Construction Worker Falls to His Death at Kyle Field
January 15, 2014 —
Melissa Zaya-CDJ STAFFThe family of Angel Garcia, a construction worker who fell to his death while working on Texas A&M’s football stadium (Kyle Field), has filed a $100 million lawsuit against six construction companies claiming inadequate safety policies, procedures, and negligence, Jordan Overturf of The Eagle reported.
According to The Eagle, Garcia’s attorneys alleged, “[Garcia] was ‘catapulted off the edge of a fourth-floor ramp’ on the northeast side when a section of concrete fell onto the bucket of the skid steer-loader he was operating. The tractor hit a steel beam during the fall, which exerted enough force to eject Garcia from the tractor.” Garcia did not survive his injuries. The complaint claims the companies involved violated the Occupational Safety and Health Administration rules and regulations. The defendants in the suit were unavailable for comment, according to The Eagle.
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Tower Opponents to Try Mediation
June 28, 2013 —
CDJ STAFFThere are plenty of issues on the table in the fight between CityCenter and Tutor Perini over the Harmon Tower project in Las Vegas. Some of them might be solved at a mediator’s table instead of reaching the courtroom.
Both sides will be participating in a six-day negotiation with an outside mediator. Their hope is that the projected two-year jury trial can be reduced to only one year. The judge in the case remains skeptical. “It ain’t happening. I know you all,” was Clark County District Judge Elizabeth’s Gonzalez’s comment.
Read the court decisionRead the full story...Reprinted courtesy of
All Risk Policy Only Covers Repair to Portion of Dock That Sustains Damage
January 06, 2012 —
Tred R. Eyerly - Insurance Law HawaiiA portion of a dock on Lack Michigan operated by the Ports of Indiana suffered visible damage. See Ports of Indiana v. Lexington Ins. Co., 2011 U.S. Dist. LEXIS 130979 (S.D. Ind. Nov. 14, 2011). Lexington Insurance Company insured the port. Lexington agreed that a portion of the dock was damaged and paid $1.2 million for repairs. A dispute arose, however, over whether additional sections of the dock were damaged and whether the damage was the result of more than one "occurrence."
An expert report opined that a significant drop creating record lows in the water level of Lake Michigan in 2007 caused damage to the dock. Lexington maintained that only 128 feet of the dock was damaged; other portions of the dock did not sustain "direct physical loss or damage."
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Additional Dismissals of COVID Business Interruption, Civil Authority Claims
December 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAmong the recent decisions dismissing complaints for business interruption and civil authority coverage due to closures caused by COVID-19 are Pappy's Barber Shops, Inc. v. Farmers Group, Inc., 2020 U.S. Dist. LEXIS 166808 (S.D. Calif. Sept. 11, 2020) and Sandy Point Dental v. Cincinnati Insurance Co., 2020 U.S. Dist. LEXIS 171979 (E.D. Ill. Sept. 21, 2020). The difficulty in proving "direct physical loss" was the downfall of both cases.
In Pappy's, claims were made for business income losses insured as a result of local and state closure orders. The policy required "direct physical loss of or damage to property at the described premises." Plaintiffs argued that "direct physical loss of" did not require a tangible damage or alteration to property and that the loss of the ability to continue operating their businesses as a result of the government orders met this requirement.
The court relied upon a prior decision, 10E, LLC v. Travelers Indem. Co. of Connecticut, 2020 U.S. Dist. LEXIS 165252 (C.D. Calif. Sept. 2, 2020) [post here], where the court noted that under California law, losses from inability to use property did not amount to "direct physical loss" within the meaning of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Contract’s Scope of Work Should Be Written With Clarity
March 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesThe scope of work section in your construction contract should never be overlooked. In numerous instances, it is overlooked which leads to a dispute as to the precise nature of the scope of work. This dispute could be the result of an ambiguity in the scope of work section. Or it could be the result of an omission. Or it could be the result of a lack of clarification. Or it could be the result of not properly reviewing and vetting the scope of work section. This is a section—whether included in the body of your contract or attached as an exhibit—you absolutely, positively want clarity. Otherwise, you are potentially setting yourself up for a future dispute that could include (i) an additional work / change order dispute, (ii) an incomplete work dispute, or (iii) a failure to properly perform your work dispute. These are all disputes you want to avoid, and many times can avoid, by going through and negotiating the scope of work section to bring clarity to this section. Remember, clarity is a positive. Ambiguity or uncertainty is a negative.
An example of such an avoidable scope of work dispute can be found in All Year Cooling and Heating, Inc. v. Burkett Properties, Inc., 2023 WL 2000991 (Fla. 4th DCA 2023). Here, an air conditioning contractor was hired to install six new split air conditioning systems. The scope of work provided that there were currently “two split systems that are currently existing, working perfectly and are not to be replaced as part of this contract.” The property manager claimed the air conditioning contractor was required to bring these two existing split air conditioning systems up to code as the contract provided that notwithstanding anything to the contrary, the contractor “will certify and shall ensure that all split systems in the building, upon completion of all the work, will be fully compliant with all codes and regulations and shall be responsible for any costs relates to the implementation and/or remediation of same.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
ASBCA Validates New Type of Claim Related to Unfavorable CPARS Review [i]
May 03, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCFor government contractors, an unfavorable performance rating review posted to the Contractor Performance Assessment Reporting System (“CPARS”) can be extremely costly. Many of the government-negotiated solicitations include past performance as an important, and sometimes even primary, evaluation factor for contract award. An unfavorable CPARS review on a past contract can cause the contractor to incur substantial extra costs in addressing the unfavorable review with contracting officers on future solicitations, and, in some instances, the contractor saddled with an unfair or inaccurate CPARS may have to challenge the review and recover some of these costs.
Both the Federal Court of Claims and the Armed Services Board of Contract Appeals (“ASBCA”) have held that they have jurisdiction to hear Contract Dispute Act claims regarding unfair and/or inaccurate CPARS review. The relief available to contractors until this year was a declaration from the Court of Claims or Board that an unfair or inaccurate CPARS review was arbitrary and capricious. Neither the Board nor the Court had the authority or power to order the contracting officer to change the unfavorable review. The contractor who received a declaration from the Court or the Board regarding an unfavorable CPARS review may use it in the future to explain the unfavorable review when bidding new government work; however, the unfavorable review remains in the CPARS system and shows up on all future solicitations, the Board or Court decision notwithstanding.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
S&P 500 Little Changed on Home Sales Amid Quarterly Rally
July 01, 2014 —
Lu Wang and Jacob Barach – BloombergJune 30 (Bloomberg) --The Standard & Poor’s 500 Index was little changed, capping the longest string of quarterly gains since 1998, as a jump in pending home sales offset weaker-than-forecast manufacturing data.
D.R. Horton Inc. rallied 3.2 percent, leading gains among homebuilders. Yahoo! Inc. (YHOO) rose 2.6 percent after Piper Jaffray Cos. recommended buying the stock. MannKind Corp. jumped 9.6 percent as the maker of diabetes drugs rebounded from its worst week in two months. Allergan Inc. declined 2.7 percent following regulatory decisions on its drugs.
The S&P 500 fell less than 0.1 percent to 1,960.23 at 4 p.m. in New York. The equity benchmark gauge rose 4.7 percent for the quarter, a sixth consecutive advance. The Dow Jones Industrial Average lost 25.24 points, or 0.2 percent, to 16,826.60 today, trimming its quarterly advance to 2.2 percent. The Nasdaq Composite Index rose 0.2 percent, giving it a 5 percent increase for the three months.
Ms. Wang may be contacted at lwang8@bloomberg.net; Mr. Barach may be contacted at jbarach1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Lu Wang and Jacob Barach, Bloomberg
Fire Tests Inspire More Robust Timber Product Standard
March 22, 2018 —
Nadine M. Post– ENRBased on recent fire test results, mass timber groups have adjusted product certification standards to require the use of cross-laminated timber with structural adhesives tested to demonstrate better fire performance.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com