryland, Massachusetts, Michigan, Nevada, New Jersey, New York, North Carolina, Oregon, Pennsylvania, South Carolina, Tennessee, Texas, Utah, Virginia, and Washington, as well as in the District of Columbia. The Company operates its own architectural, engineering, mortgage, title, land development, golf course development, smart home technology, and landscape subsidiaries. The Company also operates its own lumber distribution, house component assembly, and manufacturing operations.
Read the court decisionRead the full story...Reprinted courtesy of
Why Metro Atlanta Is the Poster Child for the US Housing Crisis
January 04, 2023 —
Brentin Mock - BloombergLast year, the Federal Reserve declared that not one of the 13 counties that make up metro Atlanta qualified as an affordable housing market. In many places, monthly housing costs consume more than 40% of homeowners’ incomes, well beyond the 30% threshold that the Federal Reserve uses to monitor market affordability.
Accelerating housing prices have been the narrative for virtually every major US metro lately, but Atlanta is somewhat “paradigmatic” of the trend, according to Georgia State University urban studies professor Dan Immergluck. Since arriving in Atlanta in 2005, Immergluck has been tracking and documenting the direction of metro Atlanta’s housing conditions, focusing on segregation and gentrification patterns.
His new book, Red Hot City: Housing, Race and Exclusion in 21st-Century Atlanta, released in October, is the culmination of much of that scholarship. What Red Hot City reveals is that while exorbitant house prices are typically the result of market forces, Atlanta can blame a lot of its own policy decisions over the last 20 years, particularly as it pertains to large civic projects like the BeltLine and Centennial Yards, a massive new development planned for south downtown Atlanta.
Read the court decisionRead the full story...Reprinted courtesy of
Brentin Mock, Bloomberg
U.K. to Set Out Plan for Fire-Risk Apartment Cladding Crisis
March 01, 2021 —
Emily Ashton & Olivia Konotey-Ahulu - BloombergThe U.K. government will set out its plans for stripping cladding from potentially unsafe apartment blocks, more than three years after a fire at London’s Grenfell Tower killed 72 people.
Reports suggest Housing Secretary Robert Jenrick will set out a package of measures amounting to billions of pounds when he makes a statement to the House of Commons on Wednesday.
Ministers announced a 1.6 billion pound ($2.2 billion) “safety fund” to remove dangerous cladding last year but Jenrick is expected to announce additional support on top of this. The price for the repairs could be as high as 15 billion pounds, according to a parliamentary committee last June.
Reprinted courtesy of
Emily Ashton, Bloomberg and
Olivia Konotey-Ahulu, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of