Coverage for Faulty Workmanship Found In South Dakota
October 11, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe South Dakota Supreme Court found coverage in favor of the general contractor who was sued for alleged faulty workmanship. Owners Ins. Co. v. Tibke Constr., Inc., 2017 S.D. LEXIS 106 (S.D. Aug. 23, 2017).
The homeowners hired Tibke Construction Inc. as general contractor to build a new house. Tibke hired Jerry's Excavating Inc. as a subcontractor to prepare the soil and perform excavation work. After the project was completed, the homeowners sued Tibke and Jerry's Excavating for negligent construction and breach of contract. The homeowners alleged that Jerry's Excavating failed to conduct soil-compaction testing before construction. They alleged that the home was built upon highly expansive soils, resulting in damage to the home by "excessive settlement, cracking, structural unsoundness and other damages." The complaint further alleged that damages existed only on portions of the home not worked on by Jerry's Excavating.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Montana Supreme Court Tackles Decade-Old Coverage Dispute Concerning Asbestos Mineworker Claims
December 20, 2021 —
Patricia B. Santelle & Paul A. Briganti - White and WilliamsOn November 23, 2021, the Montana Supreme Court issued an almost unanimous decision in National Indemnity Company v. State of Montana, a ten-year-old coverage dispute arising from claims against the State of Montana alleging it had failed to warn of asbestos dust conditions at vermiculite mining and milling operations in and around Libby, Montana (the Libby Mine) run by W.R. Grace & Company and its predecessors. Affirming in part and reversing in part rulings by the trial court that culminated in a $98 million judgment against the State’s CGL insurer from 1973 to 1975, the court addressed issues including the duty to defend/estoppel, the number of occurrences, “trigger of coverage,” and, in a case of first impression, allocation under Montana law.
Whether the Insurer Breached the Duty to Defend Depended Upon the Timeframe
The court looked at whether (1) the insured provided sufficient information to bring the claims within the possibility of coverage under the subject policy and (2) the insurer gave “the necessary substance to” fulfilling its duty to defend at four points in the relevant timeframe:
- The insurer did not breach its duty at the time the State initially tendered the Libby Mine claims because the State defended the claims through its self-insurance program, hired its own counsel, managed the litigation, made its own defense decisions, and took the position with the insurer that the matter was “under control” and “nothing was left to be done[.]”
Reprinted courtesy of
Patricia B. Santelle, White and Williams and
Paul A. Briganti, White and Williams
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The “Unavailability Exception” is Unavailable to Policyholders, According to New York Court of Appeals
September 10, 2018 —
William S. Bennett & Warsame Y. Hassan - Saxe Doernberger & Vita, P.C.The New York Court of Appeals recently upheld a prior appellate division decision finding that policyholders facing environmental claims, spanning multiple years, cannot force their insurers partially on the risk to provide coverage for years where the insurers did not issue policies, even though pollution insurance was unavailable in the marketplace.
In Keyspan Gas E. Corp. v. Munich Reins. Am., Keyspan Gas East Corporation (“Keyspan”) argued other insurers should cover the period when pollution property insurance was unavailable in the marketplace, according to their pro-rata share of coverage. 31 N.Y.3d 51 (2018). In a unanimous decision, the Court emphasized the Appellate Division’s prior ruling that stated, “spreading risk should not by itself serve as a legal basis for providing free insurance to an insured.”
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
PFAS and the Challenge of Cleaning Up “Forever”
July 31, 2023 —
PFAS Team - Gravel2Gavel Construction & Real Estate Law BlogFrom a stream of legal challenges, to ever-expanding regulations on things like cosmetics and drinking water, PFAS are the “forever chemicals” keeping companies and consumers on high alert. While industries scramble to remove the synthetic compounds from products, scientists are researching new techniques for scrubbing PFAS from the environment. There is money to be had for those who can find a more streamlined method of purging the substances—the U.S. Army Corps of Engineers has an $800 million contract on the table for the handling, destruction and replacement of PFAS-laden fire-fighting foam—leaving technology companies racing to create solutions. The three main PFAS cleaning techniques currently relied upon can be very effective but are also costly and may leave questionable byproducts in their wake.
The established approaches include:
- Granular Activated Carbon. As one of the most studied treatments for PFAS removal, granular activated carbon is often used in water treatment plants. Large beds of carbon essentially soak up the unwanted chemicals. After the Sweeney Water Plant in North Carolina, whose water source is downstream from a fluorochemical-producing Chemours plant, was found to be contaminated with PFAS, the plant invested around $46 million into upgraded activated carbon systems. Once installed, these systems cost roughly $2.9 million to operate yearly, as the carbon needs to be replaced each time it reaches capacity. Though pricey, the plant says that the process now clears close to 100% of PFAS.
Read the court decisionRead the full story...Reprinted courtesy of
PFAS Team, Pillsbury
Nobody Knows What Lies Beneath New York City
August 10, 2017 —
Greg Milner - BloombergBefore a single raindrop fell, Alan Leidner knew the waters could rise and throw the city into darkness. On this point, the maps were as clear as a crystal ball. All you had to do was look.
It was 2010, and Leidner was consulting for the government services company Booz Allen Hamilton Inc., contracted by the U.S. Department of Homeland Security to identify potential threats and vulnerabilities in the nation’s critical infrastructure. Leidner was examining a region that included New York and New Jersey. One day he was thinking about the area’s electrical power grid. He consulted some flood projection maps the Federal Emergency Management Agency had prepared. Then he stared at a map of the grid maintained by Consolidated Edison Inc., the region’s power supplier. And it just jumped out at him: The substation at East 13th Street, on the banks of the East River, was smack in the middle of a flood zone.
Leidner voiced his concerns with utilities, hospitals, and other major facilities. “The reaction was mostly, ‘Eh,’ ” he recalls, as we sit in the Tribeca offices of the Fund for the City of New York, where he directs the nonprofit organization’s Center for Geospatial Innovation.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Milner, Bloomberg
California Insurance Commissioner Lacks Authority to Regulate Formula for Estimating Replacement Cost Value
April 15, 2015 —
Valerie A. Moore and Christopher Kendrick – Haight Brown & Bonesteel LLPIn Assn. of Cal. Insurance Companies v. Jones ( No. B248622, filed 4/8/15), a California appeals court held that California’s Insurance Commissioner Dave Jones lacked the authority to promulgate California Code of Regulations, title 10, section 2695.183, which set out specific requirements for estimating replacement cost as part of any application or renewal for homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the wildfires in Southern California in 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Negligence Claim Not Barred by Gist of the Action Doctrine
February 18, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Pennsylvania Supreme Court held that the insureds' negligence claim survived because it was not based upon breach of a duty created by the policy, but upon the alleged breach of a duty imposed by tort law. Bruno v. Erie Ins. Co,, 2014 Pa. LEXIS 3319 (Dec. 15, 2014).
After purchasing their home, the insureds obtained a homeowner's policy from Erie. A separate endorsement covered loss to the property caused by "fungi," which was included as any form of mold. The endorsement obligated Erie to pay up to $5,000 for loss caused by mold. The policy required Erie to pay the cost of testing the air to confirm the absence or presence of mold. If mold was present, Erie was to pay for the cost of removal, including the cost of tearing out any part of the property needed to gain access to the mold.
While renovating the basement, the insureds discovered two areas of black mold in close proximity to leaking water pipes. Erie was notified and sent an adjuster to view the mold. The adjuster took no action, but returned a couple of days later with an engineer. The adjuster and engineer informed the insureds that the mold was harmless and that health problems associated with mold were a media frenzy and overblown.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Corps Proposes $4.6B Plan to Steel Miami for Storm Surge
June 22, 2020 —
Pam Radtke Russell - Engineering News-RecordA $4.6-billion U.S. Army Corps of Engineers proposal to protect Miami from future storm surge, largely by building massive sea walls and elevating infrastructure systems, is the latest of such plans the agency has developed for East Coast communities.
Pam Radtke Russell, Engineering News-Record
Ms. Russell may be contacted at Russellp@bnpmedia.com