Microsoft Urges the Construction Industry to Deliver Lifecycle Value
June 25, 2019 —
Aarni Heiskanen - AEC BusinessDigitalization is changing the way that we operate and use buildings. Salla Palos is directing Microsoft towards a future that inspires innovative changes in both the mindset and the business models of AECO industry stakeholders.
Salla Palos moved from Finland to the United States in July 2015 and settled down in Seattle, one of the fastest growing areas in the USA. She was versed in digitalization of construction industry in Finland as well as Europe and sought the opportunity to bring that knowledge into the US market.
As the Director of Emerging Technology and Innovation for Sellen Construction, one of the largest general contractor companies in the Pacific Northwest United States, Salla started developing digital building lifecycle as a strategy to solve number of industry problems.
“I zeroed in on developing digital construction strategy, re-engineering processes, and innovating how emerging technology supports digital construction. My approach was open innovation, pulling the industry along with our own digital transformation. I set up collaboration with both local and international partners to be successful in driving change and transforming AEC,” Salla recalls.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Sureties and Bond Producers May Be Liable For a Contractor’s False Claims Action Violation
October 26, 2017 —
Michael C. Zisa & Susan Elliot – Peckar & Abramson, P.C.Two recent decisions from the United States District Court for the District of Columbia and the United States Court of Federal Claims highlight that sureties and bond producers are not immune to the potentially severe consequences of the False Claims Act (“FCA”) and related federal fraud statutes. In each case, the Court determined that sureties and bond producers can face potential liability under these fraud statutes for direct and indirect submission of false claims to the federal government
Reprinted courtesy of
Michael C. Zisa, Peckar & Abramson, P.C. and
Susan Elliott, Peckar & Abramson, P.C.
Mr. Zisa may be contacted at mzisa@pecklaw.com
Ms. Elliott may be contacted at selliott@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Veterans Day – Thank You for Your Service
December 05, 2022 —
Travis Colburn - Ahlers Cressman & SleightHappy Veterans Day
[1] to our country’s servicemembers past and present! ACS would like to express its deepest gratitude and respect in saying thank you to those that have served, or are serving, in our armed forces. It undoubtedly takes incredible bravery, fortitude, integrity, respect, and a commitment to our country’s evolving ideals. Some of those same attributes that are necessary for service are also well-geared toward a post-military career in construction. As some already know, Veterans have unique construction contracting opportunities at both the state and federal level. The following is a high-level overview of the process and opportunities for veterans who are not aware or who are considering a career in construction.
There are federal and state level opportunities for Veteran-owned businesses. The initial step in accessing federal and state level contracting opportunities is different for each but begins with certification/verification.
At the federal level, effective January 1, 2023, all responsibilities for the verification of Veteran-owned small businesses (“ VSOB”) will transfer from the Department of Veterans Affairs to the Small Business Administration.
[2] Verification is the process that establishes eligibility for access to Veteran-specific benefits, including certain government contracts and the purchase of surplus government property, by confirming that VSOBs and service-disabled Veteran-owned small businesses (“SDVOSB”) are operated by Veterans.
[3] Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Texas Legislature Puts a Spear in Doctrine Making Contractor Warrantor of Owner Furnished Plans and Specifications
May 31, 2021 —
Paulo Flores, Timothy D. Matheny & Jackson Mabry - Peckar & Abramson, P.C.The Texas Legislature has just sent Senate Bill 219 (“S.B. 219”) to the Governor for signature; if this legislation is signed by the Governor, it will further erode the Texas legal doctrine that makes the contractor the warrantor of owner-furnished plans and specifications unless the prime contract specifically places this burden on the owner.
Background
49 states follow what is known as the Spearin doctrine (named after the U.S. Supreme Court case of United States v. Spearin) in which owners warrant the accuracy and sufficiency of owner-furnished plans and specifications. Texas, on the other hand, follows the Texas Supreme Court created Lonergan doctrine, which has been an unfortunate presence in Texas construction law since 1907. In its “purest form,” as stated by the Texas Supreme Court, the Lonergan doctrine prevents a contractor from successfully asserting a claim for “breach of contract based on defective plans and specifications” unless the contract contains language that “shows an intent to shift the burden of risk to the owner.” Essentially, this then translates into the contractor warranting the sufficiency and accuracy of owner-furnished plans and specifications, unless the contract between them expressly places this burden on the owner. Over the years some Texas courts of appeal had ameliorated this harsh doctrine, but in 2012, the Texas Supreme Court indicated Lonergan was still the law in Texas, in the case of El Paso v. Mastec. In 2019, the Texas Legislature took the first step toward hopefully abrogating the Lonergan doctrine by implementing a new Chapter 473 to the Texas Transportation Code with respect to certain projects undertaken by the Texas Department of Transportation, and Texas political subdivisions acting under the authority of Chapters 284, 366, 370 or 431 of the Transportation Code, adopting, as it were, the Spearin Doctrine in these limited, transportation projects. Now, the legislature has further chipped away at the Lonergan doctrine with the passage of S.B. 219.
Reprinted courtesy of
Paulo Flores, Peckar & Abramson, P.C.,
Timothy D. Matheny, Peckar & Abramson, P.C. and
Jackson Mabry, Peckar & Abramson, P.C.
Mr. Flores may be contacted at PFlores@Pecklaw.com
Mr. Matheny may be contacted at tmatheny@pecklaw.com
Mr. Mabry may be contacted at jmabry@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The Need for Situational Awareness in Construction
January 27, 2020 —
Aarni Heiskanen - AEC BusinessRecent research backs up what we already know from practice: construction work is suboptimal. What happens on a construction site has not kept up with the demands of an increasingly complex work environment. Situational awareness could give on-site employees the necessary means to finally reap the productivity benefits of digitalization.
Under the guidance of Professor Olli Seppänen, research teams at the Finnish Aalto University have delved into everyday conditions at a construction site. With the workers’ permission, they used video cameras, sensors, and surveys to locate the bottlenecks in productivity. The researchers also monitored the movement of products and materials on a construction site. The results are eye-opening.
According to Aalto’s data, digitalization has not improved the productivity of construction foremen and workers. A typical worker still spends up to 70% of their time on activities that add no value: searching for information, unnecessary movement, and waiting. Construction materials are moved from place to place six times on the site before being consumed. In addition, especially on large construction sites, machinery often goes missing or is displaced.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Revised Cause Identified for London's Wobbling Millennium Bridge After Two Decades
December 20, 2021 —
Peter Reina - Engineering News-RecordU.S. and British researchers claim to have found a better explanation for the wobble of London's River Thames Millennium pedestrian suspension bridge than the one prevailing for over 20 years. Alarming swaying of the bridge was caused not by synchronization of walkers' footsteps, as previously believed, but the negative damping effect of their efforts not to fall over.
Reprinted courtesy of
Peter Reina, Engineering News-Record
Mr. Reina may be contacted at reina@btinternet.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Last, but NOT Least: Why You Should Take a Closer Look at Your Next Indemnification Clause
March 09, 2020 —
Aimee Cook Oleson - Construction & Infrastructure Law BlogIndemnification clauses appear in nearly every agreement, but they are often overlooked as mere boilerplate provisions after the parties have painstakingly negotiated all of the other terms. It is not uncommon for parties to simply re-use the indemnity language from a prior agreement without considering whether it is a good fit for their current project. This can be a big mistake that may lead to ambiguities and uncertainties if a dispute arises down the road. A standard or canned indemnification clause might work to undo all of the effort that has gone into properly allocating risk. These clauses often contain language such as “notwithstanding anything to the contrary herein,” or the like, which can alter and override other provisions in the agreement.
Indemnification clauses are arguably the most important part of an agreement when an accident or dispute arises on a project. Therefore, they deserve an extra look before finalizing an agreement. Here are a few issues to keep in mind when reviewing your next indemnification clause:
- Have you included all necessary parties?
- Any party who could face potential liability should be included as an indemnified party. This often includes entities and persons related to the contracting parties, not just the parties themselves.
- A well drafted indemnity clause will ensure that all parties are liable for the result of their own work and negligence and that of any party that they have hired to work on a project. This includes employees, agents, subcontractors, or any other similar party.
Read the court decisionRead the full story...Reprinted courtesy of
Aimee Cook Oleson, Sheppard MullinMs. Oleson may be contacted at
AOleson@sheppardmullin.com