Three-Year Delay Not “Prompt Notice,” But Insurer Not “Appreciably Prejudiced” Either, New Jersey Court Holds
November 04, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPIn Harleysville Preferred Insurance Company v. East Coast Painting & Maintenance, LLC, 2019 U.S. Dist. LEXIS 135295 (D.N.J. Aug. 12, 2019) (East Coast Painting), the U.S. District Court for the District of New Jersey held that an insurer, which received notice of a bodily injury accident three years after it happened, was not “appreciably prejudiced” by such late notice, even as the court acknowledged notice three years later did not satisfy the policy’s “prompt notice” condition. The court also held that the policy’s “Operational Exclusion,” which excluded coverage for bodily injury arising out of the operation of “cherry pickers and similar devices,” did not apply because the accident arose out of the use of a “scissor lift,” which is not a device similar to a cherry picker.
East Coast Painting arose out of a Queens, New York bridge-painting project, during which an employee of the insured, East Coast Painting and Maintenance LLC was injured while “standing on a scissor lift mounted to the back of a truck,” owned and operated by East Coast. The employee sued various project-related entities which, in turn, joined East Coast as a defendant. East Coast sought coverage under its business auto policy, and the insurer agreed to defend the insured under a reservation of rights. The insurer subsequently sought a declaration that it did not owe coverage based on, among other things, the policy’s “Operational Exclusion,” and the insured’s failure to satisfy the policy’s “prompt notice” condition. The insurer moved for summary judgment on both of those bases, but the court in East Coast Painting denied the motion.
As for the insurer’s “prompt notice” defense, the court in East Coast Painting concluded that, the insured’s notice to the insurer was not prompt because it did not receive notice until three years after the accident. But, the court added, the inquiry does not end there. “[T]his Court must determine whether [the insurer] was appreciably prejudiced by that delay.” Reviewing the facts, the court held that the insurer was not “appreciably prejudiced,” even though during the three-year delay the lift truck was “not properly maintained” or “in the same condition it was at the time of the Accident.” The court observed that the insurer had “ample other evidence with which it can defend itself,” such as experts who inspected the lift truck and opined about the cause of the accident.” [Emphasis added.] Further, “there are multiple contemporaneous accident reports,” “a list of the East Coast employees on site at the time,” “photographs of the lift truck and its location when [the employee] was injured,” and “depositions of [the employee] and others regarding the events at issue.” Thus, the court held, the insurer was not prejudiced and summary judgment was inappropriate.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Timothy A. Carroll, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Rising Construction Disputes Require Improved Legal Finance
November 15, 2022 —
Apoorva Patel - Construction ExecutiveConstruction disputes are famously high stakes, and the industry is currently experiencing an uptick in the value and number of disputes resulting from contractual obligations and third-party or force majeure incidents. While this is not entirely surprising given COVID-19’s disruption of global markets and supply chains, the numbers are noteworthy.
For example, in 2020 alone, the International Chamber of Commerce (ICC)—the leading institution for construction disputes, partly because its clauses feature in many FIDIC standard form contracts—registered 194 construction arbitrations, and construction disputes now comprise over 20% of the ICC caseload.
In addition to the damage to business outcomes that the underlying disputes may present, parties can quickly spend many millions on legal fees and expenses, as well as technical experts and consultants, if and when those disputes progress through the courts or arbitration. According to Norton Rose’s 2020 Global Construction Disputes Report, the average construction dispute value rose sharply from $30.7 million in 2019 to $54.26 million in 2020.
Reprinted courtesy of
Apoorva Patel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Impaired Property Exclusion Bars Coverage When Loose Bolt Interferes with MRI Unit Operation
May 16, 2018 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn All Green Electric v. Security National Ins. Co. (No. B279456, filed 3/19/18, ord. pub. 4/17/18), a California appeals court ruled that the impaired property exclusion barred coverage for a claim based on the insured’s failure to tighten a loose bolt that resulted in stray magnetic fields interfering with operation of an MRI machine and allegedly threatening the health of personnel.
All Green was an electrical contractor hired to perform wiring for an MRI unit installation. Stray magnetic fields interfered with the unit’s operation. Efforts to remediate the problem included installing shielding and ultimately relocating the unit to another room. An expert finally determined that a bolt left loose by All Green was causing the magnetic field, which disappeared when the bolt was properly tightened. The facility sought damages for negligence, including costs for unnecessary modifications and repairs, payments to outside sources for substitute mammography testing, operational costs and expenses, damage to reputation, lost profits, and the loss of an HMO contract.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Strategy for Enforcement of Dispute Resolution Rights
May 30, 2018 —
Whitney Judson - Smith CurrieArbitration and litigation each offer their own benefits and drawbacks to litigants looking to resolve a construction dispute. A careful analysis of these benefits and drawbacks may be helpful in determining whether to avoid or pursue either dispute resolution process. Arbitration is oftentimes regarded as the more economically feasible dispute resolution option and is therefore attractive to many construction dispute litigants. Although arbitration may prove to be less expensive than litigation in the long run, some litigants may prefer to file a case in court because the upfront filing fees in litigation are less expensive than the filing fees of arbitration.
Litigants may also prefer the decision makers of one process for dispute resolution over another. Arbitrators in a construction dispute oftentimes have a background in the construction industry, whereas a judge or jury may not. Strategy may dictate whether the preferable decision maker should have experience within the construction industry or be free of any construction industry knowledge and possible biases. The finality of decisions may also be a reason to strategically choose one dispute resolution process over another. Arbitration decisions are overturned only under very narrow and specific circumstances. The losing party in litigation however, has a right to appeal decisions to a higher court and has more options for recourse when the findings of the court are not supported by the evidence or the law.
Read the court decisionRead the full story...Reprinted courtesy of
Whitney Judson, Smith CurrieMs. Judson may be contacted at
wtjudson@smithcurrie.com
Jury Could Have Found That Scissor Lift Manufacturer Should Have Included “Better” Safety Features
January 02, 2024 —
Garret Murai - California Construction Law BlogA few years ago I listened to an NPR segment called “
What Can Kids Learn by Doing Dangerous Things?” It was about a summer program called the Tinkering School where kids can learn to build things, using tools of course, including power tools.
The founder of the program, Gever Tulley, also wrote a book entitled
50 Dangerous Things (You Should Let Your Children Do), in which he argued that while well-intentioned, children today are overly protected, and that giving children exposure to “slightly” dangerous things can help foster independence, responsibility, and problem-solving as well as a healthy dose of caution.
The plaintiff in the next case might have benefitted from that program.
In
Camacho v. JLG Industries Inc., 93 Cal.App.5th 809 (2023), the Court of Appeals examined whether the manufacturer of a scissor lift should have incorporated “better” safety features when a construction worker fell from the lift.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Chicago Criticized for Not Maintaining Elevator Inspections
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Crain’s Chicago Business, “as few as a fifth of elevators get the required annual checkup,” Chicago Inspector General Joe Ferguson claimed.
Ferguson audited the roughly 5,100 buildings that city inspectors were assigned to inspect elevators, and found that only 965 were actually inspected, reported Crain’s Chicago Business. Furthermore, “when problems were found in inspections conducted by city personnel, they often were not fixed in a timely manner, again according to city records.”
Read the court decisionRead the full story...Reprinted courtesy of
Consider Manner In Which Loan Agreement (Promissory Note) Is Drafted
March 02, 2020 —
David Adelstein - Florida Construction Legal UpdatesConsider who you loan money too and, perhaps more importantly, the manner in which your loan agreements (promissory notes) are drafted. By way of example, in what appears to be a failed construction project in Conrad FLB Management, LLC v. Diamond Blue International, Inc., 44 Fla. L. Weekly D2897a (Fla. 3d DCA 2019), a group of lenders lent money to a limited liability company (“Company”) in connection with the development of a project. Promissory notes were executed by Company and executed by its managing member as a representative of Company, and not in a personal capacity. Company, however, did not own the project. Rather, an affiliated entity owned the project (“Affiliated Entity”). Affiliated Entity had the same managing member as Company. Once the Company received the loan proceeds, it transferred the money to Affiliated Entity, presumably for purposes of the project.
The loans were not repaid and the lenders sued Company, Affiliated Entity, and its managing member, in a personal capacity. The lenders claimed they were all jointly liable under the promissory notes. Although the trial court granted summary judgment in favor of the lenders, this was reversed on appeal as to the Affiliated Entity and the managing member because there was a factual issue as to whether they should be bound by the note executed on behalf of Company.
First, Florida Statute s. 673.4011(1) provides that “a person is not liable on a promissory note unless either (a) the person signed the note, or (b) the person is represented by an agent who signed the note.” Conrad FLB Management, LLC, supra. Affiliated Entity is a separate entity and did not execute the note.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Law Job Opps and How to Create Them
October 24, 2021 —
Christopher G. Hill - Construction Law MusingsFor this weeks Guest Post Friday, Kirsten Grant (@kgrantcareers on Twitter) has graced us with her thoughts on a very timely topic: How to get a job as a construction attorney. Before becoming a career specialist at Kaplan University, one of the largest online universities in the nation, Kirsten Grant had faxed almost 1000 resumes, e-mailed close to 300 resumes, personally mailed 20 resumes with each one featuring “special inserts” to encourage hiring managers to read her resume (50% of those resumes received calls for an interview) and interviewed with 50 companies over the course of 5 months. Based on the feedback hiring managers provided, in addition to 10 years experience in human resources, training, recruiting and staffing she REALLY learned what hiring managers look for in a candidate and today helps over 40,000 adult learners understand how to conduct successful job searches and earn a promotions.
As the real estate industry makes torrid adjustments to right itself due to foreclosures, short sales, and falling house prices, court rooms are seeing more construction law cases. As houses and properties fall into states of disrepair and as efforts are taken to repair them a chain of events take place:
- Property is purchased
- Contractors are hired to make repairs to a property
- The selected contractor files permits for the type of work performed
- After work has been performed, contactor receives compensation
Read the court decisionRead the full story...Reprinted courtesy of