Risk Protection: Force Majeure Agreements Take on Renewed Relevance
November 30, 2020 —
Michael E. Carson - Construction ExecutiveForce majeure clauses have been standard in contracts dating back hundreds of years in the United States—and even longer in Europe. “Force majeure,” which is French for “greater force,” removes liability for unforeseen events that prevent parties from fulfilling contractual obligations.
In a year defined by the COVID-19 pandemic, these clauses have gone from boilerplate basics to something worthy of further examination and attention in order to minimize risk for all parties involved in a construction project. Prior to COVID-19, drafters might have considered a localized or regional event that would lead to invoking a force majeure clause. It is doubtful, however, that anybody envisioned the impact on such a world-wide scale.
UNDERSTANDING THE AGREEMENTS
Force majeure clauses cover unforeseen events, a broad term that encompasses both acts of God and human-caused incidents. These range from natural disasters like earthquakes and hurricanes to acts of terrorism, strikes, political strife, government actions, war and other difficult- or impossible-to-predict disruptions. When such an event occurs, the force majeure clause attempts to remove, or at least reduce, uncertainty as to the rights and liabilities of the parties to the agreement.
Reprinted courtesy of
Michael E. Carson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Carson may be contacted at
michael.carson@nationwide.com
Colorado Court of Appeals Defines “Substantial Completion” for Subcontractors’ Work so as to Shorten the Period of Time in Which They Can Be Sued
October 20, 2016 —
David M. McLain – Colorado Construction Litigation BlogOver the past few years, there has been a battle raging on in district courts and arbitration hearing rooms throughout Colorado regarding when a subcontractor’s work is to be deemed “substantially complete,” for purposes of triggering Colorado’s six-year statute of repose. C.R.S. § 13-80-104 states, in pertinent part:
Notwithstanding any statutory provision to the contrary, all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within the time provided in section 13-80-102 after the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than six years after the substantial completion of the improvement to the real property, except as provided in subsection (2) of this section.
* * *
(2) In case any such cause of action arises during the fifth or sixth year after substantial completion of the improvement to real property, said action shall be brought within two years after the date upon which said cause of action arises.
C.R.S. § 13-80-104 (emphasis added).
As the battle raged on at the trial court level, subcontractors and design professionals argued that their work should be deemed “substantially complete” when they finished their discrete scope of work within a project. Developers and general contractors, seeking to maintain third-party claims against the subcontractors and design professionals, typically argued either that the subcontractors’ and design professionals’ work should be deemed “substantially complete” upon the issuance of the final certificate of occupancy on the project, or upon the issuance of the final certificate of occupancy for the last building within a project on which the subcontractor or design professional worked. Trial court judges and arbitrators have been split on this issue, with perhaps a slight majority favoring one or the other approaches advocated by developers and general contractors, that the subcontractors’ and design professionals’ work is “substantially complete” upon the issuance of the last certificate of occupancy in a project (the minority view) or upon the issuance of the last certificate of occupancy for the last building within a project on which the subcontractor of design professional worked (the majority view).
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Updated 3/13/20: Coronavirus is Here: What Does That Mean for Your Project and Your Business?
March 16, 2020 —
Alexander Gorelik, Joshua E. Holt, Brian N. Krulick, Shoshana E. Rothman, A. Michelle West, & Brian S. Wood - Smith CurrieThe outbreak of COVID-19 (“coronavirus”) has wreaked a considerable human toll of death, physical suffering, fear, and anxiety internationally. Much of the fear and anxiety results from a lack of information or a full understanding about the spread of the disease, protection against infection, and treatment. At Smith, Currie & Hancock, we urge our clients, friends, and colleagues to take seriously, but calmly and prudently, the threat of this disease to protect yourselves, your loved ones, and your businesses. The first step in that process is to inform yourselves with reliable information. Toward that end, we direct your attention to the Centers for Disease Control and Prevention’s Coronavirus Disease 2019 website: https://www.cdc.gov/coronavirus/2019-ncov/index.html
In addition to the human toll, coronavirus has caused substantial disruptions to economies worldwide. In that regard, the adage “a picture is worth a thousand words,” is particularly foreboding. Satellite images taken by the U.S. National Aeronautics and Space Administration (NASA) of China at the outset of the coronavirus outbreak and approximately a month later show a dramatic decline in air pollution, signifying and illustrating a sharp decline in industrial activity and transportation caused by the disease.
Reprinted courtesy of Smith Currie attorneys
Alexander Gorelik,
Joshua E. Holt,
Brian N. Krulick,
Shoshana E. Rothman,
A. Michelle West, and
Brian S. Wood
Mr. Gorelik may be contacted at agorelik@smithcurrie.com
Mr. Holt may be contacted at jeholt@smithcurrie.com
Mr. Brian may be contacted at bnkrulick@smithcurrie.com
Ms. Shoshana may be contacted at serothman@smithcurrie.com
Ms. West may be contacted at amwest@smithcurrie.com
Mr. Wood may be contacted at bswood@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
SB 939 Proposes Moratorium On Unlawful Detainer Actions For Commercial Tenants And Allows Tenants Who Can't Renegotiate Their Lease In Good Faith To Terminate Their Lease Without Liability
June 01, 2020 —
Rhonda Kreger – Newmeyer DillionSB 939 is currently working its way through the Senate Judiciary Committee. The legislation would impose new obligations on landlords, and provide protections for commercial tenants who meet specified criteria. SB 939 would impose a moratorium on eviction of those qualified commercial tenants while emergency COVID-19 orders are in effect. Any eviction actions commenced after the date of the emergency COVID-19 order, but before the adoption of SB 939, would be void and unenforceable. The Senate Judiciary Committee has scheduled a hearing for SB 939 on May 22, 2020, at 9:00 a.m.
Who qualifies as a commercial tenant under SB 939?
To qualify under this legislation, a commercial tenant must be a business that operates primarily in California. The commercial tenant must be a small business, nonprofit, an eating or drinking establishment, place of entertainment, or performance venue. Publicly traded companies or any company owned by, or affiliated with a publicly traded company, do not qualify. The commercial tenant must have experienced a decline of at least 40 percent monthly revenue, either as compared to two months before the emergency COVID-19 order, or other local government shelter-in-place orders took effect, or as compared to the same month in 2019. If the commercial tenant is an eating or drinking establishment, place of entertainment, or performance venue, the commercial tenant must also show a decline of 25 percent or more in capacity due to social or physical distancing orders or safety concerns, and show that it is subject to regulations to prevent the spread of COVID-19 that will financially impair the business when compared to the period before the emergency COVID-19 order or other local shelter-in-place orders took effect.
What eviction actions are prohibited while emergency COVID-19 orders are in effect?
If adopted, SB 939 would add Section 1951.9 to the Civil Code. This section would make it unlawful to terminate a tenancy, serve notice to terminate a tenancy, use lockout or utility shutoff actions to terminate a tenancy or otherwise evict a tenant of commercial real property, including a business or nonprofit, during the pendency of the COVID-19 emergency order proclaimed by Governor Newsome on March 4, 2020. Exceptions apply if a tenant poses a threat to the property, other tenants or a person, business or other entity. Any violations of this eviction prohibition would be against public policy and unenforceable.
Any eviction started after proclamation of the state of emergency but before the effective date is deemed void, against public policy and is unenforceable.
Does SB 939 impose new penalties or remedies?
Any landlord who harasses, mistreats or retaliates against a commercial tenant to force the tenant to abrogate the lease would be subject to a fine of $2,000 for each violation. Further, any such violation would be an unlawful business practice and an act of unfair competition under Section 17200 of the Business and Professions Code and would be subject to all available remedies or penalties for those actions under state law.
When is a commercial tenant required to pay unpaid rent due to COVID-19?
If a commercial tenant fails to pay rent during the emergency COVID-19 order, the sum total of the past due rent must be paid within 12 months following the date of the end of the emergency proclamation, unless the commercial tenant has successfully negotiated an agreement with its landlord to pay the outstanding rent at a later date. Nonpayment of rent during the state of emergency cannot be used as grounds for eviction. Notwithstanding lease terms to the contrary, landlords may not impose late charges for rent that became due during the state of emergency.
Are landlords required to provide notice of protections adopted under SB 939?
Landlords would be required to provide notice to commercial tenants of the protections offered under SB 939 within 30 days of the effective date. SB 939 does not preempt local legislation or ordinances restricting the same or similar conduct which impose a more severe penalty for the same conduct. Local legislation or ordinances may impose additional notice requirements.
Does SB 939 impose new protections for commercial tenants when negotiating lease modifications?
If enacted, SB 939 would permit commercial tenants to open negotiations for new lease terms, and provide commercial tenants the ability to terminate the lease if those negotiations fail. A commercial tenant who wishes to modify its commercial lease, may engage in good faith negotiations with its landlord to modify any rent or economic requirement regardless of the term remaining on the lease. The commercial tenant must serve a notice on the landlord certifying that it meets the required criteria, along with the desired modifications.
If the commercial tenant and landlord do not reach a mutually satisfactory agreement within 30 days, then within 10 days, the commercial tenant may terminate the lease without any liability for future rent, fees, or costs that otherwise may have been due under the lease by providing a written termination notice to the landlord. The commercial tenant would be required to pay previously due rent, in an amount no greater than the sum of the following: (1) the actual rent due during the emergency COVID-19 order, or a maximum of three months of the past due rent during that period, and (2) all rent incurred and unpaid during a time unrelated to the emergency COVID-19 order through the date of the termination notice. The payment is due within 12 months from date of the termination notice. The commercial tenant would be required to vacate the premises within 14 days of the landlord's receipt of the termination notice. Upon service of the notice, any lease, and any third party guaranties of the lease would terminate. If the landlord and commercial tenant reach an agreement to modify the lease, the commercial tenant would not have the option to later terminate the lease under this provision.
When is the next Senate Judiciary Committee Meeting for SB 939?
The Senate Judiciary Committee set a hearing for SB 939 on May 22, 2020 at 9:00 a.m. The Senate will livestream the hearing on its website at www.sen.ca.gov. Public comments or testimony may be submitted in writing to the Judiciary Committee by emailing Erica.porter@sen.ca.gov. Alternatively, the public may participate via telephone during the public comment period. Any changes to the Judicial Committee schedule may be found at: https://www.senate.ca.gov/calendar.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino Prevail on Summary Judgment
June 17, 2024 —
Linda Carter - Kahana FeldCongratulations to Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino for Prevailing on a Motion for Summary Judgment!
Irvine Partner Cinnamon J. Carr and Associate Brittney H. Aquino prevail on summary judgment in a slip and fall case venued in Riverside County!
Plaintiff filed a lawsuit alleging negligence against Kahana Feld’s client, a grocery store with over 50 stores throughout Southern California. Prior to Plaintiff’s fall, security cameras captured footage of a third-party customer picking up a case of water bottles near the entrance of the store. The customer tilted the case and water streamed to the floor. The customer then returned the leaky case to the pallet, picked up another case of water, and walked away. Approximately a minute and 10 seconds later, Plaintiff walked through the area, slipping on the spilled water.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
U.S. Codes for Deck Attachment
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFTed Cushman in Big Builder explained how “decks often collapse when the ledger attachment to the main house fails.” Now, codes require “positive attachment…a solid connection with closely spaced lag screws (or better yet, bolts)." Cushman demonstrated this pictorially in a detail. He also stated to make sure to fasten securely, remove siding, and install flashing.
Read the court decisionRead the full story...Reprinted courtesy of
Roadway Contractor Owed Duty of Care to Driver Injured Outside of Construction Zone
January 04, 2021 —
Garret Murai - California Construction Law BlogFor the roadway contractor it appeared to be an open and shut case:
Plaintiff car driver was stopped at a standard one-way “reversing lane closure” traffic control in which traffic going in one direction would be stopped while traffic going in the other direction was allowed to proceed, and then the procedure would be reversed.
Plaintiff, while stopped at the traffic control, was rear-ended by another vehicle driven by George Smithson. Smithson testified that he “must have looked off to the side” at some point prior to the collision because he did not see plaintiff’s vehicle before hitting it. He also testified that the primary reason the accident happened was that he was not paying attention and that he knew of no other cause of the accident.
For the roadway contractor you couldn’t ask for a better admission. And it ended in the trial court just the way you thought it would, with a win for the roadway contractor. That is, until it was appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Don’t Get Caught Holding the Bag: Hold the State Liable When General Contractor Fails to Pay on a Public Project
June 21, 2017 —
Sean Minahan - Construction Contractor AdvisorAccording to a quick Google search the term “holding the bag” comes from the mid eighteenth century and means be left with the onus of what was originally another’s responsibility. Nobody wants to be left holding the bag. But that is the situation our client (subcontractor) found themselves in when upon completion of a public project the general contractor went out of business before paying the remaining amount due and owing to our client.
Under Nebraska law, liens are not allowed against public projects. Instead the subcontractor is to make a claim on the payment and performance bond secured by the general contractor at the start of the project. In our case, the general contractor never secured a bond on which to make a claim; consequently leaving our client holding the bag.
Fortunately, we were able to hand the bag back to the State and obtain full payment for the services and materials provided.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Minahan, Lamson, Dugan and Murray, LLPMr. Minahan may be contacted at
sminahan@ldmlaw.com