Intricacies of Business Interruption Claim Considered
January 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiReaching into the weeds to analyze a business interruption claim, the Massachusetts Court of Appeals determined the cost of ordinary payroll could be included in the calculation of net profit or loss in determining business loss income when business is resumed quickly after a fire. Verrill Farms, LLC v. Farm Family Cas. Ins. Co., 2014 Mass. App. LEXIS 145 (Mass. App. Ct. Nov. 4, 2014).
The insured suffered a fire loss at its farm store. Within two days, the business was reopened at alternate locations at reduced capacity. Within a month, the business had resumed nearly full capacity in temporary locations. No employees were laid off. This allowed the insured to maintain its business and generate income.
The insured submitted a claim for loss of business income, based on its loss of net income in the year after the fire. The insurer paid a sum considerably less than the claim based upon its interpretation of what expenses could be included in a calculation of net profit or loss in order to determine loss of business income. The trial court held that the insurer did not have to pay the cost of ordinary payroll beyond the sixty-day limit, and granted summary judgment in the insurer's favor.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Litigation Roundup: “Tender Is the Fight”
August 21, 2023 —
Daniel Lund III - LexologyA performance bond surety for a defaulted general contractor principal found itself with a recalcitrant owner which refused to accept the tender of a replacement general contractor to complete a $3,000,000 construction project in Monmouth County, New Jersey.
Even before the original GC was off the job, the surety – having been notified of the contractor’s difficulties in performing the work – stepped in promptly, providing assistance in the form of an additional contractor. At the surety’s behest, that additional contractor remained on the project (focused principally at the time on roof repairs) after the initial GC was placed in default and terminated.
Eventually, the surety, by draft tender agreement issued to the owner, offered that the additional contractor serve as the completion contractor for the entire project (not simply the roof repairs), a proposal rejected by the owner – which had never cared for the additional contractor. Instead, the owner proposed its own completion contractor and, in connection with that offer, demanded a sum of money ($1.6 million) from the surety – a proposal the surety rejected: “[Owner] cannot choose whatever contractor it wants to complete the work and then charge the costs to [the surety]."
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Ambush Elections are Here—Are You Ready?
May 07, 2015 —
Craig Martin – Construction Contractor AdvisorOn April 14, 2015, the National Labor Relations Board’s new election rule went into effect. The new rule, which shortens the time frame for union elections, will make it easier for unions to organize. Employers must get prepared now, not when they hear about an election. As the NLRB Members who dissented from the final rule noted:
"The Final Rule has become the Mount Everest of regulations: Massive in scale and unforgiving in its effect. Very few people will have the endurance to read the Final Rule in its entirety."
Here are some highlights of the new rule:
- Within 2 business days after service of the Notice of the Pre-Election Hearing, the employer must post a Notice of Petition for Election. The employer must also distribute the notice via e-mail if the employer customarily communicates with employees via e-mail.
- A Pre-Election hearing will be scheduled within 8 days from the Notice.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
CDC Issues Moratorium on Residential Evictions Through 2020
October 05, 2020 —
Steven E. Ostrow, C. Jason Kim, & Marissa Levy - White and Williams LLPOn September 1, 2020, the Centers for Disease Control and Prevention (CDC) announced that it was issuing an order (CDC Order) to temporarily halt residential evictions to prevent the further spread of COVID-19. The CDC Order became effective on September 4, 2020 and will remain in effect through December 31, 2020.
The purpose of the CDC Order is to keep tenants in their residences to reduce crowding in shelters or other shared housing and to reduce the number of unsheltered homeless, as those conditions have been shown to increase the spread of COVID-19.
APPLICABILITY & PROTECTIONS
The CDC Order is broader than the previous eviction moratorium under the Coronavirus Relief and Economic Security Act (CARES Act), which applied only to federally-funded housing and expired on July 24, 2020. Eligible renters include those who qualified for a stimulus check under the CARES Act and individuals who expect to make less than $99,000 this year or a joint-filing couple that expects to make less than $198,000.
Reprinted courtesy of
Steven E. Ostrow, White and Williams LLP,
C. Jason Kim, White and Williams LLP, and
Marissa Levy, White and Williams LLP
Mr. Ostrow may be contacted at ostrows@whiteandwilliams.com
Mr. Kim may be contacted at kimcj@whiteandwilliams.com
Ms. Levy may be contacted at levymp@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Snooze You Lose? Enforcement of Notice and Timing Provisions
November 11, 2024 —
Cornelius F. "Lee" Banta, Jr. - ConsensusDocsDeadlines are an inescapable part of the construction industry. Bid deadlines. Submittal deadlines. Material delivery deadlines. Substantial completion. Final completion. And so, inevitably, fighting about deadlines becomes a necessary byproduct. Was the deadline really a deadline? Was the schedule slippage on the critical path? Should there be an equitable extension to the date of substantial completion? Given the amount of attention and concern conferred on deadlines, those drafting construction contracts naturally seek to clarify which deadlines really matter with the inclusion of notice and timing provisions.
A contract’s change order and claims procedures are often a key friction point for those drafting and administering the contract. Should there be a requirement for prior written notice of a claim for cost/time relief? How much advance notice? Who should the request be sent to? Is a specific form of notice required? What are the consequences of failing to provide timely notice? A practitioner should pay careful attention to negotiating these terms on the front end, because rest assured, these contract provisions will garner scrutiny when a change order dispute boils over.
Read the court decisionRead the full story...Reprinted courtesy of
Cornelius F. "Lee" Banta, Jr., Peckar & Abramson, P.C.Mr. Banta may be contacted at
lbanta@pecklaw.com
San Francisco OKs Revamped Settling Millennium Tower Fix
August 29, 2022 —
Nadine M. Post - Engineering News-RecordAfter more than six months of scrutiny, San Francisco’s Department of Building Inspection has issued a revised building permit for the revamped perimeter pile upgrade of the settling 645-ft-tall Millennium Tower, thanks to a determination from the planning department that the revised scheme would not have any negative environmental impacts. The upgrade now consists of 18 piles to bedrock, already installed, rather than 52.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
EPA Seeks Comment on Clean Water Act Section 401 Certification Rule
July 19, 2021 —
Karen Bennett - Lewis BrisboisThe Environmental Protection Agency (EPA) announced that it will revise a 2020 final rule clarifying requirements for water quality certification under the Clean Water Act (CWA). 85 Fed. Reg. 42210 (June 2, 2021). CWA Section 401 requires states and tribes to certify that any discharges associated with a federal permit will comply with applicable state or tribal water quality requirements.
In an effort to eliminate 401 certification being used as a tool for delaying or imposing conditions unrelated to protecting water quality on federal permits, the 2020 rule established limits on the scope and timeline for review and required any conditions on certification to be water-quality related. State and Tribal governments and environmental groups challenged the rule, arguing it constrained state and tribal decision-making authority by limiting the term “other appropriate requirements of State law” in CWA Section 401(d) to “water quality requirements” and “point source discharges.”
With EPA’s decision to revise the rule, many believe these same scope and timing limitations will be targets for change. Clients with experience, positive or negative, under the 2020 rule should consider submitting comments by the August 2, 2021 deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Bennett, Lewis BrisboisMs. Bennett may be contacted at
Karen.Bennett@lewisbrisbois.com
Skanska Will Work With Florida on Barge-Caused Damage to Pensacola Bay Bridge
October 19, 2020 —
Jim Parsons - Engineering News-RecordFlorida Dept. of Transportation investigators continue to assess damage to the Pensacola Bay Bridge, which sustained multiple impacts from two construction barges unmoored by Hurricane Sally’s storm-driven waves on Sept. 15.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of