Competent, Substantial Evidence Carries Day in Bench Trial
February 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesA number of construction disputes, if tried, are tried through a bench trial meaning the judge is serving in the role of the jury in the construction trial. In a bench trial, two points are important. First, “the factual findings of the judge are entitled to the weight of a jury verdict.” Q.G.S. Development, Inc. v. National Lining Systems, Inc., 2024 WL 357984 (Fla. 3d DCA 2024) (internal quotation and citation omitted). Second, “[t]he appellate court is only authorized to reverse if such findings are not supported by competent, substantial evidence.” Id. These two points need to be appreciated when participating in any construction dispute that will be resolved through a bench trial.
A recent construction dispute highlights these two points. In Q.G.S. Development, a contractor was hired to refurbish a golf course which included constructing a lake. The contractor was going to construct the lake, prepare the subgrade, perform dewatering, and it hired a subcontractor to install a reservoir liner at the bottom of the lake.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
CDJ’s #3 Topic of the Year: Burch v. The Superior Court of Los Angeles County, 223 Cal.App.4th 1411 (2014)
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFIn 2013, the case Liberty Mutual Insurance Company v. Brookfield Crystal Cove, LLC received a great deal of attention for its possible ramifications to how California’s Right to Repair Act (also known as SB 800) could be applied. However, 2014 had its share of SB 800 policy trends, most notably caused by the ruling in Burch.
In their article, “Construction Law Client Alert: California’s Right to Repair Act (SB 800) Takes Another Hit, Then Fights Back,” authors Steven M. Cvitanovic and Whitney L. Stefco, of Haight Brown & Bonesteel, analyzed Burch as well as KB Home Greater Los Angeles v. The Superior Court of Los Angeles County, et al., both cases that had ramifications on how California’s Right to Repair Act is applied.
Read the full story...
Karen L. Moore of Low, Ball & Lynch discussed the Liberty Mutual and Burch cases in her article, “California’s Right to Repair Act is Not a Homeowner’s Exclusive Remedy when Construction Defects cause Actual Property Damage.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
On Rehearing, Fifth Circuit Finds Contractual-Liability Exclusion Does Not Apply
November 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiOn rehearing, the Fifth Circuit determined that the contractual-liability exclusion did not apply to bar coverage for damage caused by the insured contractor to the home it constructed. Crownover v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 20727 (5th Cir. Oct. 29, 2014).The court withdrew its prior opinion, summarized here.
Arrow Development, Inc. contracted with the Crownovers to construct a home. The contract had a warranty-to-repair clause, which, in paragraph 23.1, provided that Arrow would "promptly correct work . . . failing to confirm to the requirements of the Contract Documents." After the Crownovers moved in, cracks began to appear in the walls and foundation of the home. Additional problems with the heating, ventilation, and air conditioning ("HVAC") caused leaking in the exterior lines and air ducts inside the home. To compensate for defects in the HVAC system, the system's mechanical units ran almost continuously in order to heat or cool the home. Because they were overburdened, the mechanical units had to be replaced. The Crownovers paid several hundred thousand dollars to fix the problems with the foundation and HVAC system.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Georgia Court of Appeals Holds That Policyholder Can “Stack” the Limits of Each Primary Policy After Asbestos Claim
December 19, 2018 —
Michael S. Levine & Alexander D. Russo - Hunton Insurance Recovery BlogA Georgia Court of Appeals judge recently ruled that Scapa Dryer Fabrics was entitled to $17.4 million worth of primary coverage from National Union Fire Insurance Company of Pittsburgh, PA for claims of injurious exposure to Scapa’s asbestos-containing dryer felts. Nat’l Union Fire Ins. Co. of Pittsburgh, PA v. Scapa Dryer Fabrics, Inc., No. A18A1173, 2018 WL 5306693, at *1 (Ga. Ct. App. Oct. 26, 2018). Scapa sought coverage under five National Union policies issued from 1983–1987. The 1983, 1984 and 1985 National Union policies had limits of $1 million per occurrence and $1 million in the aggregate. The liability limits for the 1986 and 1987 renewal policies were amended by endorsement to $7.2 million. Scapa sought to recover the full $17.4 million from all five policies. National Union argued that a “Non-Cumulative Limits of Liability Endorsement” in the 1986 and 1987 policies limited Scapa’s recovery to only $7.2 million. Scapa sued National Union and its sister company, New Hampshire Insurance Company (from which Scapa purchased excess liability coverage), in Georgia state court.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Alexander D. Russo, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Russo may be contacted at arusso@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Waive Too Much In Your Mechanic’s Lien Waiver
December 22, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past few years, the Virginia General Assembly has, with certain caveats, precluded pre-furnishing waiver of mechanic’s lien rights. While this essentially outlawed the types of mechanic’s lien waiver clauses that pervaded construction contracts in Virginia, the key to the previous sentence is “pre-furnishing.” What the General Assembly left intact were the usual waivers of mechanic’s lien rights typically required to be provided to Owners and others in the payment chain in exchange for payment.
These lien waivers come in a few “flavors” from conditional to unconditional, partial to full. Their terms usually include an acknowledgement of receipt of payment (we’ll get to this later), and a statement that the one seeking payment knows of no possible claims by lower tier subcontractors and then waives all mechanic’s lien rights against the property for work performed and included in the request for payment. Often over my years as a Virginia construction attorney, I have noticed that these waivers are often signed without comment or review. They are just part of the process and more often than not are not even an issue for most projects. Of course, if they are an issue they can be a big one, and their terms can come back to bite a claimant that has not properly vetted them.
The first potential issue is waiving lien rights while acknowledging receipt prior to actual receipt of the check or wire. Many of the waiver forms that are out there list a payment amount, or possibly simply state that the waiver is in exchange for some small payment, and then state “receipt of which is acknolwedged” or something similar. The issue here is that receipt may not have happened yet because these lien waivers are submitted as part of the payment package in order to get paid in the first place. In short, should you sign the waiver prior to payment, you may have acknowledged a non-event and in the event of non-payment have a written document stating that you waived your claim to a lien for that money. What a court would do with this, I am unsure, but why risk it? My advice, be sure your waiver is contingent on actual clearance of payment as well as receipt.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
From Singapore to Rio Green Buildings Keep Tropical Tenants Cool
June 07, 2021 —
Andrew Janes & Shawna Kwan - BloombergOn a typically hot and humid afternoon in Singapore, a fresh breeze blows beneath the canopy of the South Beach development, keeping temperatures several degrees cooler than on the surrounding streets.
The rippling 280-meter (919 feet) wave of steel-and-aluminum runs the length of the Norman Foster-designed complex, funneling prevailing winds over outdoor patrons of restaurants and bars and saving on air conditioning for the mixed-use complex. The canopy is covered with solar panels and catches rainwater to irrigate the gardens.
Offices and apartment blocks designed to be green are springing up all over the world as architects reverse almost a century of trying to insulate workers from nature and instead try to adapt structures to their natural surroundings. The change is being driven by stricter building codes, a desire to cut energy costs and, in particular, demands from corporations and startups that need to show shareholders and customers they are meeting environmental standards.
Reprinted courtesy of
Andrew Janes, Bloomberg and
Shawna Kwan, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Rooftop Solar Leases Scaring Buyers When Homeowners Sell
June 26, 2014 —
Will Wade – BloombergDorian Bishopp blames the solar panels on his roof for costing him almost 10 percent off the value of the home he sold in March.
That’s because instead of owning them he leased the panels from SunPower Corp. (SPWR), requiring the new owner of the house to assume a contract with almost 19 years remaining. He had to shave the asking price for the house in Maricopa, Arizona, to draw in buyers unfamiliar with the financing arrangement.
Leasing is driving a boom in solar sales because most require no money upfront for systems that cost thousands of dollars. That’s made solar affordable for more people, helping spur a 38 percent jump in U.S. residential installations in the past year. Since the business model only gained currency in the past two years, the details embedded in the fine print of the deals are only starting to emerge.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade, BloombergMr. Wade may be contacted at
wwade4@bloomberg.net
Another Colorado District Court Refuses to Apply HB 10-1394 Retroactively
October 28, 2011 —
In Martinez v. Mike Wells Construction Company, 09CV227, Teller County District Court Judge Edward S. Colt refused to apply C.R.S. § 13-20-808 retroactively to provide coverage for the underlying construction defect allegations. According to the recitation of facts in Judge Colt’s March 2011 order, Martinez contracted with Mike Wells Construction to serve as the general contractor for the construction of a home. At that time, Mike Wells Construction was insured through ProBuilders Specialty Insurance Company, RRG. Disputes arose between Martinez and Mike Wells Construction, resulting in Martinez ordering it off of the project in mid-November 2007 and terminating its right to work there by letter dated November 28, 2007.
Mike Wells, the owner of the corporation, subsequently died. Martinez sued Mike Wells Construction in July 2009 for breach of contract and various claims relating to alleged defecting workmanship. Martinez provided notice of the suit to the special administrator of the probate estate. No answer having been filed, the court entered a default judgment against Mike Wells Construction and Martinez sought to garnish Mike Wells Construction’s ProBuilders insurance policy.
Read the full story...
Reprinted courtesy of Higgins, Hopkins, McLain & Roswell, LLC. Mr. McClain can be contacted at mclain@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of