“I Didn’t Sign That!” – Applicability of Waivers of Subrogation to Non-Signatory Third Parties
September 30, 2019 —
Rahul Gogineni - The Subrogation StrategistIn Gables Construction v. Red Coats, 2019 Md. App. LEXIS 419, Maryland’s Court of Special Appeals considered whether a contractual waiver of subrogation in the prime contract for a construction project barred a third party – a fire watch vendor hired to guard the worksite – from pursuing a contribution claim against the general contractor. The court concluded that the general contractor could not rely on the waiver of subrogation clause to defeat the contribution claim of the vendor, who was not a party to the prime contract. As noted by the court, holding that a waiver of subrogation clause bars the contribution claims of an entity that was not a party to the contract would violate the intent of the Maryland Uniform Contribution Among Tortfeasors Act (UCATA).
When dealing with claims involving construction projects, there may exist multiple contracts between various parties that contain waivers of subrogation. The enforceability of such waivers can be limited by several factors, including the jurisdiction of the loss, the language of the waiver and the parties to the contract.
In Gables Construction, Upper Rock, Inc. (Upper Rock), the owner, contracted with a general contractor, Gables Construction (GCI) (hereinafter referred to as the “prime contract”), to construct an apartment complex. After someone stole a bobcat tractor from the jobsite, Gables Residential Services Incorporated (GRSI), GCI’s parent company, signed a vendor services agreement (VSA) with Red Coats to provide a fire watch and other security services for the project.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Top 10 Hurricane Preparedness Practices for Construction Sites
September 25, 2018 —
Andrew Gilbert - Construction ExecutiveLast year, the National Oceanic and Atmospheric Administration (NOAA) recorded that the North Atlantic saw the third highest number of major hurricanes to date. North America alone saw three tropical storms and four hurricanes make landfall, the most since 2005.
As the 2018 hurricane season takes shape (running from June 1 to Nov. 30), it’s imperative to begin construction site hurricane planning efforts early and to be as prepared as possible prior to any storm. Preparing for a storm can help ensure the safety of not only project and onsite teams, but also of the surrounding communities.
1. DEVELOP AND REVIEW A HURRICANE PREPAREDNESS AND SAFETY PLAN
Prior to hurricane season, make sure the project contractor has provided the team with a hurricane preparedness and safety plan. Review this plan with the entire team and the owner. This document outlines the exact timeline and steps the contractor will take to safely secure the project site in the event of a storm. The integrated process is especially important when dealing with renovation projects, exterior upgrades or projects that connect new construction to existing facilities.
Reprinted courtesy of
Andrew Gilbert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Gilbert may be contacted at
andrew.gilbert@cbre.com
Appraisal Panel Can Determine Causation of Loss under Ohio Law
February 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured's motion to compel an appraisal that would include a determination of causation of the loss. Eagle Highland Owners Association v. State Farm Fire and Casualty Co., 2023 U.S. Dist. LEXIS 220937 (S.D. Ohio Dec. 12, 2023).
Plaintiff argued its property suffered wind and hail damage from a storm on June 18, 2021. A claim was submitted to State Farm. State Farm's investigation determined the loss to be $0.00. Plaintiff's investigator determined the loss to be $586,647.08 in repair costs.
State Farm opposed appraisal because, in its view, the damage arose from a loss in 2019, not from the June 18, 2021 storm. Plaintiff submitted a loss claim in 2019 for damage that State Farm alleged was exactly the same as the damage alleged in the loss claim for the June 18, 2021 storm. Therefore, State Farm did not view the matter as a dispute over an amount of loss, but rather over whether a loss even occurred on June 18, 2021.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Southern California Super Lawyers Recognizes Four Snell & Wilmer Attorneys As Rising Stars
July 15, 2019 —
Snell & WilmerSnell & Wilmer is pleased to announce that four attorneys in the Orange County and Los Angeles offices have been selected for inclusion in the 2019 Southern California Rising Stars list.
Steffi Gascón Hafen,
Estate Planning and Probate
Hafen is a Certified Specialist in Estate Planning, Trust and Probate Law, California Board of Legal Specialization. Her practice is concentrated in tax, trust, and estate matters with emphasis in estate planning, trust and probate administration, and estate and gift taxation.
Irina Ling,
Tax
Ling's practice is concentrated in estate planning and taxation matters. She has experience assisting clients with all aspects of estate and tax planning, including advising clients on various charitable giving devices and business succession. Irina also assists clients with estate and gift tax issues, property tax issues, and probate and trust administration.
Joshua Schneiderman,
Mergers and Acquisitions
Schneiderman advises clients on a wide range of transactional matters, including mergers and acquisitions, joint ventures and public and private offerings of debt and equity securities. He advises clients on matters related to franchising, including the establishment of new franchise systems and the expansion of existing franchise systems nationally and internationally.
Jeffrey Singletary,
Business Litigation
Singletary concentrates his practice on business litigation in state and federal courts. He represents clients in matters involving breach of contract, business competition torts, real estate, public and private construction projects, and various intellectual property litigation matters, including trademark, trade dress, trade secret and patent claims.
Read the court decisionRead the full story...Reprinted courtesy of
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
What You Should Know About Liquidated Damages and Liability Caps for Delay and Performance Liquidated Damages
May 06, 2024 —
Chris Cazenave - ConsensusDocsLiquidated damage clauses are omnipresent in today’s construction contracts—often considered in early negotiations to provide a degree of certainty and limit financial liability.
There are two principal types of LDs appearing in construction contracts—(i.) damages for delay when a contractor fails to deliver a project by a certain milestone; and (ii.) performance damages when a contractor fails to meet specific performance requirements. Differentiating between LDs for delay and LDs for performance—especially when both LD types are combined in the same contract—is key to risk awareness and allocation during contract negotiations and throughout performance.
This article briefly outlines what you should know about LDs for delay and LDs for failing to meet certain performance requirements. The article also covers how contractors can allocate and cap risks based on risks each party can either manage, insure, or otherwise limit.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLPMr. Cazenave may be contacted at
ccazenave@joneswalker.com
Sometimes You Get Away with Default (but don’t count on it)
July 27, 2020 —
Christopher G. Hill - Construction Law MusingsAs an almost universal rule here in Virginia, failing to show up for court or respond to a lawsuit is a bad idea. Consequences include default judgment against you without the right to defend or make your case. Courts simply enter judgment and the consequences of that judgment will follow.
However, and as is often the case around here, there are small exceptions where the courts of Virginia allow the defaulting party off the hook. Sullivan Mechanical Contractors, Inc. v. KBE Building Corporation is just such a case. In Sullivan Mechanical, the Federal District Court for the Western District of Virginia was faced with a Motion to Vacate Default Judgment from KBE. The facts are laid out in the opinion, but basically come down to the usual subcontractor not paid by the general contractor and general contractor has reasons for non-payment. Subcontractor, Sullivan Mechanical, sued KBE and KBE failed to respond in a timely manner. One day after the deadline for response had passed, Sullivan moved for entry of default and the clerk entered the default that same day. KBE moved to vacate the default a mere 6 days after entry of default.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Georgia Update: Automatic Renewals in Consumer Service Contracts
August 31, 2020 —
David R. Cook - AHC BlogGeorgia HB 1039 amends O.C.G.A. § 13-12-3 to provide additional protections for consumers who enter into service contracts containing lengthy automatic renewal provisions.
Pre-Existing Requirement: For service contracts with an initial term of twelve months or longer and an automatic renewal provision for more than one month, unless the consumer terminates the agreement, sellers must provide written or electronic notification of the automatic renewal provision to the consumer. The notification must be provided to the consumer between 30 and 60 days before the cancellation deadline under such renewal provision. The notice must also “clearly and conspicuously” disclose that unless the consumer cancels, the agreement will automatically renew and disclose how the consumer may obtain details about the automatic renewal provision and cancellation procedure. The process by which a consumer may obtain such information must include the seller’s contact information (e.g., specific phone number or address), reference to the contract, or any other method provided.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com