Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
August 06, 2019 —
William L. Porter - Porter Law GroupThe “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Non-Responsibility will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Construction Defects in Roof May Close School
October 21, 2013 —
CDJ STAFFA school in Wales may have to close due to roof leaks. The school was opened six years ago, but since then the leaks at Ysgol Ffynnonbedr are “leading to the deterioration of the structure and fabric of the school.” The Lampeter city council have budgeted £35,000 (about $56,000) for repairs to the roof.
The leaks have already rendered some of the electrical systems and teaching areas unusable. The city council had been in discussion with the builders, Cowlin Construction, when that firm was bought by Balfour Beatty. Balfour Beatty did not comment to the Cambrian Times about resolving the construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Ten Years After Colorado’s Adverse Possession Amendment: a brief look backwards and forwards
September 25, 2018 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogIn response to national outrage over an infamous adverse possession case in Boulder, Colorado, in which a lawyer and a judge intentionally took their neighbors’ undeveloped land through adverse possession, the Colorado legislature amended the state’s adverse possession statute (C.R.S. § 38-41-101) to make the claim significantly harder to prove. It did this because it believed “there were insufficient ‘obstacles’ to establishing a claim for adverse possession under the existing law.”[1] Effective July 1, 2008, the amendment created a heightened burden of proof, additional element requirements, and the possibility of a losing defendant recovering money from successful plaintiffs for the value of the land they took and the taxes the defendant had paid on that land.
The Boulder case eventually settled, but the resulting statutory amendments have drastically changed the landscape of Colorado’s adverse possession law. Ten years later, this blog post takes a brief look at the amended statute, the impact it has had, and questions that have yet to be resolved.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Sochi Construction Unlikely to be Completed by End of Olympic Games
February 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAs journalists and visitors descended upon Sochi, Russia for this winter’s Olympic Games, they reported “used linen, improper toilets, poor wiring, unclean water and loose fixtures” using the Twitter hash tag @SochiProblems, according to The International Business Times. Furthermore, it is doubtful that the construction work “in and around Sochi” will be completed by February 23rd—the official end of the games.
The International Business Times article features photographs of various unfinished construction sites including an apartment building, hotels, a sports store, and other buildings. The Olympic opening ceremony took place on February 7th.
Read the court decisionRead the full story...Reprinted courtesy of
Understand and Define Key Substantive Contract Provisions
March 23, 2020 —
Phillip L. Sampson Jr. & Richard F. Whiteley, Construction ExecutiveThe following contract provisions should be clearly understood before undertaking any construction project commences.
Force Majeure
Often referred to as an “Act of God,” a force majeure is an event, typically beyond the parties’ control, that prevents performance under a contract. To determine if a contractor need a force majeure clause in its contract, it should ask whether there may be instances where events beyond the contractor’s control could impact its contractual performance? If so, it will want this clause.
Courts currently treat force majeure as an issue of contractual interpretation, focusing on the express language in the contract. Consequently, the scope and applicability of a force majeure clause depends on the contract’s terms. Using broad language in a force majeure clause may help protect against unforeseen events. But to the extent possible, parties should describe with particularity the circumstances intended to constitute a force majeure.
The law relating to force majeure also fairly consistently provides that parties cannot avoid contractual obligations because performance has become economically burdensome. Courts have refused to apply force majeure clauses where an event only affects profitability. Recent attempts to categorize tariffs on construction materials as a force majeure have failed. Unless a tariff or tax is specifically listed as a force majeure event, it is unlikely to constitute a force majeure because it only affects profitability.
Reprinted courtesy of
Phillip L. Sampson Jr. & Richard F. Whiteley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
It’s Getting Harder and Harder to be a Concrete Supplier in California
December 04, 2018 —
Garret Murai - California Construction Law BlogIn 2015, the California state legislature passed AB 219, which amended the state’s prevailing wage law to add Labor Code section 1720.9, which requires the payment of prevailing wages to “ready-mixed concrete” drivers on state and local public works projects.
Ready-mixed concrete suppliers filed suit in Allied Concrete and Supply Co. v. Baker (September 20, 2018) U.S. Court of Appeals for the Ninth Circuit, challenging the law on the ground that, because AB 219 singled out ready-mixed concrete drivers but not other drivers of materials on state and local public works projects, the law violated the Equal Protection Clause of the U.S. Constitution.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Conflicts of Laws, Deficiency Actions, and Statutes of Limitations – Oh My!
May 10, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogWhat law governs a deficiency action if the choice-of-law provisions in the note and deed of trust conflict? The Arizona Court of Appeals answered that very question in ZB, N.A. v. Hoeller, No. 1 CA-CV 16-0071 (Ct. App. April 15, 2017). It turns out, the note controls.
The Facts
In ZB, ZB, N.A. (ZB), a Utah bank, lent money to the Hoellers to purchase a commercial property in Missouri. The note included a choice-of-law provision stating that Utah law governed the debt. The deed of trust securing the commercial property, however, provided that Missouri law controlled “procedural matters related to the perfection and enforcement of [ZB’s] rights and remedies against the [p]roperty.” In 2012, the Hoellers defaulted, and the bank recovered the property through a trustee’s sale.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Congratulations Bryan Stofferahn, August Hotchkin, and Eileen Gaisford on Their Promotion to Partner!
April 19, 2021 —
Bremer Whyte Brown & O’MearaBryan Stofferahn has been with BWB&O’s Oakland office since 2016 and has been practicing law since 2002. Mr. Stofferahn focuses his practice on insurance defense matters and was lead counsel on the Millennium Tower construction defect case in San Francisco, which was the largest construction defect action in the country.
Outside of work, Bryan is passionate about traveling the world with his wife Claire and has finished in last place in two separate chili cook-offs (pre-COVID, of course).
August Hotchkin has been with BWB&O since 2013 and helped open the Reno office located in Northern Nevada in 2016. He is duly licensed in both Nevada and California, handling various legal matters, especially complex litigation, throughout Northern Nevada and Northern California.
Mr. Hotchkin has taken several cases to trial, including a successful defense verdict on a wrongful death matter. He has also argued countless dispositive motions as well as having cases heard at the Appellate level.
During his free time, Mr. Hotchkin enjoys golfing, snowboarding, and spending time with his family and friends, especially up at Lake Tahoe.
Eileen Gaisford has been with BWB&O’s Woodland Hill’s office for almost a decade and is licensed to practice law in California.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP