No Coverage Under Ensuing Loss Provision
September 09, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe cost of removing and replacing cracked flanges to prevent future leakage was not covered as an ensuing loss under a builder’s risk policy in RK Mechanical, Inc. v. Travelers Prop. Casualty Co. of Am., 2011 U.S. Dist. LEXIS 83958 (D. Colo. Aug. 1, 2011).
The insured, RK Mechanical Inc., was a subcontractor hired to install plumbing for a residential construction project. RK was an additional insured on the general contractor’s policy with Travelers. RK installed approximately 170 CPVC flanges on the project. Subsequently, two of the flanges cracked, allowing water to overflow and causing water damage to the project. Travelers was notified of the flange failure and resulting water damage.
RK subsequently removed and replaced the two cracked flanges and began water remediation. Travelers paid for the cost of the water damage due to the cracked flanges.
RK then examined all of the flanges installed in the project and discovered many were cracked and/or showed signs of potential failure. RK removed and replaced the cracked flanges. RK tendered a claim and demand for indemnity to Travelers for these repair costs. Travelers denied the claim. RK then sued for breach of contract and declaratory relief. The parties filed cross motions for summary judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
New Iowa Law Revises Construction Defects Statute of Repose
September 07, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Starting July 1st of this year, Iowa homeowners now have only ten years to file a claim against the builder instead of the fifteen years that was allowed previously, reported WZAD 8 News. Furthermore, commercial property owners will only have eight years to file their suits.
Scott Webster, Vice President of the Quad Cities Builders and Re-modelers Association, told WZAD 8 News that insurance companies played a part in the change: “[I]nsurance companies were saying, Iowa is at such a long period of time for any kind of defect, that may be hard to prove whether the builder even did it or the homeowner modified the house.”
However, Tom Miller, Iowa Attorney General, disagreed with the change in policy: “We think that it’s unfair to consumers, the defects in buildings and commercial buildings too, can show up very easily between eight and fifteen years out.”
Read the court decisionRead the full story...Reprinted courtesy of
Inspectors Hurry to Make Sure Welds Are Right before Bay Bridge Opening
August 27, 2013 —
CDJ STAFFEach of the 20 welds at the base of the tower of the Bay Bridge took more than four hours to complete, with the lengthy welds forming at one-and-a-half inches per minute. They’ve been finished for two years now, but inspectors are just now checking the welds for defects.
Any defects found will have to be removed and repaired. Mazen Wahbeh, an engineer on the project, assumes that less than 5 percent of the total welded area will have to be repaired. According to Wahbeh, the bridge can open before the welds are thoroughly checked and repaired, and so “the contractor is prioritizing the remaining work.”
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 and Mutual Responsibility Clauses
June 01, 2020 —
Joseph M. Leone - ConsensusDocsAs everyone knows, there is a tremendous amount of uncertainty in the construction industry due to the COVID-19 pandemic. Schedules, productivity, safety processes, and seemingly everything else are being affected. In these difficult times, most contractors are making every effort to work together to solve the problems caused by COVID-19. But what happens when differences arise between project owners, contractors, and subcontractors as to the effect of COVID-19 on a project? One party may want to continue pushing the schedule, others may want to slow down, or, more likely, not be able to keep up with the original schedule because of some reason related to COVID-19. As between a prime contractor and a subcontractor, a mutual responsibility clause can provide some clarity or, unfortunately, depending on how the subcontract is written, confusion.
Almost all subcontracts have a clause which flows down the prime contractor’s obligations on a project to the subcontractor as applicable to the subcontractor’s work. Known as “flow-down” clauses, this clause works in one direction; obligations of the prime contractor “flow-down” to the Subcontractor. A mutual responsibility clause, in essence, works in both directions. The subcontractor is required to perform its obligations consistent with the prime contractor’s obligations to the owner and the subcontractor is granted the same rights against the prime contractor which the prime contractor has against the owner. Obligations flow down and rights flow up. The rights and obligations flowing through the prime contractor include, the obligation to perform the work in accordance with the plans and specifications, the obligation to meet the schedule constraints in the prime agreement, and the right to extensions of time and change orders to the extent the prime contractor obtains the same.
Read the court decisionRead the full story...Reprinted courtesy of
Joseph M. Leone, Drewry Simmons Vornehm, LLP Mr. Leone may be contacted at
jleone@dsvlaw.com
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Loan Snarl Punishes Spain Builder Backed by Soros, Gates
July 30, 2014 —
Katie Linsell, Manuel Baigorri and Ruth David – BloombergPressure is mounting on Esther Koplowitz to refinance personal loans before a deadline tomorrow and allow a Spanish builder that counts Bill Gates and George Soros among investors to resolve its own debt tangle.
Koplowitz is renegotiating about 1 billion euros ($1.8 billion) of debt tied to her controlling stake in Fomento de Construcciones & Contratas SA, according to two people familiar with the matter, who asked not to be identified because it’s private. Her determination to retain control means that she is unlikely to approve any plan by FCC to raise equity until she refinances her own debt, the people said.
Ms. Linsell may be contacted at klinsell@bloomberg.net; Mr. Baigorri may be contacted at mbaigorri@bloomberg.net; Ms. David may be contacted at rdavid9@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Katie Linsell, Manuel Baigorri and Ruth David, Bloomberg
London Penthouse Will Offer Chance to Look Down at Royalty
March 05, 2015 —
Zainab Fattah – Bloomberg(Bloomberg) -- A penthouse “overlooking the Queen’s balcony” will cap a London luxury apartment project planned near Buckingham Palace, according to its Abu Dhabi-based owner.
The 10,000 square-foot (929 square-meter) apartment at No. 1 Palace St. across the street from the royal residence will probably fetch about 60 million pounds ($92 million), Jassim Alseddiqi, chief executive officer of Abu Dhabi Financial Group LLC, said in an interview in the capital of the United Arab Emirates on Monday.
Read the court decisionRead the full story...Reprinted courtesy of
Zainab Fattah, BloombergMs. Fattah may be contacted at
zfattah@bloomberg.net
Indiana Federal Court Holds No Coverage for $50M Default Judgment for Lack of Timely Notice of Class Action
August 26, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Greene v. Kenneth R. Will, a CGL insurer recently prevailed in a declaratory judgment action arising from an underlying class action alleging pollution and nuisance claims against the insured, VIM Recycling LLC, an Indiana-based waste-recycling facility.[1] “[T]his case has some whiskers on it,” the Indiana federal district court recounted in its exhaustive decision granting the insurer relief. The court relieved the insurer of indemnifying a $50 million default judgment against the insured, which, the court observed, “proved to be a bad neighbor” and “nuisance in both the legal and colloquial sense.” The court held that the insured failed to provide timely notice of the class action.
“The judgment against the [insured] came about when a group of nearby homeowners decided that they had had enough of VIM’s polluting behavior and brought this class action to recover damages for environmental violations, nuisance and negligence based on the impact of the waste facility on their homes and property,” the court explained. Eventually, the court entered a default judgment against the insured for $50,568,750, plus an award of $273,339.85 in attorney’s fees. Because the insured was “judgment-proof,” the class action plaintiffs “aligned” with the insured “hoping to collect on their monumental judgment” from the insured’s CGL insurer. Within a few weeks’ time, the class action plaintiffs sued the insurer seeking a declaration of coverage for the default judgment against the insured.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com