Natural Disasters’ Impact on Construction in the United States
December 14, 2020 —
Robert S. Peckar & Crystal T. Dang - Construction ExecutiveIn these times of easy and instant access to news from around the globe, the effects of major earthquakes in Indonesia and Mexico, cyclones in Southeast Asia, Tsunamis around the world, volcanoes in Europe in unexpected places and, of course, raging forest fires and hurricanes in the United States are frequently in the news. Accompanying each of these disasters are immediate threats to construction projects, both physical and those affecting the safety and health of personnel.
However, after the dust settles or the waters recede, myriad issues will become obstacles to the road to recovery for a contractor to navigate. In 2020 alone, the volume of strong storms and forest fires have focused so much attention on the impact of disasters. The purpose of this article is to provide guidelines in anticipation of disasters, for reviewing the impact of a disaster as it is happening, and developing a mitigation plan to limit losses.
Anticipating Disasters
The best time to prepare for a disaster on a project is before the project starts. Reviewing contract rights, insurance policies and company disaster response protocols while a category 3 hurricane is a day away is not a best practice. To avoid falling into that situation, a contractor should follow the following guidelines. Doing so facilitates proper action during the actual disaster itself and in the aftermath.
Reprinted courtesy of
Robert S. Peckar & Crystal T. Dang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Peckar may be contacted at rpeckar@pecklaw.com
Ms. Dang may be contacted at cdang@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Appeal of an Attorney Disqualification Order Results in Partial Automatic Stay of Trial Court Proceedings
October 11, 2017 —
Howard M. Garfield & Renata L. Hoddinott - Haight Brown & Bonesteel LLPIn URS Corporation v. Atkinson/Walsh Joint Venture (No. G055271 filed September 26, 2017), Division Three of the Fourth Appellate District dealt with, for the first time, the question of whether an appeal of an attorney disqualification order results in an automatic stay of the trial proceedings and, if so, how far the automatic stay extends.
The underlying action involved a construction dispute between a contractor and subcontractor. During the pendency of that action, one party’s counsel filed a motion to disqualify another party’s counsel based on an alleged misuse of mediation-privilege protected documents. The trial court granted the disqualification motion and the disqualified counsel promptly filed a notice of appeal. The trial court then denied an application to stay proceedings pending the appeal, rejecting the assertion that the appeal automatically stayed the underlying proceedings.
Reprinted courtesy of
Howard M. Garfield, Haight Brown & Bonesteel LLP and
Renata L. Hoddinott, Haight Brown & Bonesteel LLP
Mr. Garfield may be contacted at hgarfield@hbblaw.com
Ms. Hoddinott may be contacted at rhoddinott@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Diggin’ Ain’t Easy: Remember to Give Notice Before You Excavate in California
February 15, 2018 —
Matthew Peng – Construction Law Blog If you are reading this blog, my guess is that you know what excavation is and why it is important to the construction process. However, what you may not know is the complicated California law that governs this process. The statute for an excavation contractor to be familiar with is California Government Code section 4216,
et seq. However, like most things worth pursuing, that is easier said than done. Section 4216 contains several layers of prerequisites and requirements. This article will explore the notice requirement.
Section 4216.1 requires “every operator of a subsurface installation” to share costs of a regional notification center. This is necessary because Section 4216.2(b) requires “an excavator planning to conduct an excavation shall notify the appropriate regional notification center of the excavator’s intent to excavate” before beginning that excavation. The statute lists two regional notification centers: the Underground Service Alert—Northern California and the Under Ground Service Alert—Southern California.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Peng, Gordon & ReesMr. Peng may be contacted at
mpeng@grsm.com
Leveraging the 50-State Initiative, Connecticut and Maine Team Secure Full Dismissal of Coverage Claim for Catastrophic Property Loss
March 23, 2020 —
Regen O'Malley - Gordon & Rees Insurance Coverage Law BlogOn behalf of Gordon & Rees’ surplus lines insurer client, Hartford insurance coverage attorneys Dennis Brown, Joseph Blyskal, and Regen O’Malley, with the assistance of associates Kelcie Reid, Alexandria McFarlane, and Justyn Stokely, and Maine counsel Lauren Thomas, secured a full dismissal of a $15 million commercial property loss claim before the Maine Business and Consumer Court on January 23, 2020. The insured, a wood pellet manufacturer, sustained catastrophic fire loss to its plant in 2018 – just one day after its surplus lines policy expired.
Following the insurer’s declination of coverage for the loss, the wood pellet manufacturer brought suit against both its agent, claiming it had failed to timely secure property coverage, as well as the insurer, alleging that it had had failed to comply with Maine’s statutory notice requirements. The surplus lines insurer agreed to extend the prior policy several times by endorsement, but declined to do so again. Notably, the insured alleged that the agent received written notice of the non-renewal prior to the policy’s expiration 13 days before the policy’s expiration. However, the insured (as well as the agent by way of a cross-claim) asserted that the policy remained effective at the time of the loss as the insured did not receive direct notice of the decision not to renew coverage and notice to the agent was not timely. Although Maine’s Attorney General and Superintendent intervened in support of the insured’s and agent’s argument that the statute’s notice provision applied such that coverage would still be owed under the expired policy, Gordon & Rees convinced the Court otherwise.
At issue, specifically, was whether the alleged violation of the 14-day notice provision in Section 2009-A of the Surplus Lines Law (24-A M.R.S. § 2009-A), which governs the “cancellation and nonrenewal” of surplus lines policies, required coverage notwithstanding the expiration of the policy. The insured, the agent, and the State of Maine intervenors argued that “cancellation or nonrenewal” was sufficient to trigger the statute’s notice requirement, and thus Section 2009-A required the insurer to notify the insured directly of nonrenewal. In its motion to dismiss, Gordon & Rees argued on behalf of its client that Section 2009-A requires both “cancellation and nonrenewal” in order for the statute to apply. Since there was no cancellation in this case – only nonrenewal – Gordon & Rees argued that Section 2009-A is inapt and that the insurer is not obligated to provide the manufacturer with notice of nonrenewal. Alternatively, it argued that the statute is unconstitutionally vague and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Regen O'Malley, Gordon & ReesMs. O'Malley may be contacted at
romalley@grsm.com
Virginia Tech Has Its Own Construction Boom
May 10, 2013 —
CDJ STAFFThe last few years has been a tough time for the construction industry, unless you’re in the proximity to the campus of Virginia Tech. Since 1999, the school has seen more than $1 billion in construction projects. Charles Steger, the president of the university says that “we have no intention of slowing down.”
Steger views some of the construction as vital to the school’s mission, noting that at Davidson Hall, which contains chemistry laboratories, “the wiring and other facilities were almost a health hazard.” The building is undergoing a $31 million renovation.
In order to keep the campus walkable, parking lots are being replaced by parking garages. Four dormitory buildings will be demolished and replaced by new facilities. Funds for the development have come from a mix of student fees, donations, research revenues, bond issues, and taxpayer revenues.
Read the court decisionRead the full story...Reprinted courtesy of
In Kansas City, a First-Ever Stadium Designed for Women’s Sports Takes the Field
December 17, 2024 —
Mark Byrnes - BloombergThe Kansas City Current won its first-ever at-home playoff match on Nov. 9, a breakthrough for the team playing its fourth season in the National Women’s Soccer League. Although the Current’s postseason push ended a week later in a semifinals loss, women’s soccer nevertheless returns to Kansas City, Missouri, for the national championship on Nov. 23.
The title match will be a landmark for all of women’s sports: CPKC Stadium, the new home for the Current and host of the NWSL championship game, is the first purpose-built women’s professional sports stadium in the world.
Designed by Generator Studio, a women-led firm based in Kansas City, CPKC Stadium gives the young franchise a permanent base while providing inspiration for other women’s clubs looking for equal footing in an increasingly competitive and expensive era of stadium development. The Current played their first match at CPKC Stadium to a sellout crowd this spring, and attendance hasn’t dropped since.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Byrnes, Bloomberg
Illinois Non-Profit Sues over Defective Roof
November 27, 2013 —
CDJ STAFFCoordinated Youth and Human Services (CYHS), a family services organization hired Honey-Do Home Repair to design and install a new roof for its building in Granite City, Illinois. Honey-Do removed portions of the roof for testing. A few day later during a rainstorm, a tarp failed, leading to water intrusion and damage to the building.
The CYHS is suing the contractor for $400,000. It is claiming that repairing the damage cost the organization $200,000, and it seeks additional damage and court costs.
Read the court decisionRead the full story...Reprinted courtesy of