The Fourth Circuit Applies a Consequential Damages Exclusionary Clause and the Economic Loss Doctrine to Bar Claims by a Subrogating Insurer Seeking to Recover Over $19 Million in Damages
February 23, 2016 —
William L. Doerler – White and Williams LLPIn Severn Peanut Company, Inc. v. Industrial Fumigant Company, 807 F.3d 88 (4th Cir. (N.C.) 2015), the United States Court of Appeals for the Fourth Circuit (Fourth Circuit), applying North Carolina law, considered whether a consequential damages clause in a contract between the Severn Peanut Company, Inc. (Severn) and Industrial Fumigant Company (IFC) barred Severn and its subrogating insurer, Travelers Property Casualty Company of America (Travelers), from recovering over $19 million in damages that Severn suffered as the result of a fire and explosion at its Severn, North Carolina plant. The Fourth Circuit, rejecting Severn’s unconscionability and public policy arguments related to the consequential damages clause and finding that the economic loss doctrine barred Severn from pursuing negligence claims, affirmed the trial court’s judgment granting summary judgment in IFC’s favor.
As noted in the Severn decision, the facts showed that Severn and IFC signed a Pesticide Application Agreement (PAA) requiring IFC to use phosphine, a pesticide, to fumigate Severn’s peanut storage dome and to apply the pesticide “in a manner consistent with instructions . . . and precautions set forth in [its] labeling.” With respect to damages, the PAA specified that IFC’s charge for its services, $8,604 plus applicable sales tax, was “based solely upon the value of the services provided” and was not “related to the value of [Severn’s] premises or the contents therein.” In addition, the PAA specified that the $8,604 sum to which the parties agreed was not “sufficient to warrant IFC assuming any risk of incidental or consequential damages” to Severn’s “property, product, equipment, downtime, or loss of business.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Southern California Lost $8 Billion in Construction Wages
August 17, 2011 —
CDJ STAFFLos Angeles and Orange Counties are first on a list no area wants to be on. According to the Sacramento Bee, reporting on data from the U.S. Bureau of Economic Analysis, LA and Orange Counties saw an $8 billion drop in construction wages in 2010, as compared to 2006. In 2006, the region saw payrolls of $26.8 billion, but in 2010, that was reduced to $18.5 billion.
This was not the largest percentage change. Of the metropolitan areas with the largest declines in construction earnings, Las Vegas saw a $3.6 billion drop, however that represented half of their 2006 totals of $7.2 billion. Conversely, a $3.3 billion drop in the New York area represented only 10% of what had been $33.8 billion in payroll in 2006.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Rules that Developers Retain Perpetual Control over Construction Defect Covenants
June 21, 2017 —
Jesse Witt - The Witt Law FirmThe Colorado Supreme Court ruled today that developers can retain control over community covenants in perpetuity by recording a covenant that requires declarant consent to any amendments. Although the Colorado Common Interest Ownership Act (CCIOA) states that such controls should be void, the court nevertheless ruled that a declarant may veto amendments that alter the dispute resolution procedures for construction defect actions at any time.
The case of Vallagio at Inverness Residential Condominium Ass’n v. Metropolitan Homes, Inc., __ P.3d __, 15CO508, arose when the community’s members discovered widespread construction defects. When the declarant developed the project, it had recorded a declaration of covenants that purported to waive the homeowners’ right to a jury trial and instead require that any construction defect disputes be resolved by a private arbitration panel. The declaration also prohibited the homeowners from recovering attorney fees and costs, and it limited the declarant’s liability for damages. Consistent with CCIOA, the declaration allowed the homeowners to amend their covenants by a 67% vote, but it recited that the declarant could veto any such amendment prior to the sale of the last unit to a homeowner. The covenants further stated that the declarant must consent to any amendment that altered the construction defect restrictions.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Cross-Motions for Partial Judgment on the Pleadings for COVID-19 Claim Denied
May 24, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied both parties' motions for partial judgment on the pleadings seeking clarification of the policy's contamination exclusion. Thor Equities, LLC v. Factory Mut. Ins. Co., 2021 U.S. Dist. LEXIS 62967 (S.D. N.Y. March 31, 2021).
Thor was a commercial landlord, renting properties across the country to hundreds of tenants, for use in a variety of businesses, including office space, retail stores, restaurants, and bars. When state governments began shutting down businesses and issuing stay-at-home orders in March 2020, many of Thor's tenants had to close shop and sought abatements or other accommodations. Thor alleged it suffered significant business interruption as a result of the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Homebuilding Down in North Dakota
October 30, 2013 —
CDJ STAFFOnly eleven new homes have been started this year in the Pierre area in North Dakota. Last year saw 35 homes built in the same area. Brad Lawrence, the Fort Pierre Director of Public Works, blamed last year’s Hurricane Sandy in New Jersey, stating that “superstorm Sandy has just devoured a tremendous amount of building projects.”
Area builders did say that some building materials went up in price after the storm, describing it as an “availability scare,” but some prices went down during the summer of 2013. Susan Ogan, of Neil Ogan Construction said that “our biggest thing is that people cannot find a lot they can afford and still say within their budget for the overall project.”
Although single-family homes aren’t being built, apartments are. “We’ve got a 24-unit apartment going in as we speak,” said Mr. Lawrence. That, some feel, may be responsible for the lack of demand for single-family homes.
Read the court decisionRead the full story...Reprinted courtesy of
Five "Boilerplate" Terms to Negotiate in Your Next Subcontract
November 08, 2017 —
James R. Lynch - Ahlers & Cressman PLLCWhether you negotiate your own subcontracts or rely on your lawyer to do the heavy lifting at contract time, a savvy subcontractor should understand the basic purpose of common subcontract provisions, and be prepared to negotiate for fair and commercially reasonable terms. While most sophisticated subcontractors are skilled at negotiating the core terms of a subcontract—scope of work, price, and time—a few simple but less obvious tweaks to common subcontract terms and conditions can go a long way to protect a subcontractor from unfair results when a dispute arises.
From the desk of an experienced construction lawyer, below are the first three of the top five “boilerplate” provisions that subcontractors too often overlook during contract negotiations, along with tips on language to include and to avoid.
Read the court decisionRead the full story...Reprinted courtesy of
James R. Lynch, Ahlers & Cressman PLLCMr. Lynch may be contacted at
jlynch@ac-lawyers.com
A Compilation of Quirky Insurance Claims
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 showcased five “nutty claims stories” based upon recollections by several insurance professionals.
Number four, subtitled, “The Case of the Soaked Survivalists,” described a claim by an elderly couple who “made a $350,000 water-damage claim after heavy rains and an inadequate sump pump ruined what they described as thousands of ‘valuable items’ in their storage area.” However, a claims adjuster discovered during the investigation that the area in question was actually a bomb shelter built during the Cold War era, and the so-called valuable items were actually “soap, toothpaste, canned goods, and more.” The insurer ended up settling for about $200,000.
Read the court decisionRead the full story...Reprinted courtesy of
A Few Green Building Notes
December 02, 2019 —
Christopher G. Hill - Construction Law MusingsThis past week, the blogosphere (if that’s even the word these days) has been abuzz about green building and the value that green can add to a project. Three items in particular (among many) got my attention.
The first of these was the fact that a new private sustainability rating system is ready for launch. The Institute for Sustainable Infrastructure (or ISI) is seeking public comment on its proposed envISIon. This new system (aptly dubbed Version 1.0) will go “live” in July for comment. Why mention this new system? First of all, ISI’s founding members are the American Society of Civil Engineers (ASCE), the American Public Works Association (APWA) and the American Council of Engineering Companies (ACEC). This trio gives the new program some fairly heavy weight backing. Second, while there are rating systems aside from the ever present LEED, none have taken hold in any real way to compete with LEED. I am curious to see if the envISIon system has any better luck. Finally, this shows that sustainable building is of interest to more than the USGBC and those of us that discuss LEED on a daily basis. I find this to be a great thing that could lead to more societal acceptance of sustainable practices as a standard practice rather than a goal.
Hopefully such efforts will offset the other two notes that caught my eye recently.
The first of these is the foreclosure of the Chapel Hill, North Carolina Greenbridge project. This project is well documented at my friend Doug Reiser’s (@douglasreiser) Builders Counsel blog so I won’t further discuss the details here. However, the question that Doug asks is a good one, i. e. were the “green” elements of the project to blame?
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at