Miller Act Claim for Unsigned Change Orders
June 30, 2016 —
David Adelstein – Florida Construction Legal UpdatesContracts and subcontracts often contain language that requires
change orders to be in writing and that no change order work shall be performed unless agreed to in advance in a signed change order. Oftentimes change order work is performed but the parties have not complied with the strict requirements of the contract by having this work signed off by the parties in a change order prior to the commencement of the work. Well, can such requirements be
waived? If so, can such change orders form the basis of a
Miller Act claim? The answer is generally yes provided the party arguing waiver can support the waiver with evidence (that the other party voluntarily relinquished the requirements through its course of conduct / actions).
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury” or “property damage” be caused by an “occurrence” and that the “bodily injury” or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury” or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury“ or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivan’s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing , including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
Wildfire Insurance Coverage Series, Part 5: Valuation of Loss, Sublimits, and Amount of Potential Recovery
July 25, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogInsurance policies provide different levels of insurance coverage and even if the amount purchased was adequate at one time, developments over time (e.g., inflation, upgrades, regulatory changes and surge pricing) may leave the policyholder underinsured. In this post in the Blog’s Wildfire Insurance Coverage Series, we emphasize the need for policyholders to take a close look at the policy’s terms to select the right type and amount of coverage for a potential loss.
Various types of coverage are available and there has been extensive litigation concerning the amount of coverage provided by one policy form or another. For example, the policyholder may have purchased market value coverage (the value of the house at the time of the wildfire), replacement coverage subject to a policy limits cap, guaranteed replacement cost coverage, or some variation on the theme. While the property may be properly valued when the insurance is purchased, it may become undervalued at the time of loss due to factors like inflation or home improvements that were not disclosed to the insurer. And, however generous the limits may be when the policy is procured, as one court discussed, it may be insufficient when “surge pricing” occurs after a wildfire.
[1]
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Corps Proposes $4.6B Plan to Steel Miami for Storm Surge
June 22, 2020 —
Pam Radtke Russell - Engineering News-RecordA $4.6-billion U.S. Army Corps of Engineers proposal to protect Miami from future storm surge, largely by building massive sea walls and elevating infrastructure systems, is the latest of such plans the agency has developed for East Coast communities.
Pam Radtke Russell, Engineering News-Record
Ms. Russell may be contacted at Russellp@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Steven L. Heisdorffer Joins Higgins, Hopkins, McLain & Roswell
March 27, 2019 —
Steve Heisdorffer - Colorado Construction LitigationHiggins, Hopkins, McLain & Roswell is pleased to announce that Steve Heisdorffer has joined the firm as Special Counsel. Steve joins the firm after having been a partner at Godin & Baity, LLC for the last twenty-five years.
Mr. Heisdorffer represents construction professionals in construction defect disputes and advises them regarding risk mitigation and transfer. Mr. Heisdorffer is an experienced trial lawyer that has tried commercial disputes and construction defect cases in arbitration forums and courts over the last 28 years. In addition, he has successfully represented large and small companies in commercial disputes, including computer software performance and intellectual property disputes, taking several to trial. Steve has also acted as a counselor to technology companies. Steve has expertise drafting and negotiating development agreements, distributor agreements, license agreements, and service agreements for his technology clients.
Mr. Heisdorffer graduated with high honors from both the University of Northern Iowa and University of Iowa, College of Law and is an AV ® Preeminent™ Peer Review Rated attorney by Martindale-Hubbell and has presented to a variety of trade groups including technology, construction, and insurance industries.
Read the court decisionRead the full story...Reprinted courtesy of
Steve Heisdorffer, Higgins, Hopkins, McLain & RoswellMr. Heisdorffer may be contacted at
heisdorffer@hhmrlaw.com
Safety Accusations Fly in Dispute Between New York Developer and Contractor
July 01, 2019 —
Richard Korman - Engineering News-RecordThe developer of a New York City high rise and the project's former prime contractor are trading unusually nasty safety related accusations in a dispute over the contractor's exit from the project. The contractor, New York City-based Pizzarotti, claims the settlement of the structure in soft soils creates hazards in future work that could send building components crashing to the streets. In reply, developer Fortis Property Group says the contractor’s uneven pace of work is to blame for what it sees as only slab misalignments that don’t compromise safety in any way.
Read the court decisionRead the full story...Reprinted courtesy of
Richard Korman, ENRMr. Korman may be contacted at
kormanr@enr.com
Montana Federal Court Upholds Application of Anti-Concurrent Causation Clause
November 08, 2021 —
Tred R. Eyerly - Insurance Law HawaiiInterpreting Montana law, the federal district court found that the policy's anti-concurrent causation clause prevented coverage for the insured's damaged home. Ward v. Safeco Ins. Co. of Am., 2021 U.S. Dist. LEXIS 149051 (D. Mont. Aug. 9, 2021).
Plaintiff was advised by her tenants that water was bubbling up from the ground. It was determined that water was leaking from a main pipe serving the property. Subsequently, this old pipe was abandoned, left in the ground, and replaced with a new pipe in a new path with new excavation. Nevertheless, the insured reported the incident to her agent under her Landlord Protection Policy issued by Safeco, but reported there was no damage to the property.
Two months later, it was discovered a pipe burst again. The insured called her agent, who maintained the loss would not be covered, but agreed to submit a claim to Safeco. Safeco hired an inspector. A report stated that a portion of cracks found in the concrete perimeter of the home were not new and that the shape of the structure on which the house sat could explain their presence. The report noted that new cracks in the foundation could have been caused by a lack of care to make sure that the foundation was sufficient supported by consolidated soil during the excavation of the new water line. Based upon this report, Safeco denied coverage based upon the earth movement and water damage exclusions.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ninth Circuit Resolves Federal-State Court Split Regarding Whether 'Latent' Defects Discovered After Duration of Warranty Period are Actionable under California's Lemon Law Statute
December 17, 2015 —
Laura C. Williams & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Daniel v. Ford Motor Company (filed 12/02/15), the Ninth Circuit resolved a federal and state court split on the issue of whether consumers can sustain a breach of implied warranty claim under California’s Song Beverly Consumer Warranty Act (aka the “lemon law” statute) for “latent” defects discovered after the warranty period has expired. Answering this question in the affirmative, the Ninth Circuit followed the holding in the California state appellate decision of Mexia v. Rinker Boat Co. 95 Cal.Rptr.3d 285 (2009), which definitively determined there is nothing in California’s lemon law that requires a consumer to discover a latent defect during the duration of the warranty.
The underlying class action lawsuit was brought in federal district court by purchasers of Ford Focus vehicles. The plaintiffs alleged Ford was aware of, but failed to disclose, a rear suspension defect in the Focus that resulted in premature tire wear which can cause decreased vehicle control, catastrophic tire failure and drifting on wet or snowy roads. The plaintiffs alleged a number of claims including violations of California’s Song Beverly Consumer Warranty Act and Magnuson Moss Warranty Act. Ford successfully moved for summary judgment on all claims prompting an appeal.
Reprinted courtesy of
Laura C. Williams, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Ms. Williams may be contacted at lwilliams@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of