Construction Termination Part 2: How to Handle Construction Administration When the Contractor Is Getting Fired
August 01, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaIf you’ve been working as a design professional for any length of time, you know that you must be a chameleon on the construction project. You need to “step into the skin” of both the Owner and the Contractor to determine who is at fault, and who should pay.
You are usually the Initial Decision Maker (IDM), and so you have a duty under the AIA documents to act fairly and impartially in making those decisions. See AIA B101§3.6.2.4.
Even if you are not under an AIA contract, you still have that duty if you are the IDM or handling construction administration for the project. More often than not, however, it will be the owner asking you to support its termination of the contractor “for cause.”
Should you do so?
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Alert: AAA Construction Industry Rules Update
June 07, 2021 —
Christopher G. Hill - Construction Law MusingsThe American Arbitration Association has made some needed updates to their Construction Industry Arbitration and Mediation Rules, effective July 1, 2015. Among the changes listed at their website are:
- A mediation step for all cases with claims of $100,000 or more (subject to the ability of any party to opt out).
- Consolidation and joinder time frames and filing requirements to streamline these increasingly involved issues in construction arbitrations.
- New preliminary hearing rules to provide more structure and organization to get the arbitration process on the right track from the beginning.
- Information exchange measures to give arbitrators a greater degree of control to limit the exchange of information, including electronic documents.
- Availability of emergency measures of protection in contracts that have been entered into on or after July 1, 2015.
- Enforcement power of the arbitrator to issue orders to parties that refuse to comply with the Rules or the arbitrator’s orders.
- Permissibility of dispositive motions to dispose of all or part of a claim or to narrow the issue in a claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hawaii Appellate Court Finds Duty to Defend Group Builders Case
May 10, 2013 —
Tred EyerlyOn May 19, 2010, the Hawaii Intermediate Court of Appeals determined construction defect claims did not constitute an occurrence under a CGL policy.Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010) ("Group Builders I"). The appeal in Group Builders I, however, only addressed the duty to indemnify. The ICA has now issued a second decision (unpublished), holding that there is was duty to defend Group Builders on the construction defect claims under Hawaii law, based upon the policy language and the allegations in the underlying complaint. Group Builders, Inc. v. Admiral Ins. Co., 2013 Haw.App. LEXIS 207 (Haw. Ct. App. April 15, 2013).
The underlying suit involved allegations by Hilton Hotels Corp. that Group Builders, a subcontractor working on an addition to the hotel, was responsible for mold found after completion of the project. Hilton alleged that the "design, construction, installation, and/or selection of the . . . building exterior wall finish . . . did not provide an adequate air and/or moisture barriers." The counts alleged against Group Builders included breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at
te@hawaiilawyer.com
Cal/OSHA-Approved Changes to ETS Will Take Effect May 6, 2022
May 16, 2022 —
Matthew C. Lewis & Nicole R. Kardassakis - Payne & FearsA new, third revised version of the Cal/OSHA COVID-19 Prevention Emergency Temporary Standards (“ETS”) has been approved by Cal/OSHA, and is expected to go into effect on May 6, 2022. This updated ETS will likely be in effect through Dec. 31, 2022.
The language still needs to be reviewed, finalized, and filed with the Secretary of State by the Office of Administrative Law, but a redline of the proposed changes that Cal/OSHA has approved is available here. Much of the previous ETS (which took effect in January 2022, and we discussed here) will remain in effect. But the new version includes some key changes, including the following:
- Employers will now have similar obligations toward employees who are fully vaccinated and employees who are not fully vaccinated with respect to testing and face coverings. Employers must make COVID-19 testing available at no cost to all symptomatic employees during the employee’s paid time, regardless of the employee’s vaccination status. Employers also must make respirators available to all employees upon request, again regardless of the employee’s vaccination status.
Reprinted courtesy of
Matthew C. Lewis, Payne & Fears and
Nicole R. Kardassakis, Payne & Fears
Mr. Lewis may be contacted at mcl@paynefears.com
Ms. Kardassakis may be contacted at nrk@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Performing Work with a Suspended CSLB License Costs Big: Subcontractor Faces $18,000,000 Disgorgement
September 17, 2015 —
Steven M. Cvitanovic & David A. Harris – Haight Brown & Bonesteel LLPIn what could lead to a draconian result, the Court of Appeal for the First Appellate District held that a contractor who performs work without a valid license can be required to disgorge all payments received, even if the contractor perfectly performed its work. The case, Judicial Council of California v. Jacobs Facilities, Inc. (Ct. of Appeal, 1st App. Dis., Div. One, A140890, A141393), involved an $18,000,000 contract between Jacobs Facilities, Inc. (“Jacobs Facilities”) and the Judicial Council of California (“Judicial Council”). In April 2006, Jacobs Facilities, a wholly owned subsidiary of Jacobs Engineering Group, Inc. (“Jacobs Engineering”) entered into a three year contract with the Judicial Counsel to maintain 121 courthouses and other judicial branch buildings throughout Southern California (the “Contract”). Jacobs Facilities contracted to provide maintenance and oversight services, while retaining subcontractors to perform the actual maintenance and repair work.
In December 2006, as part of a corporate reorganization, Jacobs Engineering started winding up Jacobs Facilities and transferred its employees to Jacobs Engineering and then subsequently to another wholly owned subsidiary called Jacobs Project Management Co. (“Jacobs Management”). The work that was performed by Jacobs Facilities was taken over by Jacobs Management. As part of the windup, Jacobs Facilities’ Contractor’s State License Board license was allowed to lapse and the license expired by operation of law in November 2008. Although Jacobs Management was now performing the work, it was not added as a party to the contract. Although it appears Judicial Council was aware of the corporate changes, it was not until November 2009 that the parties assigned the contract to Jacobs Management.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
David A. Harris, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Harris may be contacted at dharris@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Taylor Morrison Home Corp’ New San Jose Development
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Silicon Valley Business Journal reported that Taylor Morrison Home Corp has made the “biggest land acquisition so far in San Jose” after acquiring “an 8-acre chunk of dirt in the developing Montecito Vista area where it has plans to build out 184 townhomes.”
The developer “paid about $32.5 million, or roughly $176,600 per buildable unit, for the land, according to public tax records,” according to the Silicon Valley Business Journal. Construction is scheduled to begin November of 2015 and models should be ready by April of 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (5/29/24) – Megaprojects on the Rise, Agency Guidance for CRE, and an Upbeat Forecast for Commercial Real Estate Investment
June 21, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, summer travelers seek alternative lodging options, purpose-built wellness real estate investments grow, bonds backed by CRE debt hit are hit with losses, and more!
- Across all property types, purpose-built wellness real estate investment has grown dramatically in recent years, including properties with wellness features as a focus. (Mary Salmonsen, Multifamily Dive)
- The travelers on the road this summer will have different demographics, budgets and reasons for travel and different preferences on accommodations, with more travelers opting for alternative housing options. (Noelle Mateer, Hotel Dive)
- Megaprojects are on the rise, with massive projects, from rail tunnels to computer chip factories, having myriad stakeholders and lengthy timelines that span political administrations. (Julie Strupp, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Potential Pitfalls Under the Contract Disputes Act for Federal Government Contractors
February 28, 2018 —
Sarah K. Carpenter – Smith Currie PublicationsThe Contract Disputes Act (CDA) governs monetary and non-monetary disputes arising out of contracts or implied-in-fact contracts between the federal government and contractors. Because the CDA is an exclusive remedy, it is important that contractors be wary of the many pitfalls that may be encountered by a contractor seeking to assert a claim against the government under the CDA.
The pitfalls faced by a contractor under the CDA can arise before a contractor becomes aware of a potential claim. Pursuant to the Federal Acquisition Regulation (FAR) § 43.204(c), a contracting officer should include in any supplemental agreement, including any change order, a Contractor’s Statement of Release which requires a contractor to execute a broad release of the government from any and all liability under the contract. As a result of this FAR provision, in executing a routine change order, a contractor may inadvertently release its right to pursue a potential claim under the CDA. A contractor should always review any release language prior to executing a supplemental agreement or change order with the government.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah K. Carpenter, Smith CurrieMs. Carpenter may be contacted at
skcarpenter@smithcurrie.com