MGM Begins Dismantling of the Las Vegas Harmon Tower
June 26, 2014 —
Beverley BevenFlorez-CDJ STAFFMGM has begun to dismantle the $8.5 billion, incomplete Harmon Hotel in Las Vegas, Nevada, according to the Las Vegas Review-Journal. The demolition process is expected to take up to a year.
The Las Vegas Review-Journal reported that construction of the tower was halted in 2008 after construction defects were allegedly discovered. Later, “the building was deemed structurally unsound.”
“Instead of blowing the building up in grand fashion, contractors hired by MGM Resorts are now removing scrap metal and other materials from the building, along with taking off the blue-tinged glass that has covered the structure for the last five years,” Howard Stutz wrote in the Las Vegas-Review Journal. “The process also includes installing pedestrian protection systems outside the structure above adjacent sidewalks and walkways.”
Read the court decisionRead the full story...Reprinted courtesy of
Manhattan’s Property Boom Pushes Landlords to Sell Early
August 26, 2015 —
Sarah Mulholland – BloombergManhattan property owners are cashing out ahead of schedule.
With New York real estate values and rents surging, owners of commercial properties acquired as recently as a year ago are already seeking buyers. In the case of one Midtown site, the developer scrapped construction plans to sell an empty plot of land.
There’s so much buyer demand that in some situations it’s more opportune for landlords to sell rather than follow through on plans for redevelopment or filling buildings with new tenants. A record $29.4 billion of Manhattan property deals were completed in the first half of 2015, according to brokerage Jones Lang LaSalle Inc., part of a five-year real estate rally that’s pushed prices to new highs in big U.S. cities.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Mulholland, Bloomberg
Higgins, Hopkins, McLain & Roswell, LLC Announces Leadership Changes and New Vision for Growth
January 21, 2025 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCHiggins, Hopkins, McLain & Roswell, LLC (“HHMR”) is excited to announce several significant developments as the firm transitions into an exciting new chapter of growth and innovation. Sheri Roswell, one of the firm’s founding members, is stepping out of ownership to serve as “Of Counsel,” continuing her vital work with clients and strengthening relationships that have been the cornerstone of HHMR’s success. Her tireless contributions since the firm’s inception have helped establish HHMR as a leader in Colorado’s construction law landscape.
“Sheri has been a pillar of HHMR since day one. Her commitment to our clients and her unwavering dedication to the firm’s success have left an indelible mark. We are excited for her to continue contributing her expertise and leadership in this new capacity,” said David McLain at the firm’s recent holiday celebration.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Break out the Neon: ‘80s Era Davis-Bacon “Prevailing Wage” Definition Restored in DOL Final Rule
August 21, 2023 —
A. Scott Hecker & Ted North - The Construction SeytOn August 8, 2023, the U.S. Department of Labor (DOL)
announced its
final rule related to the Davis-Bacon Act (the “Act”), entitled “Updating the Davis-Bacon and Related Acts Regulations.” However, the official final rule must be published in the Federal Register – likely by week’s end – before going into effect 60 days after publication.
DOL issued its notice of proposed rulemaking (“NPRM”) in March 2022 and received more than 40,000 comments from interested stakeholders. Evaluating and addressing those comments took the better part of a year, as DOL did not send the rule to the Office of Information and Regulatory Affairs (“OIRA”) for White House approval until December 16, 2022. After languishing for months, OIRA has now concluded its review, allowing DOL to move forward with its final rule.
Reprinted courtesy of
A. Scott Hecker, Seyfarth and
Ted North, Seyfarth
Mr. Hecker may be contacted at shecker@seyfarth.com
Mr. North may be contacted at enorth@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of
How Are You Dealing with Material Delays / Supply Chain Impacts?
June 07, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a prior article I discussed a material escalation provision in your construction contract to account for the volatility of the material price market. While including such a provision may not have been much of a forethought before, it is now!
What about concerns with the actual supply chain that impacts the availability of and the lead time of materials? How are you addressing this concern in your construction contract?
The pandemic has raised awareness to this issue as certain material availability has been impacted by the pandemic. As a result, parties in construction have tried to forecast those materials where delivery issues may occur including those materials with longer than expected lead times. But equally important is how this issue is being addressed in your construction contract including how you want to negotiate this risk in future construction contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California’s Fifth Appellate District Declares the “Right to Repair Act” the Exclusive Remedy for Construction Defect Claims
September 03, 2015 —
Stephen A. Sunseri – Gatzke Dillon & Balance LLPAugust 26, 2015 - The Fifth Appellate District ruled SB800 (California's "Right to Repair Act" [the "Act"]) provides the sole remedy for homeowners in construction defect actions. The court found "no other cause of action is allowed to recover for repair of the defect itself or for repair of any damage caused by the defect." (McMillin Albany LLC v. Superior Court of California (Aug. 26, 2015, No. F069370) __ Cal.App.4th __ [2015 WL 5029324].) The court issued a blistering criticism of the Fourth Appellate District's prior opinion in Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, which severely limited the reach of the Act to actions not involving property damage and allowing property damage claims to proceed freely under common law without any constraints posed by the Act.
In McMillin, the court reviewed whether a homeowner was required to follow the Act's prelitigation procedures even after dismissing a cause of action arising under the Act. In deciding the issue, the court quoted directly from the first line of the Act (Civ. Code § 896) and found "[i]n any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … , the claimant's claims or causes of action shall be limited to violation of" the standards set out in the Act. The court recognized the statutory exceptions to this rule, such as for claims arising under contract, or any action for fraud, personal injuries, or statutory violations. (Civ. Code., § 943.) However, this result directly conflicts with the Fourth Appellate District's decision in Liberty Mutual, which found homeowners can circumvent the entire Act by simply alleging property damage claims. McMillin rejects Liberty Mutual's "reasoning and outcome" as being inconsistent with the express language of the Act.
McMillin found that Liberty Mutual failed to fully analyze the statutory language of the Act, which (on its face) limits any action for construction deficiencies to the requirements of the Act. McMillin concludes the Legislature intended that all construction defect actions (for new residences sold on or after January 1, 2003), are subject to the requirements of the Act, including the prelitigation procedures, regardless of whether a complaint expressly alleges a cause of action under the Act or not.
McMillin is a great victory for homebuilders, but battle lines are now clearly drawn between the two appellate districts. McMillin directly conflicts with Liberty Mutual, and because of this conflict, the issue will need to be resolved by the California Supreme Court. Until such review is granted, the conflict will remain and trial courts will likely continue to conflate the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen A. Sunseri, Gatzke Dillon & Balance LLPMr. Sunseri may be contacted at
ssunseri@gdandb.com
If You Can’t Dazzle Em’ With Brilliance, Baffle Em’ With BS: Apprentices on Public Works Projects
October 24, 2023 —
Garret Murai - California Construction Law BlogThe “Big Four” when it comes to public works contracting on state and local projects in California are:
- Registration with the California Department of Industrial Relations (“DIR”);
- Payment of prevailing of wages and maintenance and submission of certified payroll;
- Compliance with the “skilled and trained workforce” requirements on certain projects; and
- Hiring apprentices on state and local public works projects with a value of $30,000 or more.
The next case,
GRFCO, Inc. v. Superior Court, 89 Cal.App.5th 1295 (2023), discusses the last of these requirements. The case also reminded me of W.C. Field’s old saying – “If you can’t dazzle em’ with brilliance, baffle em’ with bullshit” – and which ended with expected results.
Read the court decisionRead the full story...Reprinted courtesy of