Soldiers Turn Brickies as U.K. Homebuilders Seek Workers
May 20, 2015 —
Neil Callanan – BloombergAfter 21 years in the British Army that included tours of duty in Afghanistan and Iraq, Ross Wilson was offered a buyout. Britain’s shortage of construction workers allowed him to trade desert sand for muddy building sites in the north of England.
Wilson, 38, is working as an apprentice bricklayer for homebuilder Persimmon Plc, which will train more than 300 former soldiers this year because of the country’s shortage of skilled workers.
The government formed after next month’s national election will have to urgently address the lack of new homes, according to the Royal Institution of Chartered Surveyors. Persimmon’s Combat to Construction program is the latest effort by the industry to increase output as the shortage sends asking prices to record highs.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, Bloomberg
Hurricane Harvey: Understanding the Insurance Aspects, Immediate Actions for Risk Managers
September 07, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.As it’s been more than 10 years since a major hurricane made landfall in the U.S., Hurricane Harvey will test many risk managers’ insurance programs and response plans. Such disasters are complex, and decisive decision-making could mean the difference between staying in business and closing for good.
In this Alert, SDV’s Gregory Podolak and Frank Russo of Procor outline, in clear language, what risk managers need to know about large-scale natural disasters in order to mitigate risks up front and stay sound once they’ve hit.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Court Finds Matching of Damaged Materials is Required by Policy
April 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted, in part, the insured's motion for summary judgment by finding that matching roof tiles were required under the policy. Bertisen v. Travelers Home and Marine Ins. Co., 2024 U.S. Dist. LEXIS 3907 (D. Colo. Jan. 8, 2024).
The insureds sued Travelers for breach of contract, common law bad faith, and unreasonable delay or denial of benefits. They alleged that their residence was damaged by a hailstorm and that Travelers breached their policy and acted in bad faith in the handling of the claim. The insureds demanded an appraisal to determine the "amount of loss" under the policy and an appraisal award was issued. Travelers then denied payment for all roof tiles that were contemplated by the appraisal award.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
How Helsinki Airport Uses BIM to Create the Best Customer Experience
September 07, 2017 —
Aarni Heiskanen - AEC BusinessHelsinki Airport is arguably one of the best in the world. Thanks to its perfect location between Asia and Europe, it’s becoming an ever-more-popular hub. I interviewed Finavia’s Design Manager, Kari Ristolainen, about the airport’s development program and how building information modeling (BIM) is essential to its success.
On my way to Finavia’s project office, I walked by the newly opened South Pier. The construction company’s blue site huts were still there, but inside, the terminal seemed fully operational. The South Pier is the latest addition in the development program that started in 2014. Of the 21 airports that Finavia has in Finland, Helsinki is the crown jewel. The €900 million expansion and renovation program will eventually double the airport’s capacity.
In 2014, Finavia chose Lemminkäinen as the project management contractor for the terminal expansion. Destia is the partner in the alliance for extending the airport apron. PES Architects continues as the principal designer, while other designers include Sweco Structures, Granlund, and SITO.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Pennsylvania Supreme Court Adopts New Rule in Breach-of-the-Consent-to-Settle-Clause Cases
August 19, 2015 —
Sean Mahoney – White and Williams LLPIn Babcock & Wilcox Company, et al. v. America Nuclear Insurers, et al., the Pennsylvania Supreme Court recently held that where a liability insurer has agreed to provide a defense to its insured in an underlying tort action subject to a reservation of rights but refuses to consent to a settlement in that action, the insured may nevertheless accept the settlement over the insurer’s objection where the settlement is “fair, reasonable, and non-collusive” from the perspective of a reasonably prudent person in the insured’s position in light of the totality of the circumstances and is covered. Babcock & Wilcox Company v. America Nuclear Insurers, No. 2 WAP 2014, 2015 WL 4430352 (Pa. Jul. 21, 2015). This decision fills an important gap in Pennsylvania precedent addressing the rules applicable when an insurer refuses to consent to an insured’s settlement of a lawsuit.
In Babcock, the underlying plaintiffs sued Babcock & Wilcox Company and Atlantic Richfield Company (“the Insureds”) alleging that the Insured’s nuclear facilities caused bodily injury and property damage. The Insureds’ liability insurers agreed to defend the Insureds subject to a reservation of rights. The insurers later refused to consent to an offer to settle the underlying action for a total of $80 million because they believed the Insureds were likely to succeed on the merits. Nevertheless, in 2009, the Insureds accepted that offer and settled the underlying action for $80 million, notwithstanding the insurer’s refusal. The Insureds then sought reimbursement of the $80 million settlement from their insurers, who rejected that request on the ground that the Insureds had breached the consent-to-settlement/cooperation provisions of the implicated policies.
Read the court decisionRead the full story...Reprinted courtesy of
Sean Mahoney, White and Williams LLPMr. Mahoney may be contacted at
mahoneys@whiteandwilliams.com
US Court Questions 102-Mile Transmission Project Over River Crossing
February 07, 2022 —
Mary B. Powers - Engineering News-RecordA federal judge will decide in February whether to stop construction of a $492-million Iowa-to-Wisconsin transmission line, after issuing an opinion in mid-January “declaring” that federal rules preclude the 102-mile Cardinal-Hickory Creek project from crossing the 261-mile Upper Mississippi River National Wildlife and Fish Refuge by right-of-way or land transfer.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Right to Repair Act (Civ.C §895 et seq.) Applies and is the Exclusive Remedy for a Homeowner Alleging Construction Defects
February 07, 2018 —
Craig Wallace – Smith Currie McMillin Albany LLC v. Superior Court (01.18.18) ____ Cal.4th _____ (2018 WL 456728)
The California Supreme Court confirmed that the Right to Repair Act (CA Civil Code § 895, et seq. and often referred to by its legislative nomenclature as “SB800”) applies broadly to any action by a residential owner seeking recovery of damages for construction defects, regardless of whether such defects caused property damages or only economic losses. This includes the right in the Act of the builder to attempt repairs prior to the owner filing a lawsuit.
Background
Homeowners sued builder for construction defects. Included in their causes of action was a cause of action for violation of the Right To Repair Act. The Act requires that before filing litigation, a homeowner must give the builder notice and engage in a nonadversarial prelitigation process which gives the builder a right to repair the defects. The builder asked the court to stay the homeowners’ action so the prelitigaiton process could be undertaken. Rather than give the builder the repair right, the homeowners dismissed the particular cause of action from their case, leaving only other so-called common law and warranty causes of action. The common law claims sought recovery for property damage caused by the defects. The builder nonetheless asked to the Court to stay the action so it could exercise its right to repair.
The trial court, relying on
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, denied builder’s request to stay the action. The
Liberty Mutual Court concluded that certain common law construction defect claims fell outside the purview of the Act. Builder appealed. The Court of Appeal disagreed with
Liberty Mutual, so did not follow it, granted the builder’s request for a stay, and directed that the homeowners afford the builder the right to repair the claimed defects as provided under the Act.
The California Supreme Court affirmed, disapproving
Liberty Mutual and the subsequent cases relying on it.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Wallace, Smith CurrieMr. Wallace may be contacted at
swwallace@smithcurrie.com
Negligence Per Se Claim Based Upon Failure to Pay Benefits Fails
December 21, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit affirmed the district court's issuance of the insurer's motion for summary judgment, thereby rejecting the insureds' negligence per se claim for failure to pay benefits. Braun-Salinas v. Am Family Ins. Group, 2016 U.S. App. LEXIS 19555 (9th Cir. Oct. 28, 2016).
The insureds argued that Oregon recognized a negligence per se claim based on an insurer's failure to pay benefits in violation of the statutory standard under state law. Oregon appellate courts, however, only allowed a negligence per se claim only where a negligence claim otherwise existed. The Oregon courts had previously rejected a statutory theory, holding that a violation of the statute did not give rise to a tort action.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com