Challenging and Defending a California Public Works Stop Payment Notice: Affidavit vs. Counter-Affidavit Process
October 21, 2019 —
William L. Porter - Porter Law GroupOne of the most effective collection procedures available to subcontractors and suppliers to California Construction projects is the “stop payment notice” procedure found under California Civil Code sections 9350 – 9364. Under this procedure, the unpaid subcontractor or supplier may serve the stop payment notice on the public entity and the direct or “prime” contractor and cause the public entity to withhold from the direct contractor 125% of the funds identified in the stop payment notice. Thereafter, funds will not generally be released unless the parties reach a settlement agreement or the issue is decided through litigation, arbitration or mediation. There is however an alternative procedure available to direct contractors to expedite the determination of whether a stop payment notice is valid and to possibly obtain an early release of the funds withheld by the public entity. This “summary proceeding” process could result in release of funds to the direct contractor in less than 30 days. The summary proceeding can also be challenged by the unpaid subcontractor or supplier. All public works contractors, subcontractors and suppliers should be aware of the process. The process for direct contractors to release a stop payment notice and for subcontractors and suppliers to challenge the process works as follows:
After a California stop payment notice has been served and the public entity has withheld funds accordingly, the direct contractor may challenge the stop payment notice by serving an “affidavit” (basically a sworn statement showing why the stop notice is not valid) on the public entity, demanding that the public entity release all funds withheld. Upon receipt of such an affidavit, the public entity will serve the subcontractor or supplier who served the stop payment notice with a copy of the affidavit, along with a “demand for release of funds”. If the stop payment notice claimant does not respond with a “counter-affidavit” by the date stated on the notice sent by the public entity (“not less than 10 days nor more than 20 days after service on the claimant of a copy of the affidavit”), then the public entity will be within its rights to release the withheld funds to the direct contractor, and the stop payment notice claimant will relinquish its stop payment notice rights.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Toddler Crashes through Window, Falls to his Death
January 24, 2014 —
Beverley BevenFlorez-CDJ STAFFTwo-year old Alijah Glenn fell 17 stories to his death after crashing through “a floor-to-ceiling window” at the Crystal Tower apartments in East Cleveland, Ohio, on January 13th, according to The Plain Dealer. Solandra Wallace, East Cleveland’s building and housing manager, told The Plain Dealer that “the city inspects the building whenever a complaint is filed and does not have regular inspections.” The apartment complex “was built in 1966 and would have to adhere to that era's building code standards,” according to the article.
The Plain Dealer reports that three complaints have been filed at the Crystal Tower since 2010. A resident complained in 2012 that “her apartment was falling apart, causing water damage and emitting a foul odor,” however, by the time an inspector arrived the ceiling was being fixed. In 2011, an “unspecified roof leak” turned out to be “condensation from a hot pipe.” An elevator was reported inoperable in 2010, however the claim was deemed “invalid” since the elevator worked when inspectors arrived.
The Cuyahoga County Medical Examiner ruled Glenn’s death accidental.
Read the court decisionRead the full story...Reprinted courtesy of
2025 Construction Law Update
January 07, 2025 —
Garret Murai - California Construction Law BlogIt’s that time of year again.
The second half of the 2023-2024 legislative session saw the introduction of 2,124 bills, of which, 1418 were signed into law. Among the bills signed by the governor impacting contractors is an increase in the small work licensing exemption for $500 to $1,000, the licensing of Indian tribes by the CSLB, and a number of project-specific bills, as is typical, related to project-specific alternative project delivery methods.
Wishing you and yours a great 2025!
Licensing
AB 2622 – Increases the small work licensing exemption from $500 to $1,000 provided that the work: (1) does not require a building permit; and (2) does not involve the employment of others to perform or assist in the work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
BHA at The Basic Course in Texas Construction Law
October 21, 2015 —
CDJ STAFFBert L. Howe & Associates, Inc., (BHA) is proud to be partnering with the State Bar of Texas, Construction Law Section, as a sponsor and exhibitor at The Basic Course in Texas Construction Law to be held November 12 & 13, 2015 at The Westin Austin at The Domain.
With offices in San Antonio and Houston, Bert L. Howe & Associates, Inc., offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in over 5,500 cases. BHA’s staff encompasses a broad range of licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of developers, general contractors and subcontractors.
BHA’s experience covers the full range of construction defect litigation, including single and multi-family residential (including high-rise), institutional (schools, hospitals and government buildings), commercial, and industrial claims. BHA also specializes in coverage, exposure, premises liability and delay claim analysis.
As the dynamic litigation climate in Texas continues to change, and as the number of construction defect and other construction-related cases continues to rise and become more sophisticated, it is more important than ever for contractors and builders to be aggressive in preparing for claims before they are made, and in defending against those claims once they are filed.
Since 1993, Bert L. Howe & Associates, Inc., has been an industry leader in providing construction consulting services, and has been a trusted partner with builders and insurance carriers, both large and small, in Texas and across the Western United States.
Register for the Basic Course...
Read the court decisionRead the full story...Reprinted courtesy of
At Least 23 Dead as Tornadoes, Severe Storms Ravage South
March 18, 2019 —
The Associated Press (Kim Chandler) - BloombergBeauregard, Ala. (AP) -- A tornado roared into southeast Alabama and killed at least 23 people and injured several others Sunday, part of a severe storm system that caused catastrophic damage and unleashed other tornadoes around the Southeast.
"Unfortunately our toll, as far as fatalities, does stand at 23 at the current time," Lee County Sheriff Jay Jones told WRBL-TV of the death toll. He added that two people were in intensive care.
Drones flying overheard equipped with heat-seeking devices had scanned the area for survivors but the dangerous conditions halted the search late Sunday, Jones said. "The devastation is incredible," he said. An intense ground search would resume Monday morning.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
California Court of Appeal Clarifies Intent of Faulty Workmanship Exclusions
October 26, 2017 —
Tiffany Casanova – Saxe Doernberger & Vita, P.C.Last month, in Global Modular, Inc. v. Kadena Pacific, Inc., 1 a California Court of Appeal clarified the meaning of the frequently asserted j.(5) and j.(6) exclusions of the standard commercial general liability policy; an issue the court deemed one of “first impression” for the state. The court took a close look at how courts nationwide handle the exclusions and relied on the policy language to come to a policyholder-friendly decision.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Casanova, Saxe Doernberger & Vita, P.C.Ms. Casanova may be contacted at
tlc@sdvlaw.com
Should I Pull the Pin? Contractor and Subcontractor Termination for Cause
January 26, 2017 —
Patrick McNamara - Porter Law GroupAny owner or general contractor who has a few projects under his or her belt has likely had this thought: “My contractor (or subcontractor) is not performing the way I expected; should I replace him?” The other side of the termination coin is: “This project is not going the way I expected; should I get out?”
While there may be an emotional high that immediately comes from terminating a contractor or subcontractor (or leaving a project, in mid-stream), there are many factors to be weighed, before making that decision.
Project Delay. Replacing a contractor or subcontractor that has already begun performance always results in delays to the project. Assessing the work in place, interviewing replacement contractors, and negotiating the terms of the new relationship can easily consume weeks, if not months of project time.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at