Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The ARC and The Covenants
May 30, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Mike Collignon. Mike is a co-founder of the Green Builder Coalition. The Green Builder® Coalition amplifies the voice of green builders and professionals to drive advocacy and education for more sustainable building practices.
As we start to see signs of a housing recovery, slow as it may be, I feel the industry is in a great position. All the effort put in by so many to improve our energy codes, green building programs & rating systems will finally be able to bear fruit. We can start to build homes that are much more environmentally responsible. Sure, we can have a lengthy debate about implementation and adoption rates, but you’ve got to walk before you can run. Unfortunately, I can see that progress getting shackled by an unexpected impediment: the architectural review committee (ARC; sometimes called “architectural committee” or “architectural control authority”) and the covenants of a homeowners’ association.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Evaluating Smart Home Technology: It’s About More Than the Bottom Line
May 03, 2021 —
James W. McPhillips & Rachel Newell - Gravel2Gavel Construction & Real Estate Law BlogOutfitting a commercial real estate space with smart technology can be a significant cost. While the long-term benefits and strategic improvements we’ve discussed previously can make that investment worthwhile, the evaluation period is critical to ensure an impactful ROI. Property developers, owners, and managers should undertake a rigorous evaluation process to ensure the technology procurement aligns with the project’s overall financial plan. And this is not just about getting the cost right. If the technology does not meet the needs of the space, then all the smart technology in the world will not prevent the project from being a sunk cost.
Do the Research so You Know …
The Technology. While the RFP is a key step of the procurement process, a more informal research phase should be undertaken first. Smart technology is a rapidly evolving field, and before reaching out to vendors, the business should ensure that it understands what is available—both in terms of the kinds of technology that can be implemented, and the various companies that offer solutions. Gathering this information early will yield results that align more closely with a particular building’s needs.
Reprinted courtesy of
James W. McPhillips, Pillsbury and
Rachel Newell, Pillsbury
Mr. McPhillips may be contacted at james.mcphillips@pillsburylaw.com
Ms. Newell may be contacted at rachel.newell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Finding Plaintiff Intentionally Spoliated Evidence, the Northern District of Indiana Imposes Sanction
March 14, 2018 —
Shannon M. Warren – The Subrogation Strategist On January 23, 2018, the Northern District of Indiana issued a decision that clarifies what constitutes spoliation of evidence under Indiana law. In
Arcelormittal Ind. Harbor LLC v. Amex Nooter, LLC, 2018 U.S. Dist. LEXIS 10141 (N.D. Ind.), the defendant filed a motion for sanctions, alleging that the plaintiff intentionally spoliated critical evidence. The defendant sought dismissal of the action, asserting that the plaintiff intentionally discarded and lost important physical evidence within hours of a fire that occurred while the defendant’s employees were performing work at its facility. The decision underscores the importance of taking immediate action to properly identify and secure potentially material evidence in order to satisfy ones duty to preserve pre-suit evidence and avoid any spoliation defenses and associated sanctions.
In
Arcelormittal, the court initially considered whether to apply state or federal law when analyzing a litigant’s duty to preserve pre-suit evidence and determine if that party committed spoliation. Since the case was brought in federal court based on diversity jurisdiction, the court held that Indiana state law governed the spoliation analysis.
As noted by the court, under Indiana state law, “the intentional destruction, mutilation, altercation, or concealment of evidence” is considered to be spoliation. Thus, under Indiana law, a party who knew or should have known that litigation was imminent “may not lose, destroy or suppress material facts or evidence.” The plaintiff argued that Indiana law requires a showing of improper purpose or bad faith to establish that a litigant spoliated evidence. The
Arcelormittal court rejected the plaintiff’s argument.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
South Carolina Supreme Court Finds that Consequential Damage Arise From "Occurrence"
October 10, 2013 —
Tred Eyerly — Insurance Law HawaiiThe South Carolina Supreme Court held that continuing damage that was part of a continuum of property damage constituted an "occurrence." Auto-Owners Ins. Co. v. Rhodes, 2013 S.C. LEXIS 248 (Sept. 25, 2013).
Rhodes hired Eadon to design, fabricate, and erect three outdoor advertising signs on Rhodes' property bordering an interstate highway. After the signs were erected, one fell across the highway, blocking both lanes of southbound traffic. The state Department of Transportation ordered Rhodes to remove the remaining two signs and revoked Rhodes' permit to maintain signs on the property.
Rhodes sued Eaton. Eaton's insurer, Auto-Owners, filed a declaratory judgment action to determine whether there was coverage under the CGL policy. The trial court found the sign falling on the interstate constituted an "occurrence" that resulted in damages beyond the defective work to property other than the defective work itself.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Project-Specific Policies and Products-Completed Operations Hazard Extensions
May 31, 2021 —
Jeremiah M. Welch - Saxe Doernberger & Vita1. Understanding the “Products-Completed Operations Hazard”
ISO commercial general liability (“CGL”) policies use the term “products-completed operations hazard” (“PCOH”) to define a category of risk which is treated specially by certain exclusions within the policy and often subject to separate limits of insurance. In construction, we think about PCOH as being about coverage for completed work.
Bodily injury and property damage arising out of completed work is a significant construction risk. Most construction contracts include warranty and indemnity obligations for completed work. All states allow lawsuits to be brought alleging bodily injury or property damage because of completed work based on common law. Contract and common law claims are subject to statutes of limitation – laws which define the time in which suits must be brought. Most states provide exceptions to their statutes of limitation for common law claims – the most common example is an extension to file a lawsuit based on a latent defect until the defect is discovered. Most states also have “statutes of repose” – laws that set a date after which suit may no longer be brought, no matter what the circumstances are. A construction contractor, therefore, has potential liability until the statute of repose period has expired. Thus, a contractor looks to ensure that it has coverage for the PCOH for its full statute of repose liability period.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremiah M. Welch, Saxe Doernberger & VitaMr. Welch may be contacted at
JWelch@sdvlaw.com
Ohio: Are Construction Defects Covered in Insurance Policies?
January 09, 2015 —
Beverley BevenFlorez-CDJ STAFFAmanda M. Leffler of Brouse McDowell analyzed Ohio’s 2012 Supreme Court case Westfield Ins. Co. v. Custom Agri Sys., Inc., which ruled that “’[c]laims of defective construction or workmanship brought by a property owner are not claims for ‘property damage’ caused by an ‘occurrence’ under a commercial general liability policy.’”
Leffler stated that the Ohio Supreme Court decision wasn’t as “sweeping” as it might at first appear: “Rather, the Ohio Supreme Court adopted the rule that construction defects are covered ‘occurrences’ within the meaning of commercial general liability (‘CGL’) policies, but only to the extent that property other than the policyholder’s own work is damaged.“
Read the court decisionRead the full story...Reprinted courtesy of
Massive Danish Hospital Project Avoids Fire Protection Failures with Imerso Construction AI
December 23, 2023 —
Aarni Heiskanen - AEC BusinessEnsuring regulatory compliance of firewall constructions is getting a high-tech boost. Over the past 16 months, the construction team responsible for the iconic new Nyt Hospital Nordsjælland near Copenhagen used Imerso construction AI technology to achieve remarkable results. By using Imerso, the team enhanced work productivity while preventing costs and delays worth €5.2 million during the construction of the superstructure.
Inspired by this success, the team led by Project Manager Anders Kaas has since been eager to explore the potential of the technology in other areas. The opportunity arose to address a topic that has traditionally posed significant challenges and expenses in numerous construction projects – ensuring regulatory compliance of fire barriers and firewall constructions.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi