Not All Work is Covered Under the Federal Miller Act
May 24, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion out of the Eastern District Court of Virginia, Dickson v. Forney Enterprises, Inc., 2021 WL 1536574 (E.D.Virginia 2021), demonstrates that the federal Miller Act is not designed to protect ALL that perform work on a federal construction project. This is because NOT ALL work is covered under the Miller Act.
In this case, a professional engineer was subcontracted by a prime contractor to serve on site in a project management / superintendent capacity. The prime contractor’s scope of work was completed by January 31, 2019. However, the prime contractor was still required to inventory certain materials on site, which was performed by the engineer. The engineer claimed it was owed in excess of $400,000 and filed a Miller Act payment bond lawsuit on February 5, 2020 (more than a year after the project was completed).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Seattle Developer Defaults on Renovated Office Buildings
December 23, 2024 —
Anna Edgerton - BloombergA major developer in downtown Seattle defaulted on a loan backed by two of its most prized office properties, including one that formerly housed a branch of the Federal Reserve Bank of San Francisco.
Firms tied to Martin Selig Real Estate are in default on a more than $200 million loan, according to letters from lender Acore Capital dated Nov. 15 that were filed in Washington’s King County. The buildings would change ownership 30 days after that notice if no other action is taken, according to the letters.
Read the court decisionRead the full story...Reprinted courtesy of
Anna Edgerton, Bloomberg
Aecmaster’s Digital Twin: A New Era for Building Design
May 06, 2024 —
Aarni Heiskanen - AEC BusinessI sat down with Anssi Auvinen, the CEO and founder of Finnish startup Aecmaster, to discuss the future of design and how the company plans to make it happen. Anssi envisions data-driven design as the next radical change in the AEC sector.
Anssi Auvinen started working in the building industry as a 16-year-old construction worker. Since then, he has acquired two master’s degrees: structural engineering and architecture.
During his career, Anssi has witnessed how the digitalization of the design sector has progressed, but the results for both designers and building owners could have been more impressive. That inspired him in 2019 to start up
Aecmaster, a software and consulting firm that aims to fulfill the promise of digitalization. The company’s software product launched in January 2024.
The need for digital twins
Anssi states that you can’t say you own a building until you possess its digital assets, the digital twin.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Lower Manhattan Condos Rival Midtown’s Luxury Skyscrapers
April 09, 2014 —
Oshrat Carmiel – BloombergManhattan developer Bill Rudin hadn’t planned to start selling apartments at his Greenwich Village project until the end of this year. He began rethinking that strategy after getting cornered at a cocktail party.
“People came up to me and said, ‘We want to buy, we want to buy. When can we buy?’” Rudin said in an interview.
He opened a sales office in October for the Greenwich Lane, a complex under construction at the site of the shuttered St. Vincent’s Hospital, after an online sign-up list of would-be buyers for the 200 condominiums drew 1,100 names. More than half of the units at the development, still largely a field of dirt and skeletal towers, have sold at prices averaging $3,500 a square foot, in line with other projects downtown and a new luxury benchmark for the area.
While Midtown skyscrapers fringing Central Park are setting sales records and attracting international investors, downtown Manhattan’s new condos are breaking their own price barriers with a focus on local buyers. From the cobblestone streets of Tribeca to the low-rise landmarks of Greenwich Village, builders are accelerating projects with features and costs that rival high-end offerings farther north.
Read the court decisionRead the full story...Reprinted courtesy of
Oshrat Carmiel, BloombergMs. Carmiel may be contacted at
ocarmiel1@bloomberg.net
Federal Court Dismisses Coverage Action in Favor of Pending State Proceeding
October 12, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court declined to exercise jurisdiction over the coverage action that was parallel to a case pending in state court involving the same parties and same issues pending. Navigators Ins, Co. v. Chriso's Tree Trimming, 2020 U.S. Dist. LEXIS 129711 (E.D. Calif. July 22, 2020).
Pacific Gas & Electric (PG&E) entered into a tree, brush and wood removal contract with Mount F Enterprises, Inc. Mountain F subsequently entered into a subcontractor agreement with Chriso Tree Trimming, Inc. for work to be performed for PG&E. In August 2017, Chriso attempted to remove a tree, but the tree accidentally fell in the wrong direction and knocked down nearby powerlines. The powerlines came into contact with surrounding brush and started the "Railroad Fire." The fire was eventually contained on September 15, 2017, after 12, 407 acres were burned and 7 structures and 7 homes were destroyed.
Five subrogation lawsuits were filed in state court against Chriso and Mountain F by various insurance companies that paid for the damage caused by the Railroad Fire. A policy limits demand to settle all claims against Chriso and Mountain F was made. Navigators insured Chriso for $9 million through a Commercial Excess Liability Policy, payable once all other insurance was exhausted. The policy included a "Professional Services Endorsement" (PSE Exclusion) that excluded coverage of "professional services." "Professional services" was defined through a list of 12 non-exclusive professions and services that generally referred to activities involving specialized knowledge or skill that was predominantly mental or intellectual in nature rather than physical or manual.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Reminder: Just Being Incorporated Isn’t Enough
June 29, 2020 —
Christopher G. Hill - Construction Law MusingsI have discussed why contractors need to incorporate previously here at Construction Law Musings. Among the many reasons to incorporate are possible tax benefits and the protection of personal assets (like your house and your dog) from judgement and collection actions. This latter reason is key in the construction world in which Murphy can look like an optimist and projects have so many moving parts that something is likely to go wrong.
The reason incorporation works as at least a partial shield is that the company and the owners are separate “people” or entities from a legal perspective and a contract with one “person” cannot be enforced against another. This same logic applies in the context of corporate versus individual actions, i. e. the actions of one person cannot be legally attributed to another person. By extension the assets of an individual cannot be collected to satisfy a purely corporate debt or judgment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Sometimes a Reminder is in Order. . .
February 18, 2020 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Needless to say, the Court rejected both arguments. The Court rejected the first argument stating:
In its plain meaning, “employ” means to hire, use, utilize, or make arrangements for. A plain reading of the contractual provisions cited–“shall employ” and references to “employees”–and relied on by Defendant does not require that the persons performing the labor, arranged by Plaintiff, be actual employees of the company or on the company’s payroll. It did not matter how the plaintiff accomplished the work so long as it was done correctly. The purpose of those provisions was to allocate to Plaintiff responsibility for supplying a sufficient workforce to get the work done, not to impose HR duties or require the company to use only “in house” workers. So I find that use of contracted work does not constitute a breach of the contract or these contractual provisions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
ASHRAE Seeks Comments by May 26 on Draft of Pathogen Mitigation Standard
May 22, 2023 —
James Leggate - Engineering News-RecordASHRAE, the professional group focused on research and standards development for heating, ventilation, air conditioning and air conditioning systems, is seeking comments on the first draft of a standard for pathogen mitigation, it announced May 15. ASHRAE will accept comments on the
public review draft, via
osr.ashrae.org, through May 26.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of