The Importance of the Subcontractor Exception to the “Your Work” Exclusion
May 16, 2018 —
John J. Kozak, Esq. - Florida Construction Law NewsCommercial General Liability (CGL) policies typically include a “your work” exclusion, excluding coverage for “’property damage’ to ‘your work’ arising out of it or any part of it and included in the ‘products-completed operations hazard.’” These CGL policies define “your work,” in pertinent part, as “work or operations performed by you or on your behalf.” (emphasis added). As the recent case of Mid-Continent Cas. Co. v. JWN Construction, Inc., 2018 U.S. Dist. LEXIS 20529 (S.D. Fla. 2018) reminds us, the “your work” exclusion can serve to eliminate coverage for a general contractor, even when property damage is caused by a subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Kozak, Esq., Cole, Scott & Kissane, P.A.Mr. Kozak may be contacted at
john.kozak@csklegal.com
Toolbox Talk Series Recap - Guided Choice Mediation
November 05, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the September 26, 2024 edition of Division 1's Toolbox Talk Series,
Clifford Shapiro presented on Guided Choice Mediation (“GCM”) and how it can lead to better outcomes in construction disputes.
GCM is an approach to mediation that focuses on early and efficient dispute resolution, which prominent mediators created as a public interest project.
Shapiro described his particular variant of GCM based on his experience while acknowledging that other Guided Choice Mediators’ processes may differ from his in various ways. Shapiro’s brand of GCM focuses on ensuring that parties have reasonable expectations and appropriate settlement authority prior to arriving at a mediation. Some of the strategies to help accomplish these noble goals are (i) early mediator engagement, (ii) mediator facilitation of information exchange, (iii) mediator involvement with insurance issues (particularly important in construction defect cases, especially those with multiple defendants), (iii) pre-mediation ex parte meetings, and (iv) mediator participation in risk analysis. These strategies are not typical in the more traditional/historic approach to mediation in which mediation is scheduled based on a scheduling order, mediation statements are sent to the mediator roughly a week before the scheduled mediation (and sometimes not even shared with anyone other than the mediator), and the parties speak with the mediator for the first time on the day of the mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com
Construction Litigation Roundup: “Wrap Music to an Insurer’s Ears?”
February 05, 2024 —
Daniel Lund III - LexologyThe general contractor on a New Orleans condominium construction project obtained a Contractor Controlled Insurance Program/CCIP policy or "Wrap-Up" policy for the job.
An accident occurred on the job when a construction elevator/hoist fell, injuring several workers. The elevator/hoist was provided by a subcontractor, pursuant to a rental agreement and related subcontract with the general contractor. Contained within the subcontract was a provision which states that the general contractor "has arranged for the Project to be insured under a controlled insurance program (the "CCIP" or "WrapUp"),” and that the CCIP shall provide "commercial general liability insurance and excess liability insurance, in connection with the performance of the Work at the Project site."
A third-party administrator for the wrap-up policy had been in communication with the subcontractor prior to the commencement of the work, “specifically advising that insurance coverage was not automatic” and providing the subcontractor with an enrollment form for the CCIP. Ultimately, the subcontractor “declined to comply with the request,” stating that the subcontractor would "not participate in paying any wrap insurance premiums" – because the subcontractor had its own insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Washington State Safety Officials Cite Contractor After Worker's Fatal Fall
October 09, 2023 —
James Leggate - Engineering News-RecordInspectors with the Washington State Dept. of Labor & Industries found that flipper deck platforms were not used in line with the manufacturer’s specifications on a jobsite where a worker was killed in a fall earlier this year. Officials cited a contractor, SAK Builders Inc., for $16,800 in penalties over three alleged serious violations.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Government’s Termination of Contractor for Default for Failure-To-Make Progress
July 10, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhenever you elect to terminate the other party for cause or for default, you need to JUSTIFY the basis of the cause or default. The reason being is that a termination for default or cause is the harshest contractual remedy. This is why the other party will typically either (i) convert the termination for default into one for convenience, or (ii) if there is no termination for convenience provision in the contract, argue the terminating party breached the contract by terminating the contract without rightful justification.
The key is if you are going to terminate a party for cause of default, make sure you have memorialized the persuasive reasons for exercising the termination, and can otherwise reasonably support the justification. Do not, and I repeat, do not haphazardly exercise a termination for default and think you do not have to justify the basis for the termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Another Law Will Increase Construction Costs in New York
May 29, 2023 —
Bill Wilson - Construction Law ZoneNew York recently enacted legislation known as Carlos’ Law, which increases penalties for corporate liability for the death of, or serious injury to, an employee. The bill, S.621B / A.4947B, was named after Carlos Moncayo, a construction worker killed in a trench collapse on a New York City construction project. Moncayo’s employer repeatedly flouted safety rules and ignored warnings of dangerous conditions on its construction site before failing to properly support the trench that collapsed and killed Moncayo. Moncayo’s employer was convicted for his death, but the penalty was light. The company was sentenced to pay only $10,000, the maximum penalty at the time for any company convicted of a felony in New York State. The legislature responded with Carlos’ Law, which increases accountability for “employers,” and expands the scope of “employees” covered.
The corporate criminal law, NY Penal § 20.20(2)(c)(iv), imposes liability on an employer when “the conduct constituting the offense is engaged in by an agent of the corporation while acting within the scope of his employment and on behalf of the corporation, and the offense is . . . in relation to a crime involving the death or serious physical injury of an employee where the corporation acted negligently, recklessly, intentionally, or knowingly.” An “agent” of an employer is any “director, officer or employee of a corporation, or any other person who is authorized to act on behalf of the corporation.” § 20.20(a). An “employee” now includes any person providing labor or services for remuneration for a private entity or business within New York State without regard to an individual’s immigration status, and includes part-time workers, independent contractors, apprentices, day laborers and other workers. § 10.00 (22). The penalties for criminal corporate liability for the death or serious injury of an employee now include maximums of $500,000 when centered on a felony, and $300,000 when centered on a misdemeanor. § 80.10(1)(a) and (b).
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
The World’s Largest 3D-Printed Neighborhood Is Here
March 20, 2023 —
Todd Woody - BloombergAmid the tech boom-fueled sprawl in Austin, Texas, Wolf Ranch at first appears to be another colorfully named but architecturally unimaginative suburban subdivision. Until, that is, you turn a corner and stumble across giant robots building homes resembling waves frozen in concrete.
This 100-house addition to the 2,500 homes planned for Wolf Ranch is called “the Genesis Collection,” and as the world’s largest 3D-printed community, it is indeed sui generis. A collaboration between Lennar Corp., the US’s second-biggest home builder, and 3D-printing startup Icon, Genesis represents perhaps the most significant innovation in residential construction in decades. If it can scale, 3D-printed construction promises to deliver energy-efficient homes that can be built faster and more affordably, in novel designs and with minimal waste. The concrete structures are also more resilient to increasingly intense climate-driven hurricanes, wildfires and heat waves.
“I think we'll look back and say this was a pretty pivotal moment in the history of construction,” says Jason Ballard, Icon’s cowboy hat-wearing co-founder and chief executive officer. “I do think 3D printing and robotic construction are necessary to end the global housing crisis.”
Read the court decisionRead the full story...Reprinted courtesy of
Todd Woody, Bloomberg
Recovering Unabsorbed Home Office Overhead Due to Delay
May 30, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn the
preceding article, I discussed the use of a retrospective as-built delay analysis in a case before the Civilian Board of Contract Appeals (CBCA). This case also discussed a damages component in certain delay claims known as unabsorbed home office overhead—a challenging damages component to recover because this deals with indirect costs as opposed to direct costs.
Unabsorbed home office overhead is a damages component when the contractor is on standby, but this is NOT as easy as just claiming standby thereby you are automatically entitled to unabsorbed home office overhead. There are requirements that MUST be met.
To obtain an equitable adjustment for unabsorbed home office overhead as compensation for being on standby, [the contractor] must initially show “[1] a government-caused delay of uncertain duration,” that “[2] the delay extended the original time for performance” or precluded the contractor from finishing earlier than scheduled, and that “[3] the contractor [was] on standby and unable to take on other work during the delay period.
CTA I, LLC v. Department of Veteran Affairs, CBCA 5826, 2022 WL 884710 (CBCA 2022) quoting Nicon, Inc. v. U.S., 331 F.3d 878, 883 (Fed. Cir. 2003).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com