Agree First or it May Cost You Later
May 08, 2023 —
Bill Wilson - Construction Law ZoneBusiness relationships often begin before parties execute a written agreement containing the terms and conditions by which the relationship will be governed. With little more than a Letter of Intent (“LOI”) or Letter of Award (“LOA”) one party is typically pressured to begin investing time and money to start preliminary work on a project. If such LOI or LOA contains nothing more than an agreement to agree later, the performing party should minimize its investment until the later agreement is executed. A recent court decision in New York confirmed the danger to the performing party under “agreement to agree” provisions.
In Permasteelia North America Corp. v. JDS Const. Group, LLC, 2022 WL 2954131 (N.Y. Sup. CT. 7/22/22), the plaintiff subcontractor allegedly performed $1.9 million worth of preliminary work under nothing more than a LOA with an agreement to agree provision. Issues arose, and the parties never entered any later written agreement. The general contractor refused to pay the plaintiff anything for its preliminary work. In response, the plaintiff filed suit against the general contractor asserting four counts: foreclosure of its lien, breach of contract, unjust enrichment, and account stated. All four counts were based on an alleged oral “handshake deal” for subcontract work for the project. The general contractor’s LOA stated that neither party would be bound “unless and until the parties actually execute a subcontract.” During discovery, the plaintiff admitted that neither party intended to enter into any contract until its potential terms were negotiated, reduced to writing, and signed. Moreover, the plaintiff only offered one set of meeting minutes and a few project agendas to support its alleged “handshake deal.” Once these necessary undisputed facts were confirmed, the defendant moved for summary judgment on all four counts.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Court Finds Duty To Defend Environmental Claim, But Defense Limited to $100,000
August 14, 2023 —
Tred R. Eyerly - Insurance Law HawaiiWhile agreeing with the insured there was a duty to defend, the court determined the defense of an environmental claims was limited to $100,000. Casa Nido Partnership v. JAE Kwon, 2023 U.S. Dist. LEXIS 97701 (N.D. Calif. June 5, 2023).
In 1976, Casa Nido purchased the property and remains the current owner to this day. Catherine O'Hanks owned and operated a dry-cleaning facility at the property from 1960 to 1992.
In August 2016, Casa Nido learned of Tetrachloroethylene (PCE) subsurface contamination. Casa Nido stipulated that it did not know, nor had any reason to know, before 2016, of the existence of the subsurface contamination. Casa Nido alleged that due to equipment malfunction or improper usage, there were sudden and accidental spills and equipment overflows of PCE during the 32-year period that defendant O'Hanks operated the dry-cleaning business on the property. Casa Nido spent hundreds of thousands of dollars remediating the environmental damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Presidential Executive Order 14008: The Climate Crisis Order
August 16, 2021 —
Anthony B. Cavender - Gravel2GavelPresidential Executive Order 14008, “Tackling the Climate Crisis,” a long and unusually detailed Executive Order published in the Federal Register on February 1, 2021 (see 86 FR 7619), has generated considerable discussion and commentary. Below, I briefly outline its provisions.
This EO describes the “climate crisis” in existential terms:
“There is little time left to avoid setting the world on a dangerous, potentially catastrophic climate trajectory.” Confronting and combating climate change will be an important component of American foreign policy and national security, and domestically, the federal government’s resources will be mobilized to deploy a “govern-wide approach to the climate crisis.”
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Louisiana District Court Declines to Apply Total Pollution Exclusion
December 15, 2016 —
William S. Bennett – Saxe Doernberger & Vita, P.C.The United States District Court for the Eastern District of Louisiana recently decided that a broad total pollution exclusion in a marine general liability policy did not bar coverage.
The insurer could not unambiguously establish, based on the facts of the underlying case, that waste from a shipyard’s sandblasting activities met the requirements of the exclusion.
The court found that the insurer could not meet Louisiana’s three-part test to determine whether the policy’s total pollution exclusion applied. The Doerr test requires an insurer to refer to the allegations in the underlying complaint to prove 1) the insured is a “polluter”, 2) the injury-causing substance is a “pollutant,” and 3) there was a “discharge, dispersal, seepage, migration, release or escape” of the pollutant.
Total pollution exclusions are extremely prohibitive for policyholders because they eliminate coverage for virtually all pollution incidents, but this decision reinforces that policyholders may still have a path to coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Contractor Disputes Report Amid Amazon Warehouse Collapse Lawsuit
May 02, 2022 —
James Leggate - Engineering News-RecordA contractor facing a lawsuit related to the December partial collapse of an Amazon.com Inc. warehouse that was hit by a tornado is pushing back on claims in a fire marshal’s report that highlighted possible “significant structural issues” with the building.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Meet the Forum's ADR Neutrals: LESLIE KING O'NEAL
January 29, 2024 —
Marissa L. Downs - The Dispute ResolverCompany: JAMS
Office Location: Orlando, FL
Email: lkoneal1117@gmail.com
Website: https://www.jamsadr.com/oneal/
Law School: University of Florida, J.D. (1977)
Types of ADR services offered: Mediation, arbitration, neutral evaluation
Geographic area served: Nationwide
Q: Describe the path you took to becoming an ADR neutral.
A: Florida was one of the first states to allow judges to send civil cases to mediation. When I was an advocate, nearly all my cases went to mediation at least once—sometimes more than once! I became a firm believer in the value of mediation and other ADR methods. I became a Florida certified circuit court mediator in 2021 and I joined JAMS in 2022, after retiring as in-house counsel with Brasfield & Gorrie, a large commercial general contractor. I am also an adjunct professor at Pepperdine Law School, teaching arbitration theory and practice in its master of dispute resolution and master of laws programs.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Forum Selection Provisions Are Not to Be Overlooked…Even On Federal Projects
September 16, 2024 —
David Adelstein - Florida Construction Legal UpdatesForum selection provisions are NOT to be overlooked. Ever. Treat them seriously. Even on federal projects where there is a Miller Act payment bond. Consider forum selection provisions on the front end when negotiating your contract.
In a recent opinion, U.S. f/u/b/o Timberline Construction Group, LLC vs. Aptim Federal Services, LLC, 2024 WL 3597164 (M.D.Fla. 2024), a joint venture prime contractor was hired by the federal government to build a temporary housing site. The joint venture prime contractor obtained a Miller Act payment bond. The joint venture then entered into a subcontract with one of its joint venture members and the member-subcontractor then engaged a sub-subcontractor. The sub-subcontractor claimed it was owed $3.5 Million and sued the member-subcontractor, as well as the prime contractor’s Miller Act payment bond, in the Middle District of Florida. The member-subcontractor and the Miller Act payment bond sureties moved to transfer venue to the Middle District of Louisiana pursuant to a forum selection clause in the contract between the sub-subcontractor and the member-subcontractor. The contract provided that the exclusive venue would be a United States District Court located in Louisiana.
Forum selection provisions are analyzed in federal court under 28 U.S.C. 1404(a): “For the convenience of parties and witnesses, in the interest of justice, a district court may transfer any civil action to any other district or division where it might have been brought or to any district or division to which all parties have consented.” U.S. f/u/b/o Timberline, supra at *2. A forum selection provision is presumptively valid and given controlling weight. Id. (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Alaska Supreme Court Dismisses Claims of Uncooperative Pro Se Litigant in Defect Case
August 11, 2011 —
CDJ STAFFThe Alaska Supreme Court found that in the case of Khalsa v. Chose, Ms. Khalsa? failure to cooperate with the courts has obligated them to dismiss her claims against Mr. Chose. Ms. Khalsa bought a home kit from Mandala Custom Homes of Nelson, British Columbia, Canada. Mr. Chose, one of the owners of Mandala was paid by Ms. Khalsa to supervise assembly in Fairbanks. After construction, the roof developed leaks. Ms. Khalsa stated that when climbing a ladder to inspect a skylight leak, she fell and injured herself.
During the subsequent suit, Khalsa proved uncooperative. She skipped a pretrial conference. She attended a hearing that set discovery deadlines but then did not comply with discovery, including her failure to provide medical records documenting her injuries. She eventually said that she would only be able to travel from Arizona to Alaska if the defendants paid for her and her caretaker?s expenses.
When finally deposed, Khalsa terminated the deposition after five minutes, alleging the deposition was “intentionally designed to cause [her] to endure further emotional distress, due to the psychological trauma . . . that was caused or contributed to by the defendants.”
Eventually, the lower court sanctioned her twice. In July, 2008, the court concluded that her failure to provide medical records required dismissal of her injury lawsuit. In October of that year, the court dismissed all remaining claims due to her “pattern of excuses and long delays in providing information for discovery culminating in her refusal to participate in her deposition by the defendants.” Further, Khalsa has argued that the trial court displayed “prejudice and bias toward the pro se plaintiff.”
The Alaska Supreme Court rejected all of Ms. Khalsa?s claims, dismissing her case. They did, however, note that she has thirty days to file an appeal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of