Risk Management and Contracting after Hurricane Irma: Suggestions to Avoid a Second Disaster
September 14, 2017 —
Stephen H. Reisman, Gary M. Stein & Adam P. Handfinger – Peckar & Abramson, P.C.Peckar & Abramson attorneys have assisted contractors in the immediate aftermath of several Hurricanes, including Andrew in 1992, Wilma in 2005, Ike in 2008, and Sandy in 2012. Based on this experience, we offer some post-storm strategies for contracting and risk management in three situations:
- Ongoing projects in the area directly impacted by the storm;
- Projects remote from the storm-impacted areas, but which may be affected by material or labor shortages; and
- Requests for assistance in recovery/clean-up/rebuild eff orts, which would be new projects.
Projects Directly Impacted By Hurricane Irma:
1. Immediately review each Owner contract to determine what notices are required for delays and/or extra costs arising from the storm. Contract notice requirements and time limits vary, whether for force majeure or other similar time and compensation rights. There is no effective one-size-fits-all solution. While the initial notice letters will likely look very similar, you should make sure that each is sent as required by the contract. Check each contract’s requirements for particulars regarding content, the form of delivery, and parties and individuals designated to receive the letters as well as carbon copy recipients like the architect. Follow-up notices and time periods differ from contract to contract and should be tracked so that if, for example, a follow-up notice is required in a week per the contract terms, it is tracked to ensure compliance.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Stephen H. Reisman,
Gary M. Stein and
Adam P. Handfinger
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Building a Case: Document Management for Construction Litigation
October 07, 2019 —
Robert A. Gallagher, Jane Fox Lehman, & Michael I. Frankel, Pepper Hamilton LLP - ConsensusDocsSuccess in construction litigation often turns less on counsel’s ability to craft legal arguments and more on counsel’s ability to gather, master and present the often complex set of facts underlying the case. In construction matters, most of the key facts are found in documents: contract documents, drawings, plans and specifications, schedules, submittals, progress reports, daily logs, change orders, invoices and payment records. Nowadays, these documents will almost certainly be created, exchanged and stored electronically; many will never exist in hard copy. As such, timely collection, organization and analysis of electronically stored information (ESI) is crucially important in construction litigation.
The construction industry has always involved a large quantity of records. Today, the majority of those records exist only as ESI: Design professionals use computer-aided design (CAD) software to create construction plans. Construction managers use Primavera or similar software to create schedules and workflows. Estimators use job cost control programs. Innovative firms capture digital photos of the project, from mobilization through the punch process.
Because ESI is created and exchanged at a higher rate than hard-copy documents, ESI has facilitated a dramatic increase in the volume of records associated with construction projects. Further compounding the increase is the proliferation of mobile devices. With a smartphone in every pocket, ESI creation has moved out of the home office and the site trailer and onto the site itself. As the volume of ESI expands, so too does the time and expense associated with storing, processing, reviewing and producing these records. This article will cover strategies for balancing time and expense with the requirements of the rules and the needs of the case.
Reprinted courtesy of Pepper Hamilton LLP attorneys
Robert A. Gallagher,
Jane Fox Lehman and
Michael I. Frankel
Mr. Gallagher may be contacted at gallagherr@pepperlaw.com
Ms. Lehman may be contacted at lehmanj@pepperlaw.com
Mr. Frankel may be contacted at frankelm@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Assembly Reconsiders ‘Bad Faith’ Bill
May 31, 2021 —
Copernicus T. Gaza, Robert S. Nobel, Craig Rokuson, Eric D. Suben - Traub LiebermanThe New York State Assembly is considering A07285, which creates a private right of action for bad faith “if the insurer unreasonably refuses to pay or unreasonably delays payment without substantial justification.” The bill was first introduced in 2013 but was reintroduced on May 3, 2021 and has received some recent attention. According to the bill, an insurer acts unreasonably when it (among other things):
- Fails to provide the claimant with accurate information regarding policy provisions relating to the coverage at issue; or
- Fails to effectuate in good faith a prompt, fair, and equitable settlement of a claim or portion of a claim and where the insurer failed to reasonably accord at least equal or more favorable consideration to its insured's interests as it did to its own interests, and thereby exposed the insured to a judgment in excess of the policy limits or caused other damage to a claimant; or
- Fails to provide a timely written denial of a claimant's claim, or portion thereof, with a full and complete explanation of such denial, including references to specific policy provisions wherever possible; or
- Fails to act in good faith by compelling such claimant to initiate a lawsuit to recover under the policy by offering substantially less than the amounts ultimately recovered in such suit; or
- Fails to timely provide, on request of the policy holder or the policy holder's representative, all reports or other documentation arising from the investigation of a claim; or
- Refuses to pay a claim without conducting a reasonable investigation prior to such refusal.
Reprinted courtesy of
Copernicus T. Gaza, Traub Lieberman,
Robert S. Nobel, Traub Lieberman,
Craig Rokuson, Traub Lieberman and
Eric D. Suben, Traub Lieberman
Mr. Gaza may be contacted at cgaza@tlsslaw.com
Mr. Nobel may be contacted at rnobel@tlsslaw.com
Mr. Rokuson may be contacted at crokuson@tlsslaw.com
Mr. Suben may be contacted at esuben@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
AECOM Out as General Contractor on $1.6B MSG Sphere in Las Vegas
January 18, 2021 —
Doug Puppel - Engineering News-RecordDevelopers of the $1.66-billion MSG Sphere in Las Vegas have removed AECOM as general contractor on the project and will bring construction management in-house for the 875,000-sq-ft entertainment venue, according to a Madison Square Garden Entertainment Corp. statement released Dec. 17.
Reprinted courtesy of
Doug Puppel, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Appellate Court Rules General Contractors Can Contractually Subordinate Mechanics Lien Rights
November 26, 2014 —
Steven M. Cvitanovic, Jessica M. Lassere Ryland, & Colin T. Murphy - Haight Brown & Bonesteel LLPIn Moorefield Construction, Inc. v. Intervest-Mortgage Investment Co., 230 Cal. App. 4th 146 (4th Dist. 2014), a California appellate court upheld an agreement executed by a general contractor which subordinated its mechanic’s lien to a construction lender’s deed of trust.
In 2006, developer DBN Parkside LLC ("DBN") purchased land in San Jacinto, California (the "property") to build a medical complex (the "project"). DBN hired Moorefield Construction, Inc. (“Moorefield”) to act as general contractor and sought funding for the project from Intervest-Mortgage Investment Company (“Intervest”). Prior to the recordation of the construction loan, and unbeknownst to Intervest, Moorefield cleared and grubbed the project site. Pursuant to the construction loan agreement, Intervest required DBN to assign its rights and remedies under the construction contract to Intervest. Under its construction contract, Moorefield agreed to subordinate its lien rights to the construction loan.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Steven M. Cvitanovic,
Jessica M. Lassere Ryland and
Colin T. Murphy
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Lassere Ryland may be contacted at jlassere@hbblaw.com; and Mr. Murphy may be contacted at cmurphy@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Incorporation by Reference in Your Design Services Contract– What Does this Mean, and Are You at Risk? (Law Note)
June 19, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHas an Owner ever asked you to sign his contract before you started work on a new design project? Rhetorical question– this happens all the time, right? Especially in commercial work, developers or owners typically are not happy to simply agree to your Proposal for Services, but instead want you to sign *their* contract.
There are some risks with that you should be aware of — one of which is the seemingly arcane and legalistic language that reads something like this:
“The Developer’s contract with Owner is hereby incorporated by reference.”
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Funding the Self-Insured Retention (SIR)
August 17, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnlike a deductible, a self-insured retention (referred to an “SIR”) is, as the name suggests, a self-insured obligation of the insured before its insurer picks up coverage. The SIR needs to be exhausted by the insured (as the primary self-insurance component) before the carrier’s excess defense and indemnification obligations kick-in under the terms of the policy. However, an insured can generally exhaust an SIR by paying legal fees and costs associated with a claim.
Oftentimes, the language in the policy requires the SIR to be paid for by the named insured or an insured under the policy. This was an issue addressed by the Florida Supreme Court in Intervest Const. of Jax, Inc. v. General Fidelity Ins. Co., 133 So.3d 494 (Fla. 2014).
In this matter, a personal injury claimant asserted a claim against the contractor dealing with a residential home. The contractor hired a subcontractor to install attic stairs and the subcontract required the contractor to indemnify it. The owner of the house injured herself on the attic stairs and sued the contractor. The contractor, in turn, sought indemnification against the subcontractor that installed the attic stairs.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Panthers Withdraw City, County Deal Over Abandoned Facility
September 19, 2022 —
The Associated Press (Jeffrey Collins) - BloombergColumbia, S.C. (AP) -- Carolina Panthers owner David Tepper’s real estate company wants to revoke a bankruptcy settlement it negotiated with the city and county where its abandoned South Carolina practice facility was supposed to be built because it says the governments are making exorbitant and unreasonable demands.
GT Real Estate Holdings had offered $21 million to York County. It suggested giving the proceeds from selling part of its site in Rock Hill so the city would get at least $20 million.
But the county and city have filed separate lawsuits and court papers. York County said it is entitled to more than $80 million in part to get back money from a special penny sales tax that was supposed to expand a road but Tepper’s company used for the proposed practice facility.
Read the court decisionRead the full story...Reprinted courtesy of