Contractor Liable for Soils Settlement in Construction Defect Suit
February 10, 2012 —
CDJ STAFFThe California Court of Appeals ruled on January 9 in Burrow v. JTL Dev. Corp., a construction defect case in which houses suffered damage due to improperly compacted soil, upholding the decision of the lower court.
Turf Construction entered into a deal with JTL to develop a parcel they acquired. A third firm, Griffin Homes, withdrew from the agreement “when a geotechnical and soils engineering firm reported significant problems with soil stability on 14 of the lots.” Turf Construction then took over compacting and grading the lots. Turf “had never compacted or graded a residential tract before.” Robert Taylor, the owner of Turf, “testified he knew there was a significant problem with unstable soils.”
After homes were built, the plaintiffs bought homes on the site. Shortly thereafter, the homes suffered damage from soil settlement “and the damage progressively worsened.” They separately filed complaints which the court consolidated.
During trial, the plaintiff’s expert said that there had been an inch and a half in both homes and three to five inches in the backyard and pool areas. “He also testified that there would be four to eight inches of future settlement in the next fifteen to twenty years.” The expert for Turf and JTL “testified that soil consolidation was complete and there would be no further settlement.”
Turf and JTL objected to projections made by the plaintiffs’ soil expert, William LaChappelle. Further, they called into question whether it was permissible for him to rely on work by a non-testifying expert, Mark Russell. The court upheld this noting that LaChappelle “said that they arrived at the opinion together, through a cycle of ‘back and forth’ and peer review, and that the opinion that the soil would settle four to eight inches in fifteen to twenty years was his own.”
Turf and JTL contended that the court relied on speculative damage. The appeals court disagreed, stating that the lower court based its award “on evidence of reasonably certain damage.”
Turf also that it was not strictly liable, since it did not own or sell the properties. The court wrote that they “disagree because Turf’s grading activities rendered it strictly liable as a manufacturer of the lots.” The court concluded that “Turf is strictly liable as a manufacturer of the lots.”
Judge Coffee upheld the decision of the lower court with Judges Yegan and Perren concurring.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
Read the court decisionRead the full story...Reprinted courtesy of
The New Industrial Revolution: Rebuilding America and the World
March 04, 2019 —
Drew Buechley - Construction ExecutiveConventional thinking says the Industrial Revolution ended more than a century ago. Yet one crucial industry has lagged behind revolutionary changes stemming from the transition from hand production methods to the use of machines and rise of factory systems. In the 1800s, these transitions caused an influx of people to urban centers, where the majority of those changes were centered. The outcome? Not enough capital or time to build adequate housing, pushing low-income newcomers into overcrowded, unsanitary slums, resulting in increased death rates and endemic levels of contagious diseases. While other industries mechanized and surged, construction remained stagnant in comparison to demand.
Fast forward to the 21st century where the U.S .benefits from a developed and industrialized world. Monumental gains in technology, combined with regulations designed to protect communities from polluted waters and disease, have drastically improved quality of life. Yet one similarity remains – the industry still struggles to build enough housing for a growing population. Urban centers have been neglected for decades while the rate of urbanization increases annually. Communities still have no access to clean drinking water and many suffer from crumbling infrastructure. Home ownership is out of reach for an entire generation, with metropolitan areas unable to keep up with demand for housing. At the very center of this lies the staid construction industry. Lagging behind the rest of the industrialized world in terms of technology advances, it has severely impacted the ability to maintain a livable nation and world.
Reprinted courtesy of
Drew Buechley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
No Signature, No Problem: Texas Court Holds Contractual Subrogation Waiver Still Enforceable
April 10, 2023 —
Gus Sara - The Subrogation StrategistIn Chubb Lloyds Inc. Co. of Tex. v. Buster & Cogdell Builders, LLC, No. 01-21-00503-CV, 2023 Tex. App. LEXIS 676, the Court of Appeals of Texas, First District (Court of Appeals) considered whether the lower court properly dismissed the plaintiff’s subrogation case by enforcing a subrogation waiver in a construction contract which was not fully executed. The contract was signed by only one of the two subrogors and was not signed by the defendant general contractor. The Court of Appeals affirmed the trial court’s decision, holding that despite the lack of signatures, the evidence established mutual assent to the contractual terms by all parties.
The plaintiff’s subrogors, Jeffrey and Mary Meyer (collectively, the Meyers), retained defendant Buster & Codgell Builders (BCB) to expand their residence. BCB drafted a contract using the American Institute of Architects (AIA) standard form contract for residential construction. The AIA contract included, by reference, a subrogation waiver that applied to BCB and its subcontractors. Prior to beginning the work, BCB emailed Jeffrey Meyer a version of the contract that only had one signature block for both Jeffrey and Mary Meyer. Minutes later, BCB sent a second version of the contract which had a signature line for each of the Meyers. However, Jeffrey Meyer signed the first version of the contract and emailed it back to BCB. In the subject line of his email, Mr. Meyers asked that BCB countersign and return the contract. BCB did not sign and return the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
“Based On”… What Exactly? NJ Appellate Division Examines Phrase and Estops Insurer From Disclaiming Coverage for 20-Month Delay
August 20, 2019 —
Anthony L. Miscioscia and Timothy A. Carroll - White and Williams LLPOn May 28, 2019, the New Jersey Superior Court, Appellate Division examined the phrase “based on” in an assault-and-battery exclusion, finding that the phrase means “to make, form, or serve as the foundation of any claim, demand or suit.” C.M.S. Investment Ventures, Inc. v. American European Insurance Company, No. A-2056-17T3, 2019 N.J. Super. Unpub. LEXIS 1215, at *8-9 (N.J. Super. Ct. App. Div. May 28, 2019) (CMS). The CMS case is also notable because the Appellate Division held that a 20-month delay in disclaiming coverage was unreasonable and therefore warranted estoppel.
In CMS, the insured was allegedly warned by its tenant about a faulty ground-floor window that failed to lock properly. Afterward, an intruder broke into the tenant’s apartment and sexually assaulted the tenant, who sued the insured on a premises liability claim. Before she filed suit, the tenant sought payment from the insured’s CGL insurer directly. The insurer denied coverage based on the assault-and-battery exclusion and closed the file, but never informed the insured. Later, the tenant sued the insured, which sought a defense and indemnity from its insurer, which again denied coverage based on the exclusion. The insured then sought a declaration of coverage on grounds that the exclusion was ambiguous, and the insurer “was estopped from denying coverage, because it waited [20] months to inform CMS of its coverage decision.” The trial court ruled in the insured’s favor which led to the appeal in CMS.
Reprinted courtesy of
Timothy Carroll, White and Williams LLP and
Anthony Miscioscia, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Holds that Requirement of Prejudice for Late Notice Defense is a Fundamental Public Policy of the State for Choice of Law Analysis
November 04, 2019 —
Lorelie S. Masters, Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogCalifornia’s highest court held yesterday in Pitzer College v. Indian Harbor Insurance Co., that the state’s insurance notice-prejudice rule is a “fundamental public policy” for the purpose of choice of law analyses. This unanimous ruling, issued in response to certified questions from the Ninth Circuit, confirms and emphasizes California’s common law rule that policyholders who provide “late notice” may proceed with their insurance claim, absent a showing by the insurer of substantial prejudice. The California Supreme Court also extended the prejudice requirement, holding that a first-party insurer must show that it was prejudiced before denying coverage under a policy’s “consent provision,” which typically provides that the policyholder must obtain the insurer’s “consent” before incurring costs and expenses.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Lorelie S. Masters,
Michael S. Levine and
Michelle M. Spatz
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Thank You Once Again for the Legal Elite Election for 2022
December 18, 2022 —
Christopher G. Hill - Construction Law MusingsThank you once again to those in the Virginia legal community who elected me to the Virginia Business Legal Elite in the Construction Law category for the 16th consecutive year. The 16 consecutive years of election to the Legal Elite in the Construction Category span my time as a solo construction attorney. The fact that you all have continued to elect “100%” of the lawyers at The Law Office of Christopher G. Hill, PC for the last 12 years is most gratifying and only confirms that my decision to “go solo” over 12 years ago was a good one. To be included in this list of top construction attorneys is both humbling and gratifying. For the complete list of the Virginia construction lawyers that were elected along with me, see the
2022 Virginia Business Legal Elite in Construction Law.
So without further ado, thank you to all of you who voted for me. I truly appreciate your continued confidence and support of my construction law practice. Your yearly votes always prod me to learn and continually improve to meet your expectations and keep my practice at this high level. I also couldn’t do this without the great support from friends and family (not to mention clients), so my gratitude goes out to these great folks.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Florida Supreme Court Decision Limits Special Damages Presented to Juries
July 18, 2022 —
John A. Rine & Shannon Murphy - Lewis BrisboisTampa, Fla. (June 16, 2022) - Verdicts in personal injury cases are greatly impacted by the amount of medical expenses a plaintiff can present to juries. In Florida, collateral sources of compensation, such as insurance payments, are generally not disclosed to juries. However, caselaw also typically does not allow plaintiffs to recover the gross amount of medical bills, but instead the amount after insurance adjustments. For decades, Florida courts have considered whether the bills are reduced by the adjustments before or after verdict. The recent Florida Supreme Court decision in Dial v. Calusa Palms Master Association, Inc., No. SC21-43 (Fla. Apr. 28, 2022), has standardized the way past medical expenses are presented to juries where the plaintiff was treated under Medicare.
As is commonly understood, the original amount billed by medical providers is far different than the amount actually paid. Most treatment is subject to some private or government insurance and those insurers typically have negotiated rates for treatment. Thus, the bills are reduced subject to insurance contractual adjustments and the resulting net bills are far lower. For decades, defense attorneys have argued that juries should hear only the lower net amount.
Read the court decisionRead the full story...Reprinted courtesy of
John Rine, Lewis BrisboisMr. Rine may be contacted at
John.Rine@lewisbrisbois.com