Roof's "Cosmetic" Damage From Hail Storm Covered
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Seventh Circuit affirmed the district court's determination that cosmetic damage to the insured's roof was covered. Advance Cable Co., LLC v. Cincinnati Ins. Co., 2015 U.S. App. LEXIS 9805 (7th Cir. June 11, 2015).
The insured submitted a claim to its insurer, Cincinnati, for damage to the metal roof of its building caused by a hail storm. The insured inspected the roof with a claims representative for Cincinnati. Dents were spotted, but there was little other evidence of damage. The loss was estimated at $1,894.74. A check for this amount was sent to the insured.
Six months later, the insured considered selling the building. A potential buyer inspected the roof and found hail damage. At the request of the insured, Cincinnati conducted another inspection of the roof. Again, dents of approximately 1 inch in diameter were found. The inspector noted that the denting would not affect the performance of the roof panels or detract from their life expectancy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Addresses HOA Attempt to Restrict Short Term Rentals
December 11, 2018 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn a recent case, the Texas Supreme Court addressed an attempt by a homeowners’ association (“HOA”) to restrict short-term rentals based upon recorded Covenants, Conditions, and Restrictions (“CC&Rs”) applicable to a residential subdivision. The property was a single-family home. The homeowner rented the home through websites such as VRBO. The HOA issued notices of violation; the homeowner kept renting; the HOA assessed fines against the property. The property owner then sought a declaration from the court that the CC&Rs did not impose a minimum duration on occupancy or leasing. The trial court agreed with the HOA. The Texas Court of Appeals also agreed with the HOA. The Texas Supreme Court reversed, holding that the CC&Rs, as properly interpreted, did not prohibit short-term rentals. In arriving at its holding, the Texas Supreme Court analyzed the CC&Rs in detail and came to an interpretation different than the trial court and the Court of Appeals.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
The General Assembly Adds Some Clarity to Contracts and Unlicensed Contractors
March 28, 2018 —
Christopher G. Hill – Construction Law MusingsFor years, the statute regarding performing construction without a valid license (
Va. Code 54.1-1115) was a bit murky. While that statute listed several prohibited acts, among them contracting without the proper class of license or use of the license of another, the consequences of such activity, in particular the effect that such action would have on the enforcement of a construction contract (Section C of the statute), were less than clear.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Approaches to Managing Job Site Inventory
January 04, 2018 —
Jessica Stark - Construction InformerOriginally Published by CDJ on August 30, 2017
There is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
Illinois Law Bars Coverage for Construction Defects in Insured's Work
September 24, 2014 —
Tred R. Eyerly – Insurance Law HawaiiApplying Illinois law, the Seventh Circuit determined there was no coverage for faulty workmanship causing property damage to the insured's project. Nautilus Ins. Co. v. Board of Directors of Regal Lofts Condominium Ass'n, 2014 U.S. App. LEXIS 16250 (7th Cir. Aug. 21, 2014).
The developer converted a vacant building into a condominium. The construction was completed in 2000. The Condominium Board took control of the condo association on July 27, 2000. As early as May 2000, one homeowner was aware of water damage problems in the building. Other complaints surfaced. An investigation found that the exterior brick masonry walls were not fully waterproofed, which caused leaks. The investigation further showed that deteriorated conditions had likely developed over many years, even prior to the condominium conversion, but the present water penetration was caused by the inadequate restoration of the walls to a water-tight condition.
The underlying action was filed against the developer for failure to properly construct the exterior walls. The developer's carrier, Nautilus, denied coverage. In an amended complaint, the Board added a count of negligence. Again, Nautilus denied coverage. The Board's second amended complaint alleged that the developer's negligence had caused damage to personal property within the building, in addition to the interior of the building and the building itself. For the third time, Nautilus denied coverage and filed for declaratory relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Should a Subcontractor provide bonds to a GC who is not himself bonded? (Bonding Agent Perspective)
May 03, 2017 —
Christopher G. Hill - Construction Law MusingsGuest Post Friday is back, and for this week, Construction Law Musings welcomes Steve Moore. Steve has been the Construction & Surety Manager for Towne Insurance Agency-Invincia, in Chesterfield, VA since 2010. Steve’s experience in the Virginia surety bonding marketplace started in 1985 with USF&G. His underwriting travels took him from USF&G to starting National Grange Mutual’s mid-Atlantic bond department over Virginia, Maryland, Delaware, North & South Carolina, to being Reliance Surety’s “Firemark” bond manager in Virginia. Reliance was purchased by Travelers, where Steve continued to grow the surety book of business and build expertise and relationships. Experience with Travelers and Zurich had Steve handling surety bonds for some of Virginia’s largest and best-of-class contractors. Recently, he was contracted by the Commonwealth’s Attorney’s office to serve as a contract surety expert witness on behalf of the state. He is a 1985 graduate of Virginia Tech with double-major B.S. degrees in Finance and Marketing.
Today, Steve has business and relationships with Travelers, The Hartford, Westfield, CNA, CBIC, Selective, Liberty Mutual, Ohio Casualty, Cincinnati, and many other companies. Steve’s strong foundation of insurance knowledge and in bonding principles and practices allow him to serve as a great resource for his clients.
An old Aesop fable comes to mind when I am asked whether a Sub should bond to an unbonded GC:
"A woodsman entered the forest and asked the trees to give him a handle made of the best wood. After giving the woodsman a stave of hickory, the forest watched the woodsman fashion an axe onto the handle. In a flash, the woodsman began to chop down the various oaks and maples in the forest. The oak then said to a pine, “It serves us right, since we gave our adversary the very thing that contributes to our doom…"
When a subcontractor client of mine asks about bonding to an un-bonded general contractor, a number of questions immediately come to mind. Why isn’t the GC bonded? What is the existing relationship between the GC and Sub? How well is the job financed? While wanting to help my subcontractor procure work, and surely enjoying the commissions from writing a bond, I also want to help my sub client manage unforeseen risk. What are the risks to a sub, when posting a bond to an unbonded GC?
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Florida Law: Interplay of SIR and the Made-Whole Doctrine
March 12, 2015 —
Beverley BevenFlorez-CDJ STAFFAmanda Baggett of Roger Towers explained the nuances of self-insured retention or “SIR,” which “typically refers to a dollar amount stated in a liability policy that the insured must satisfy before the insurer is required to defend or indemnify a claim.” Baggett stated that most of the time, the SIR is satisfied by the insurer paying the initial defense costs up to the SIR. However, “the Florida Supreme Court has held that an insured may satisfy the SIR using funds received from a third party. Intervest Construction of Jax, Inc. v. General Fidelity Ins. Co., 133 So. 3d 494 (Fla. 2014).”
Read the court decisionRead the full story...Reprinted courtesy of
Commencing of the Statute of Repose for Construction Defects
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida has a ten-year statute of repose which applies predominantly to construction defect claims. This can be found in Florida Statute s. 95.11(3)(c). After ten years, any rights relative to a construction defect claim are time-barred. However, the statute of repose date has been watered down and can be made to be more of a factual question due to the lack of objectivity as to the date that starts the ten-year repose clock. The watering down of the statute of repose date benefits parties asserting construction defect claims provided they strategically appreciate the question of fact that can be created when up against the statute of repose. Stated differently, when up against the clock to assert a construction defect claim, strategically develop those facts, evidence, and arguments to maximize creating a question of fact as to when the statute of repose clock commenced. Conversely, as a defendant sued for construction defects, you want to maximize the facts, evidence, and arguments to fully establish the date the statute of repose clock had to commence for purposes of a statute of repose defense.
The recent opinion in Spring Isle Community Association, Inc. v. Herme Enterprises, Inc., 46 Fla. L. Weekly D2306b (Fla. 5th DCA 2021) demonstrates the factual question associated with the clock that starts the statute of repose date. This factual question is created by Florida Statute s. 95.11(3)(c) that provides:
[T]he action [founded on the design, planning, or construction of an improvement to real property] must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.
Spring Isle Community Association, supra. (Note, see also current s. 95.11(3)(c) version in effect per hyperlink above.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at