Delays in Filing Lead to Dismissal in Moisture Intrusion Lawsuit
September 09, 2011 —
CDJ STAFFThe Alabama Court of Civil Appeals has upheld a summary judgment in the case of Franklin v. Mitchell. Walter Mitchell, doing business as Southern Classic Construction built a new home for the Franklins. The Franklins moved into the home in October 2001. In April 2006 they discovered sagging floors in both the bathroom and kitchen. They contacted Mitchell who suggested the flooring might be defective. The Franklins spent eight months attempting to contact the flooring manufacturer.
In March 2007, the Franklins had the home inspected. The sagging was determined to be due to a loss of strength in the decking because of condensation from the air conditioning system. Air returns were not properly sealed and drawing moisture into the structure. There was mold on the decking and floor joints.
When Mitchell was contacted by the Franklins, he told them his one-year warranty had expired but had the HVAC subcontractor, Southern Mechanical Heating & Air (owned by Mitchell’s father, Jim Mitchell), look at the situation. SMHA replaced and braced subfloors. Later, they entered the crawl space to tape ducts, seal the air return, and insulate the air vent housing. The Franklins were not satisfied with the repairs, as not all the ducts were taped, nor were the air vent housings insulated.
Franklin complained to Walter Mitchell who again cited his one-year warranty. Jim Mitchell said he would not report complaints to his insurer, stating that the repairs were unnecessary, that the work had been done correctly in the first place, and it was only done at the request of Walter Mitchell.
In February 2009, the Franklins sued Walker Mitchell. Mitchell denied the claims, citing in part the statute of limitations. Mitchell also filed complaints against three subcontractors, including his father’s firm. Mitchell received a summary judgment as the case started after Alabama’s six-year statute of limitations.
The appeals court rejected the Franklin’s argument that the claim of damage did not start until they were aware it was due to a construction defect. The court noted that as Walter Mitchell was licensed as a “residential home builder, the statute the Franklins cite did not apply, as it concerns architects, engineers, and licensed general contactors.”
Nor did they feel that Mitchells’ claim that his warranty had expired were sufficient to override the statute of limitations, quoting an earlier case, “Vague assurances do not amount to an affirmative inducement to delay filing suit.” Their claim of subsequent negligent repairs was rejected because Mitchell did not direct the specific actions taken by his father’s firm.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Five Facts About Housing That Will Make People In New York City and San Francisco Depressed
February 26, 2015 —
Flavia Krause-Jackson and Alexandre Tanzi – BloombergIf you live in New York or San Francisco, you should spend some time mining the latest crop of home price data -- starting with the Standard & Poor’s Case-Shiller indices. Then, pull out your last rent check. It might be enough to make you move.
Here are a few things to get you thinking:
1. What you pay for parking in New York can buy a cheap home in Chicago
The cheapest tier of homes in the Windy City were valued at less than $170,368 in November, the Case-Shiller tiered-price indices show (there are three tiers: low, middle and high). That compares to the $136,052 average price tag for parking space in New York last year, according to Jonathan J. Miller, the president of the appraisal firm Miller Samuel and a Bloomberg View contributor.
Reprinted courtesy of
Flavia Krause-Jackson, Bloomberg and
Alexandre Tanzi, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Engineering Report Finds More Investigation Needed of Balconies at New Jersey Condo
March 20, 2023 —
Engineering News-RecordPress of Atlantic City
SEA ISLE CITY - An engineering report on the Spinnaker Condominiums' South Tower found that balconies directly beneath the one that collapsed last month, killing a worker, need further investigation before they are deemed safe for use.
Reprinted courtesy of
Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Material Prices Climb…And Climb…Are You Considering A Material Escalation Provision?
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you may know, material prices have been climbing. And they continue to climb based on the volatility of the material market. On top of that, there are lead times in getting material due to supply chain and other related concerns. The question is, how are you addressing these risks? These are risks that need to be addressed in your contract.
As it relates to climbing material prices, one consideration is a material escalation provision. The objective of this provision is to address the volatility of the material market in economic climates, such as today’s climate, where the price of material continues to climb. Locking down a material price today will be different than locking down the same price months from today. This volatility and risk impacts pricing and budgets. Naturally, an owner and contractor would like to be in a position to lock down supplier prices as soon as possible—both to secure pricing and to account for items with long lead times or that recent data forecasts a long lead time due to supply chain concerns. However, this is not always possible or practical and can depend on numerous issues such as when the owner contracts with the contractor, when the owner issues the notice to proceed (and permits are issued), final construction documents and revisions to the construction documents, the type of material, whether there is staging or storage available for the materials, and the current status including climitazation of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Late Filing Contractor Barred from Involving Subcontractors in Construction Defect Claim
March 01, 2012 —
CDJ STAFFThe Colorado Court of Appeals looked at that state’s Construction Defect Action Reform Act in determining if a general contractor could add subcontractors as third-party defendants to a construction defect lawsuit. Shaw Construction, LLC was the general contraction of the Roslyn Court condominium complex, and was sued by the homeowners’ association in a construction defect case. United Builder Services was the drywall subcontractor on the project. MB Roofing had installed roofs, gutters, and downspouts. The certificate of occupancy for the last building was issued on March 10, 2004. The project architect certified completion of all known remaining architectural items in June, 2004.
The HOA filed a claim against the developers of the property on January, 21, 2009. A week later, the HOA amended its complaint to add Shaw, the general contractor. Shaw did not file its answer and third-party complaint until March 29, 2010, sending its notice of claim under the CDARA on March 30.
The subcontractors claimed that the six-year statute of limitations had ended twenty days prior. Shaw claimed that the statute of limitations ran until six years after the architect’s certification, or that the HOA’s suit had tolled all claims.
The trial court granted summary judgment to the subcontractors, determining that “substantial completion occurs ‘when an improvement to real property achieves a degree of completion at which the owner can conveniently utilize the improvement of the purpose it was intended.’”
The appeals court noted that “Shaw correctly points out that the CDARA does not define ‘substantial completion.’” The court argued that Shaw’s interpretation went against the history and intent of the measure. “Historically, a construction professional who received a complaint responded by ‘cross-nam[ing] or add[ing] everybody and anybody who had a part to play in the construction chain.’” The court concluded that the intent of the act was to prevent unnamed subcontractors from being tolled.
The court further rejected Shaw’s reliance on the date of the architect’s certification as the time of “substantial completion,” instead agreeing with the trial court that “the architect’s letter on which Shaw relies certified total completion.”
The appeals court upheld the trial court’s determination that the statute of limitation began to run no later than March 10, 2004 and that Shaw’s complaint of March 29, 2010 was therefore barred. The summary judgment was upheld.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Seattle Condos, Close to Waterfront, Construction Defects Included
February 11, 2013 —
CDJ STAFFThere's a cluster of eight condominium projects in Seattle, some within easy walking distance of each other, that are either in construction defect lawsuits, arbitration, or mediation. Jeff Reynolds, contributing a Seattle PI.com reader blog, notes that as Seattle condo projects have neared the end of the four-year warranty period, condo boards are being targeted by attorneys. Reynolds writes that "once [the attorneys] are hired by the associations, they retain specialists that test for any and all construction defects with the building envelope."
The problem that Reynolds sees is that that "major lending institutions stay away from condos with lawsuits." And so homeowners dealing with construction defects have apartments they can't sell to anyone who might want to use financing. This tightens Seattle's already limited inventory, leading to both frustrated sellers and frustrated buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Reaffirming the Importance of Appeal Deadlines Under the Contract Disputes Act
January 26, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPA recent United States Court of Federal Claims (“COFC”) decision emphasizes the importance of deadlines for appealing a contracting officer’s (“CO”) decision under the Contract Disputes Act (“CDA”). On July 22, 2016, the COFC granted the consolidation of two naval contract dispute appeals totaling nearly $12.4 million in response to Nova Group/Tutor-Saliba’s (“NTS”) motion to resolve two Requests for Equitable Adjustment (“REA”) in the same forum. See Nova Group/Tutor-Saliba v. United States, No. 15-885C, 2016 WL 4009886, at *5 (Fed. Cl. July 22, 2016). NTS’s motion before the COFC sought to transfer an appeal of a REA before the COFC to the Armed Services Board of Contract Appeals (“ASBCA”), where another appeal of a REA arising under the same contract was presently on appeal. The COFC rejected NTS’s appeal to transfer the REA to the ASBCA because NTS did not appeal the REA within the 90-day limit under the CDA. Instead, the COFC allowed NTS to transfer the REA before the ASBCA to the COFC because timeliness was not an issue.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Noteworthy Construction Defect Cases for 1st Qtr 2014
April 30, 2014 —
Beverley BevenFlorez-CDJ STAFFJohn A. Husmann and Jocelyn F. Cornbleet of BatesCareyLLP analyzed several noteworthy construction defect cases that have already occurred in 2014, as published in Law360. The cases involved “the ‘occurrence’ requirement, contractual liability exclusion and ‘other insurance’ clauses.” Husmann and Cornbleet summarized Owners Insurance Co. v Jim Carr Homebuilder LLC (Alabama), Pennsylvania National Mutual Casualty Insurance Co. v. Snider (also Alabama), Woodward LLC v. Acceptance Indemnification Insurance Co. (Mississippi), and others.
Read the court decisionRead the full story...Reprinted courtesy of