An Occurrence Under Builder’s Risk Insurance Policy Is Based on the Language in the Policy
April 03, 2023 —
David Adelstein - Florida Construction Legal UpdatesBuilder’s risk insurance coverage is a vital property insurance coverage during the course of construction. Builder’s risk insurance is not a one-size-fits-all product so please make sure you are working with your insurance broker to procure this product that factors in and covers risk associated with the project.
Builder’s risk insurance is typically an occurrence-based policy. No different than other occurrence-based policies (such as commercial general liability), a dispute may arise as to the occurrence. This could be due to the triggering of the actual policy during the coverage period or it could be due deductible obligations, as in the case discussed below. When dealing with a builder’s risk insurance policy–again, no different than any policy–the language in the policy matters. Definitions used in the policy to define specific terms matter and, in numerous cases, the ordinary dictionary meanings of terms matter. But it all starts with the policy language.
In KT State & Lemon, LLP v. Westchester Fire Insurance Co., 2023 WL 2456499 (M.D.Fla. 2023), a builder’s risk policy provided coverage from April 2018 through the end of November 2019. There was a $50,000 per occurrence deductible for loss caused by or from water damage. An extension to the builder’s risk policy was negotiated through the end of January 2020 that increased this water damage deductible to $250,000 per occurrence. During construction and the testing of the fire suppression (sprinkler) system, leaks started to occur resulting in water damage. Two leaks occurred in September 2019, one leak in October 2019, one leak in November 2019, and two leaks in December 2019 (during the extension and higher water damage deductible period).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Spencer Mayer Receives Miami-Dade Bar Association's '40 Under 40' Award
March 04, 2024 —
Lewis Brisbois NewsroomMiami, Fla. (February 23, 2024) – Miami Associate Spencer Mayer received the 2024 Miami-Dade Bar Association Young Lawyers Section’s '40 under 40' Award at the association's annual "Miami Nights" event on February 22.
Mr. Mayer serves on the Board of Directors of the Miami Dade Bar Association’s Young Lawyers Section. Lewis Brisbois was a proud sponsor of this event, which raised funds for the organization's community service initiatives and pro bono programming.
Mr. Mayer is a member of the General Liability Practice. His practice focuses on all aspects of civil litigation, including complex commercial litigation, products liability, premises liability, wrongful death, catastrophic injury, and insurance coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Commonwealth Court Holds That Award of Attorney's Fees and Penalties is Mandatory Under the Procurement Code Upon a Finding of Bad Faith
October 29, 2014 —
William J. Taylor and Michael Jervis – White and Willams LLPIn a decision regarding a payment claim by a highway contractor against the City of Allentown, the Commonwealth Court of Pennsylvania has held that an award of attorney's fees and penalties is mandatory under the terms of the Pennsylvania Procurement Code, 62 Pa.C.S. § 3901 et seq., upon a finding of bad faith by the non-paying government agency, even though the statute only states that a court “may” award such fees and penalties.
In A. Scott Enterprises, Inc. v. City of Allentown, Cmwlth. Ct. No. 2163 C.D. 2013, the plaintiff, A. Scott Enterprises, Inc. (Scott), won a contract with the City of Allentown (City) to construct a one mile roadway. Several weeks after commencing work, Scott learned that soil at the construction site was potentially contaminated with arsenic, and was instructed by the City to suspend its work. Because of the soil contamination, additional work would be required to complete the project and Scott submitted proposals for the additional work plus its suspension costs. However, the City never approved the additional work and the project was never completed. The City never paid Scott for costs incurred due to the suspension of the work and Scott filed suit to recover its losses. The jury found that the City had breached the contract with Scott and had acted in bad faith in violation of the Procurement Code, and awarded damages to Scott for its unreimbursed suspension costs. However, the trial court denied Scott’s request for an award of attorney's fees and penalty interest. Both Scott and the City appealed the final judgment to the Commonwealth Court, which reversed the trial court’s refusal to award attorney's fees and penalties.
Reprinted courtesy of
William J. Taylor, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Incorporation, Indemnity and Statutes of Limitations, Oh My!
January 19, 2017 —
Christopher G. Hill – Construction Law MusingsWe all know that the contract is king in Virginia. We also know that Virginia will allow for a so called “incorporation” clause that will allow for “flow down” of certain prime contract provisions in a way that will make those provisions applicable to subcontractors. We also know that a claim for breach of contract or other contractual claim does not last forever due to certain statutes of limitation found in the Code of Virginia. What happens when all of these elements crash together in one place leading to litigation? Well, a relatively recent case from the Virginia Supreme Court gives at least a partial answer.
In Hensel Phelps Construction Company v Thompson Masonry Contractor, Inc, the Virginia Supreme Court considered a claim that arose from construction at Virginia Tech by Hensel Phelps. The construction concluded in 1998 (remember that date). The Prime Contract included language concerning a one year “Guarantee of Work” as well as fairly typical Warranty of Workmanship” language. However the Prime Contract also stated that the one year guaranty term did nothing to affect any other limitations period for any other action pursuant to the Prime Contract (this is important as well because Virginia Tech was not subject to any statute of limitations due to its status as an agency of the Commonwealth of Virginia). Final payment was made to Hensel Phelps and subsequently to the subcontractors in 1999.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
No Coverage for Hurricane Sandy Damage
August 02, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate recommended that summary judgment be entered in favor of the insurer, thereby eliminating coverage for property damage incurred during Hurricane Sandy. Madelaine Chocolate Novelties, Inc. v. Great Northern Ins. Co., 2017 U.S. Dist. LEXIS 103015 (E.D. N.Y. June 30, 2017).
Madelaine Chocolate owned a facility three blocks form the Atlantic Ocean and one block from the Jamaica Bay section of Long Island Sound. Hurricane Sandy arrived October 29, 2012. Madeline Chocolate's facility sustained significant damage to its inventory, production machinery and premises, as storm surge from both bodies of water hit the property. Operations ceased during the 2012 holiday season and beyond, resulting in millions of dollars in lost income.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Another Case Highlighting the Difference Between CGL Policies and Performance Bonds
January 07, 2015 —
David M. McClain – Colorado Construction Litigation During the summer of 2011, Ellis Construction hired Cool Sunshine Heating & Air Conditioning to install the HVAC systems in a single-family home it was building for Gary Doberman and Ellen Robertson in Boulder, Colorado. The homeowners took issue with much of the work performed on their home and tried to negotiate directly with Ellis Construction. When those negotiations broke down, the homeowners sent a notice of claim pursuant to the Construction Defect Action Reform Act, C.R.S. § 13-20-801, et seq. One of the defects alleged in the notice of claim was that the SEERS 13 compressor installed by Cool Sunshine was inappropriate for the system and that because it was installed to run on only one stage, it did not meet the City of Boulder’s code requirements for noise levels. The homeowners therefore requested that the compressor be replaced with a SEERS 20 compressor, which would comply with the Boulder City Code.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
It’s a COVID-19 Pandemic; It’s Everywhere – New Cal. Bill to Make Insurers Prove Otherwise
August 17, 2020 —
Scott P. DeVries & Andrea DeField - Hunton Andrews KurthOn June 29, in a development that may fundamentally change the landscape for California businesses which have sustained COVID-19 related business interruption loss, two California legislators amended pending legislation to address several of the most hotly contested issues regarding insurance recovery for these devastating losses.
The bill, Assembly Bill 1552, focuses on All-Risk property insurance policies. As amended, it would create a “rebuttable presumption” that COVID-19 was present on and caused physical damage to property which was the direct cause of business interruption. A similar rebuttable presumption would apply to orders of civil authority coverage and to ingress/egress coverage. The bill would further prohibit COVID-19 from being construed as a pollutant or contaminant for purposes of any policy exclusion unless the exclusion specifically referred to viruses. The bill would apply to any All-Risk policy in effect on or after March 4, 2020 and is written to satisfy the standards for an “urgency” statute, taking effect immediately upon being signed into law.
Reprinted courtesy of
Scott P. DeVries , Hunton Andrews Kurth and
Andrea DeField, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Duke Energy Appeals N.C. Order to Excavate Nine Coal Ash Pits
April 17, 2019 —
Mary B. Powers - Engineering News-RecordDuke Energy Progress said April 11 it will appeal the North Carolina Dept. of Environmental Quality’s order issued earlier this month to excavate nine remaining large coal ash pits at six power plants in the state and move ash to lined landfills; the firm claims the new mandate at sites previously deemed low-risk will cost up to $5 billion to implement.
Read the court decisionRead the full story...Reprinted courtesy of