Miller Act and “Public Work of the Federal Government”
March 01, 2017 —
David Adelstein – Florida Construction Legal UpdatesThe Miller Act applies to the “construction, alteration, or repair of any public building or public work of the Federal Government.” 40 U.S.C. s. 3131.
A recent opinion out of the Northern District of Oklahoma sheds light on what the Miller Act means regarding its application to any public work of the Federal Government. See U.S. v. Bronze Oak, LLC, 2017 WL 190099 (N.D.Ok. 2017). If the project is not a public works project of the Federal Government, the Miller Act does not apply.
In this case, the Department of Transportation entered into an agreement with the Cherokee Nation where the Department would provide lump sum funding and the Nation would use the money to fund transportation projects. Based on the federal funding, the Nation issued a bid for a transportation project in Mayes County, Oklahoma and the project was awarded to a prime contractor. The prime contractor provided a payment bond that identified the United States as the obligee (as a Miller Act payment is required to do) and stated that it was issued per the Miller Act. Thereafter, the Nation and Mayes County, Oklahoma entered into a Memorandum of Understanding where the County would assume responsibility for the construction and maintenance of the project and the Nation would pay the County an agreed amount upon the completion of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
The Anatomy of a Construction Dispute- The Claim
January 12, 2015 —
Christopher G. Hill – Construction Law MusingsA new year brings with it promise and challenges. The promise is a relatively clean slate and the thought that 2015 will be a great year for construction professionals and those that assist them. The challenges come from the almost inevitable issues that can arise on a construction site with its many moving parts and enough potential pitfalls to make even the most optimistic construction attorney, contractor, subcontractor or supplier think that Murphy was an optimist.
In order to assist with the potential challenges, this post will be the first in a series of “musings” on the best way to handle a payment dispute arising from a construction contract. This week’s post will discuss what the first steps should be once a payment dispute or claim arises. We’ll assume that you, as a construction contractor, have taken early advantage of the services of a construction lawyer and have carefully reviewed your contract for issues before signing that contract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Best Practices for ESI Collection in Construction Litigation
October 05, 2020 —
Kelley J. Halliburton - Construction ExecutiveThe construction business has always been heavy on records and data but now more than ever much of that information is stored electronically. Gone are the days of just a trailer full of drawings and paper documents.
Construction projects now have huge amounts of electronically stored information (ESI) including contract documents; drawings in both CAD, PDF and other formats; schedule files such as Primavera; spreadsheets; photos; job cost control software files; formal correspondence; and an ever-expanding amount of email communications. Successful collection of this ESI can be critical to the success of litigation in construction cases, where often very complex facts will need to be gathered to support a claim or defense.
The best first step to a successful ESI collection is to build a solid foundation before trouble arises with prepared policies and procedures in place. Implementing and enforcing a document management plan on a project basis will make sure documents are kept in an organized fashion so that materials can be accessed quickly and easily. Document management is important for types of ESI that are not handled well by word-searches, including Primavera schedules, photos and videos.
Reprinted courtesy of
Kelley J. Halliburton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “It’s None of Your Business.”
May 22, 2023 —
Daniel Lund III - Lexology“It’s none of your business.”
So said a construction surety resisting discovery of its underwriting file in the context of the surety’s affirmative $2 million indemnity claim (on a $25M bond), and a Missouri federal court agreed.
In response to the surety’s indemnity suit, the defaulted principal contractor and additional corporate indemnitors offered up defenses of “lack of consideration and the doctrine of unclean hands, laches, waiver and/or estoppel, among others.” The indemnitors also issued written discovery to the surety seeking to obtain the surety’s underwriting file – which would reveal the underpinnings of the surety’s decision to issue the bond to the contractor – asserting “that the underwriting and due diligence documents are relevant to the[] lack of consideration defense. [Indemnitors] claim that ‘[t]his defense is based on Defendants' belief that Plaintiff did not conduct any reasonable inquiry into any Defendants' ability to pay or financial resources and therefore Plaintiff did not rely on the financial condition of each Defendant in determining whether to issue the bonds.’"
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
A Property Tax Exemption, Misapplied, in Texas
June 18, 2019 —
Anthony B. Cavender - Gravel2GavelIn an important ruling for Texas businesses, the Texas Supreme Court has unanimously ruled that the TCEQ misapplied the Texas property tax’s exemption for specified pollution control equipment.
Since 1993, the Texas Constitution has included a provision which authorizes the Texas Legislature to exempt from ad valorem taxation “all or part of real and personal property used … wholly or partly … for the control or reduction of air, water or land pollution.” This provision is implemented by Section 11.31 of the Texas Tax Code, which is administered by the Texas Commission on Environmental Quality. (See the rules at Title 30, Chapter 17 of the Texas Administrative Code.) If the Executive Director of the TCEQ determines that the equipment is used wholly or partly for pollution control, he issues a “positive use determination”; in the event it does not, the Executive Director issues a “negative use determination and rejects the application for the exemption. In 2007, Section 11.31 was amended at 11.31 (k) to list several items of equipment that are presumed to be pollution-control equipment, including “heat recovery steam generators” or HRSGs. This equipment is used by powerplants to reduce nitrogen oxide emissions that are the product of generation of electricity. Several applications were submitted to the TCEQ by the Brazos Electric Power Cooperative, seeking a tax exemption for its HRSG units. In July 2012, the TCEQ denied these applications, with the flat declaration that HRSGs are not pollution-control equipment—“they are used solely for production.” The Brazos Cooperative sued the Commission, and on May 3, 2019, in the case of Brazos Electric Power Cooperative, Inc. v. TCEQ, the Texas Supreme Court issued a unanimous opinion reversing the Commission, and the lower court (the Eight Court of Appeals, sitting in El Paso) that affirmed the Commission’s action.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Arbitration is Waivable (Even If You Don’t Mean To)
February 16, 2016 —
Christopher G. Hill – Construction Law MusingsBe careful with how you act with arbitration clauses in your contracts. If you are not careful in how you act to enforce these clauses, you could find yourself stuck in court whether you like it or not.
As I stated in a recent update to a post last month, the Fourth Circuit Court of Appeals recently weighed in on the issue of a contractor’s waiver of its rights to arbitration under a contract. Briefly, the facts of Forrester v. Penn Lyon Homes, et. al., No. 07-2171 are as follows. The Forrester’s sued Penn Lyon and its warranty company alleging among other things a breach of express warranty based upon a warranty contract containing a mandatory arbitration clause. Instead of immediately alleging an affirmative defense based upon the arbitration clause, the defendants removed the case to federal court and litigated for 18 months before raising the arbitration defense for the first time.
The 4th Circuit (correctly in my opinion) affirmed the lower court and held that the defendants defaulted their right to arbitration because of their actions in defense of the court action and the prejudice to the plaintiffs caused by those actions.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Burg Simpson to Create Construction Defect Group
November 06, 2013 —
CDJ STAFFBurg Simpson Eldredge Hersh & Jardine, P.C. has announced that the attorneys of Sullan2, Sandgrund, Perczak & Nuss, P.C. will be joining them as S2SPN Construction Defect Group of Berg Simpson. The group will be headquartered at Burg Simpson’s Engelwood offices.
The combined firms will comprise 55 attorneys. Michael Burg, founding shareholder at Burg Simpson, said that “in Colorado for the past 29 years, these lawyers have provided the highest level of construction defect representation.” His counterpart, Scott Sullan of Sullan2, Sandgrund, Perczak & Nuss said that he and his colleagues are “delighted to be a part of the Burg Simpson team.” The two firms join forces effective January 1, 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Appraisers May Determine Causation
January 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a case of first impression, the Iowa Court of Appeals held that an appraisal may determine issues of causation. North Glenn Homeowners Association v. State Farm Fire & Cas. Co., 854 N.W. 2d 67 (Iowa Ct. App. 2014).
On July 15, 2009, North Glenn Homeowners Association submitted a claim to State Farm for hail damage on the roof. The claim was paid. North Glenn did not repair all of the damage, instead deciding to use some of the money to make other repairs to the property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com