Fourth Circuit Clarifies What Qualifies As “Labor” Under The Miller Act
May 08, 2023 —
Jeffrey Hummel - The Construction SeytUnder the Miller Act, 40 U.S.C. §§ 3131 et seq., contractors hired to work on federal construction projects are required to furnish payment bonds in order to ensure payment to certain persons that provide labor for the project. The United States Court of Appeals for the Fourth Circuit recently issued a published decision clarifying the type of work that qualifies as “labor” under the Miller Act. Elliot Dickson v. Fidelity and Deposit Company (issued April 26, 2023).
In that case, the U.S. Department of Defense hired Forney Enterprises (Forney) as the prime contractor on a renovation project at the Pentagon. Forney retained Fidelity and Deposit Company of Maryland (Fidelity) to provide the required Miller Act payment bond. Forney then entered into a subcontract with Elliott Dickson (Dickson), a professional engineer, to work as a project manager on the contract. Dickson primarily supervised labor on the site, but also performed other tasks, including logistical and clerical duties, taking various field measurements, cleaning the worksite, moving tools and materials, and sometimes even watering the concrete himself. Dickson’s work required him to be onsite on a daily basis.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey Hummel, SeyfarthMr. Hummel may be contacted at
jhummel@seyfarth.com
Formal Opinion No. 2020-203: How A Lawyer Is to Handle Access to Client Confidential Information and Anticipation of Potential Security Issues
December 07, 2020 —
Bremer Whyte Brown & O'Meara LLPRecently, the California Bar Association (“CBA”) published Formal Opinion No. 2020-203[1] concerning a lawyer’s ethical obligations with respect to unauthorized access to electronically stored client information. The onset of the COVID-19 pandemic greatly accelerated the growing trend of storing and maintaining data and information online so that employees and clients can access the data from anywhere in the world at any time. Now, in today’s working world, the reality is nearly all information and data is stored and shared digitally online for ease of access, use, and dissemination.
Unfortunately, a major draw-back of this switch to a cyber paradigm is serious exposure to data breaches as a result of hacking, inadvertence, or theft. Formal Opinion No. 2020-203 outlines how a lawyer is to handle access to client confidential information and anticipation of potential security issues. This article will briefly cover the key aspects addressed in Formal Opinion No. 2020-203.
What is the duty owed by a lawyer to his or her client regarding the use of technology?
At the outset, the CBA reminds lawyers of the ongoing duty of competence (Rule 1.1) and the duty to safeguard clients’ confidences and secrets (Rule 1.6; Cal. Bus. & Prof. Code, § 6068(e)) which impose the requirement that a lawyer must have a basic understanding of the risks posed when using a given technology and (if necessary) obtain help from appropriate experts to assess those risks and take reasonable steps to prevent data breaches.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
4 Breakthrough Panama Canal Engineering Innovations
October 11, 2017 —
Hobbes S. Sujith - Construction InformerThrough the rainforest of Central America stretches one of the seven wonders of the modern world. It’s the mother of all shortcuts – the Panama Canal. Over 300 million tons of cargo pass through its gates every year. Stretching through the heart of the Americans, this canal has changed the face of global trade. Ships traveling between the Atlantic and Pacific used to sail thousands of kilometers around Cape Horn. So in 1879 engineers planned to cut a channel through the Isthmus of Panama. And that, was going to become the history of Panama Canal engineering.
To understand how the Panama Canal can carry such a huge amount of cargo, we need to travel back in time to 17th century France. There, engineers building the Briare Canal (Canal de Briare) faced an big problem. How to make water flow up a hill?
Read the court decisionRead the full story...Reprinted courtesy of
Hobbes S. Sujith, Construction Informer
How You Plead Allegations to Trigger Liability Insurer’s Duties Is Critical
November 01, 2021 —
David Adelstein - Florida Construction Legal UpdatesHow you plead allegations in your lawsuit to trigger duties of a liability insurance carrier is a critical consideration. If the complaint is not pled appropriately, it can result in the carrier NOT owing a duty to defend its insured, which is the party(ies) you are suing. If there is no duty to defend, there will be no duty to indemnify the insured to cover your damages. For this reason, in a number of circumstances, this is NOT what you want because you want to trigger insurance coverage and potential proceeds to be paid by a carrier to cover your damages. There are times when you are confronted with a case that just is not a good insurance coverage case. This may result in you coming up with creative arguments to maximize insurance coverage. Even in these times, you want to plead the complaint to best maximize coverage under the creative arguments you have developed.
An example of not pleading allegations in a complaint to trigger an insurer’s duties can be found in the Eleventh Circuit Court of Appeal’s decision in Tricon Development of Brevard, Inc. v. Nautilus Insurance Co., 2021 WL 4129373 (11th Cir. 2021). This case involved a general contractor constructing condominiums. The general contractor hired a subcontractor to fabricate and install metal railings. The subcontractor had a commercial general liability (CGL) policy that named the general contractor as an additional insured with respect to liability for property damage “caused in whole or in part” by the subcontractor’s direct or vicarious acts or omissions. (This is a good additional insured endorsement.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Certifying Claim Under Contract Disputes Act
June 08, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the Contract Disputes Act (41 USC 7101 en seq.), when a contractor submits a claim to the government in excess of $100,000, the claim MUST contain a certification of good faith, as follows:
For claims of more than $100,000 made by a contractor, the contractor shall certify that–
(A) the claim is made in good faith;
(B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;
(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and
(D) the certifier is authorized to certify the claim on behalf of the contractor.
41 U.S.C. 7103(b)(1). See also 48 C.F.R. s. 33.207(c) as to the wording of the certification.
The contracting officer is not required to render a final decision on the claim within 60 days if, during this time period, he/she notifies the contractor of the reasons why the certification is defective. 41 U.S.C. 7103(b)(3). Importantly, the contracting officer’s failure to render a decision within 60 days is deemed an appealable denial.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Repeated Use of Defective Fireplace Triggers Duty to Defend Even if Active Fire Does Not Break Out Until After End of Policy Period
November 30, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Tidwell Enterprises v. Financial Pacific Ins. Co. (No. C078665, filed 11/29/16), a California appeals court held that that even though a house fire occurred after the policy period, there was nonetheless a possibility of coverage because the fire might have been the result of ongoing damage to the wood in the chimney chase during the policy period, due to the exposure of that wood to excessive heat from the chimney every time a fire was burned in the fireplace.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Two-Part Series on Condominium Construction Defect Issues
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFGregory L. Shelton, construction law attorney at Horack, Talley, Pharr & Lowndes, P.A., wrote a two-part series in the Charlotte Observer about condominium construction defect issues. The first part described “common defects and their consequences,” while the second part explained “how legal time limits can prevent the association or its owners from suing the parties responsible for defective construction.”
If interested in purchasing a condo unit, Shelton recommended hiring a building inspector, though he cautioned that “the inspector should be truly independent. His client should be you and not ‘the sale.’” In the second part, Shelton discussed the complexities of statutes of limitations and statutes of repose.
Read the full story, Part 1...
Read the full story, Part 2... Read the court decisionRead the full story...Reprinted courtesy of
Judge Rejects Extrapolation, Harmon Tower to Remain Standing
November 07, 2012 —
CDJ STAFFCityCenter has filed an emergency motion asking the Nevada Supreme Court to intervene in Judge Elizabeth Gonzalez’ order that the building’s defects cannot be extrapolated from those tested. CityCenter’s structural engineering expert “evaluated 397 of the Harmon’s critical structural elements and found all but one defective,” according to the article on Vegas.Inc. Judge Gonzalez would not permit this to be extrapolated to the untested 1,072, as the locations tested were not random.
Judge Gonzalez also ruled that if CityCenter does additional testing, they may not appeal her order that ruled the extrapolation inadmissible. CityCenter argued to the Nevada Supreme Court that “the notion that CityCenter should be forced to incur additional millions of dollars in testing costs and sanctions – on the condition that it waive its right to appeal this ruling – just to be permitted to present its own damages evidence, shocks the conscience.”
Gonzalez gave the okay to CityCenter to demolish the building, but its demolition would make any further testing impossible. Under Gonzalez’ ruling, the untested structural elements cannot b assumed to be defective.