When Can Customers Sue for Delays?
September 18, 2023 —
Scott L. Baker - Los Angeles Litigation BlogConstruction projects are subject to many internal and external factors. Due to this, delays are not an uncommon occurrence. Whether delays are the result of bad weather conditions or supply chain issues, contractors and their clients cannot control every aspect of the project.
Delay issues are very
common construction disputes. Therefore, new and experienced contractors alike need to know when their clients may have a reason for a delay claim.
2 particular types of delays that pose a risk
Common obstacles that contractors faced during the height of the COVID-19 global pandemic involved supply chain issues. The lack of materials put various projects on hold across California and the country. This widespread issue was out of contractors’ and clients’ control, meaning they were excusable delays.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Sustainability Puts Down Roots in Real Estate
January 27, 2020 —
Stephanie Amaru - Gravel2Gavel Construction & Real Estate Law BlogSustainability has evolved from a passing trend or niche preference into an undeniable, growing driver of the real estate market. This is particularly true as millennials comprise an increasing proportion of the workforce, home-buying population, and individuals influencing the future of real estate development in the United States.
If anything illustrates the significance of younger generations’ increasing interest in sustainability, it is the Global Climate Strike that drew participation of many thousands of young people, with 2,500 events scheduled in over 150 countries. In New York City, 1.1 million public school students were excused from school to join the strike in an event planned to precede the UN Summit, which itself was intended to push countries toward a commitment to faster transition to renewable energy and stricter climate targets. While both policymakers and citizens of previous generations have been split on their willingness to address global climate change with urgency, younger generations are feeling a stronger sense of responsibility for curbing the world’s trajectory towards a climate catastrophe, which will be inherited by them and their children. This has manifested in action that promotes awareness of and political action with respect to these issues—such as the Global Climate Strike—as well as evolving habits and preferences in both consumer goods and real estate.
Greener Space
In recent years, real estate developers have recognized that there is a market for “greener” developments that reduce annual expenditures on buildings, whether it be through small spaces requiring less electricity and promoting energy efficiency, or through renewable energy options such as solar photovoltaic power. Some real estate developers have chosen to install these options themselves, while others seek out sustainable financing options to cover the costs of renewable energy. If installing renewable energy is too costly, real estate developers will seek out more cost-effective locations for their brick-and-mortar operations.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Amaru, PillsburyMs. Amaru may be contacted at
stephanie.amaru@pillsburylaw.com
New Insurance Case: Owners' Insurance Barred in Reimbursement Action against Tenant
April 17, 2019 —
Jason Adams - Gibbs GidenThe Western Heritage Ins. Co. v. Frances Todd, Inc. (2019 Cal.App. LEXIS 299 / 2019 WL 1450731) case has potential implications for insurance carriers, policyholders, condominium associations, unit owners, landlords and tenants.
The case involves a fire at a commercial condominium complex (the “Association”). The Association’s CC&Rs required the Association to purchase a master fire insurance policy for the benefit of the Association and owners, with a waiver of subrogation endorsement that stated the insurance company could not seek reimbursement from the Association, its officers, owners or occupants of the units in the event of a covered fire. The CC&Rs also prohibited individual owners from obtaining their own fire insurance. The Association purchased the required fire insurance policy from Western Heritage Insurance Company (“Western Heritage”).
One of the owner’s tenants, Frances Todd, Inc. (“Frances Todd”), allegedly caused a fire that damaged several units. Although the unit owner was covered as an additional named insured under the Western Heritage fire policy, the tenant, Frances Todd, was not. Western Heritage paid for the common area fire damage caused by Francis Todd, and then sued Frances Todd in a subrogation action to recover the amounts paid.
Read the court decisionRead the full story...Reprinted courtesy of
Jason M. Adams, Gibbs GidenMr. Adams may be contacted at
jadams@gibbsgiden.com
Fifth Circuit: Primary Insurer Relieved of Duty to Defend Without Release of Liability of Insured
March 02, 2020 —
Bethany L. Barrese & Ashley McWilliams - Saxe Doernberger & Vita, P.C.In Aggreko, LLC v. Chartis Specialty Ins. Co.,1 the Fifth Circuit affirmed a decision by the Texas District Court and held that a Covenant Not to Execute constituted a “settlement” sufficient to exhaust policy limits and terminate a primary insurer’s duty to defend.
This case arose out of a wrongful death suit filed by the parents of James Brenek II (“Brenek”). In 2014, Brenek was fatally electrocuted by an electrically energized generator housing cabinet while performing work on a rig in Texas for Guichard Operating Company, LLC (“Guichard”), a Louisiana-based drilling subcontractor. Guichard had leased the generator from Aggreko, LLC (“Aggreko”). A rental agreement between Guichard and Aggreko required Guichard to maintain commercial general liability insurance during the lease period and list Aggreko and the rig owner, Rutherford Oil Corporation (“Rutherford”), as additional insureds under
the policy.
Guichard’s primary insurance carrier, The Gray Insurance Company (“Gray”), agreed to defend and indemnify Aggreko and Rutherford in the wrongful death suit. The Gray policy had a limit of $1,000,000, subject to a $50,000 self-insured retention.
Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C. and
Ashley McWilliams, Saxe Doernberger & Vita, P.C.
Ms. Barrese may be contacted at blb@sdvlaw.com
Ms. McWilliams may be contacted at amw@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Massive Danish Hospital Project Avoids Fire Protection Failures with Imerso Construction AI
December 23, 2023 —
Aarni Heiskanen - AEC BusinessEnsuring regulatory compliance of firewall constructions is getting a high-tech boost. Over the past 16 months, the construction team responsible for the iconic new Nyt Hospital Nordsjælland near Copenhagen used Imerso construction AI technology to achieve remarkable results. By using Imerso, the team enhanced work productivity while preventing costs and delays worth €5.2 million during the construction of the superstructure.
Inspired by this success, the team led by Project Manager Anders Kaas has since been eager to explore the potential of the technology in other areas. The opportunity arose to address a topic that has traditionally posed significant challenges and expenses in numerous construction projects – ensuring regulatory compliance of fire barriers and firewall constructions.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
How Robotics Can Improve Construction and Demolition Waste Sorting
September 11, 2023 —
Emily Newton - Construction ExecutiveCommercial construction projects generate a lot of waste. Managing this debris is crucial to minimizing the industry’s environmental impact, but it’s often a time-consuming and error-prone process. Robotic waste sorting provides a better alternative.
Why C&D Waste Management Must Improve
The current state of construction and demolition (C&D) debris management leaves considerable room for improvement. Nearly all C&D waste takes
decades to break down in landfills—and the sector generates hundreds of millions of tons of it annually.
More efficient debris management would help firms protect the environment and their bottom line. Poor waste management practices also take an economic toll. Recycling extends materials’ useful life, helping minimize resource costs. Inefficient waste sorting may additionally lead to unnecessarily high workforce expenses and incur lost business from firms’ lack of sustainability.
Reprinted courtesy of
Emily Newton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Clean Air, Clean Water, Citizen Suits and the Summer of 2022
November 01, 2022 —
Anthony B. Cavender - Gravel2GavelThis is a selection of significant environmental and regulatory law cases decided by the federal courts after the Supreme Court’s 2021 Term concluded.
The U.S. Court of Appeals for the DC Circuit
National Association of Broadcasters v. Federal Communications Commission
On July 12, 2022, the DC Circuit held that an order of the FCC requiring radio broadcasters to follow a prescribed five-step process to verify the identity of program sponsors was not authorized by the Communications Act. According to the court, the FCC “decreed a duty that the statute does not require, and that the statute does not empower the FCC to impose.” Here, the agency failed to identify the statutory authority it needed to authorize the issuance of such an order. While certainly not as significant as the Supreme Court’s ruling in West Virginia v. EPA, decided only a few days before this decision was released, it is a strong reminder that the courts want to know if a challenged rule is authorized by law.
Humane Society of the U.S., et al., v. U.S. Department of Agriculture
On July 22, 2022, the court decided a case involving the steps the Administrative Procedure Act and the Federal Register Act require to be taken before a final agency rule is legally promulgated. Customarily, when there has been a change in Presidential administrations, the incoming administration “quietly” withdraws rules awaiting Federal Register publication without much ceremony. The majority of this panel agreed that public notice should have been provided to the regulated community to comment on the new administration’s action to pull back a new rule which had been made available for public inspection before Federal Register publication that would have strengthened the protections afforded “show horses,” as now required by law. The court noted that “it seems clear that filing with the Federal Register constituted promulgation of a regulation even though publication may not occur until a later date.” Circuit Judge Rao filed a strong dissent. “By cutting off agency discretion at public inspection, the majority imposes judicial burden on agency procedures that conflicts with circuit precedent, the statutory framework and a longstanding regulation permitting withdrawals prior to publication.” There could be a further review of this unique ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Delaware Settlements with Minors and the Uniform Transfer to Minor Act
October 15, 2014 —
Stephen J. Milewski – White and Williams LLPAs a Delaware lawyer, one of the most frequently asked questions I get from insurance clients is: “Do all personal injury settlements with minors need to be approved by the Court?” The answer is and always has been yes. This is true regardless of the amount of the settlement. There have, however, been some recent changes under Delaware law which may help facilitate the process and even reduce the costs associated with settling small tort cases with minors. Traditionally, when settling cases with a minor, a Petition would be filed with the trial court (Superior Court) and then a hearing would be scheduled for the parties to present to the Court the terms of the settlement, explain the plaintiff’s injuries and itemize the fee breakdown. This would be the settlement approval process. After that, the plaintiff would be required to have a guardian appointed over the proceeds, which had to be approved by Chancery Court (Delaware’s Court of Equity). The purpose of this process was to ensure the settlement money going to the minor was managed properly; the net proceeds were generally placed into a bank account not to be used by the guardian or the minor until the minor reached the age of majority. To both the plaintiff, and the insurance carrier paying out the settlement, this process was burdensome and added disproportionate costs to small settlements.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen J. Milewski, White and Williams LLPMr. Milewski may be contacted at
milewskis@whiteandwiliams.com