Congratulations to Wilke Fleury’s 2023 Super Lawyers and Rising Stars!!
July 10, 2023 —
Wilke Fleury LLPWilke Fleury is extremely proud that 18 of its incredible attorneys have been selected as 2023 Northern California Super Lawyers or Rising Stars! Super Lawyers rates attorneys in each state using a patented selection process and publishes a yearly magazine issue that produces award-winning features on selected attorneys. Congratulations to this talented group:
Super Lawyers of 2023
David A. Frenznick
Steven J. Williamson
Matthew W. Powell
Daniel L. Egan
George A. Guthrie
Michael G. Polis
Daniel J. Foster
Stephen K. Marmaduke
Neal C. Lutterman
Trevor L. Stapleton
Ronald R. Lamb
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury LLP
Construction Laborers Sue Contractors Over Wage Theft
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAspen Journalism reported that “[f]our laborers who worked on the Burlingame Phase II affordable housing project financed by the city of Aspen are suing three of the project’s contractors, alleging they weren’t paid for some of their work and were never paid overtime when they worked more than 40 hours per week.”
Towards Justice, nonprofit legal services group, filed suit in August on behalf of Fernando Villalobos, Sergio Roman, Ramon Gonzalez and Hugo Esqueda, and against construction companies Haselden Construction, LLC of Centennial, Continental Constructors, LLC of Littleton, and JMS Building of Glenwood Springs.
Both sides have agreed that “the men were paid for some, but not all, of their work,” but dispute “the value of the work done by the laborers.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Law Client Alert: California Appeals Court Refuses to Apply Professional Services Exclusion to Products-Completed Operations Loss
March 19, 2014 —
Valerie A. Moore and Chris Kendrick - Haight Brown & Bonesteel LLPIn North Counties Engineering v. State Farm (No. A133713, filed 3/13/14), State Farm insured an engineering company under CGL insurance that had a professional services exclusion and included products-completed operations (PCO) coverage. The owner of the engineering company, NCE, contracted with a winery to construct a dam and associated works. Also on the project was the owner's son, who had his own construction company, NCD. There were multiple contracts, both oral and written, variously naming one company or the other. The evidence later showed that the father performed hands-on work for the project.
After completion, the winery was sued over sediment and erosion caused by the dam. State Farm denied coverage on the ground that the professional services exclusion applied, as well as a mistaken belief that the policy had no PCO coverage. State Farm then changed its position and agreed to defend, but only going forward. The insured sued State Farm over past defense fees, alleging breach of contract and bad faith. The case went to trial and after testimony detailing State Farm's claim handling, the trial judge granted a nonsuit, finding that the professional services exclusion barred all coverage:
"[I]f you look at the pleadings, the legal pleadings and the contracts, the NCE role is, as the engineering company, the support company, and that company was overseeing the [sic] NCD to make sure that whatever they did was done right.... NCE is the expert on the job, the professional providing professional services, design and construction, and also overseeing the work of NCD, the son’s business, which is doing more of the physical activity.... That takes professional expertise and I think all of what Mr. Akerstrom did was professional.... It was this professional work, and not 'something incidental to their professional involvement' that gave rise to the underlying actions. In this situation, it’s not a malpractice or E and O policy. It’s a business policy, which has good benefits, but is subject to the professional services exclusion."
Reprinted courtesy of
Valerie A. Moore and
Chris Kendrick of Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Set to Alter Law on Key Project, Workforce Issues
December 02, 2019 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordWith its term now under way, the U.S. Supreme Court could change federal laws with industry impact—from where huge pipelines can be built and new regulation of pollution in groundwater to whether LGBTQ workers have anti-bias rights under the 1964 Civil Rights Act.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Mr. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Expanded Virginia Court of Appeals Leads to Policyholder Relief
January 29, 2024 —
Michael S. Levine & Olivia G. Bushman - Hunton Insurance Recovery BlogExercising its newly expanded jurisdiction that now permits Virginia’s intermediate appellate courts to hear insurance coverage disputes, the Court of Appeals recently reversed a lower court decision that allowed a two-year “Suits Against Us” provision to serve as a basis for an insurer’s refusal to reimburse repair and replacement costs incurred more than two years after the date of loss. Bowman II v. State Farm Fire and Casualty Co., Record No. 1256-22-3 (Nov. 21, 2023). CAV (unpublished opinion).
In the proceeding below, the circuit court found no justiciable controversy and dismissed the complaint where repairs to the policyholder’s fire-damaged home continued more than two years after the date of the fire. The circuit court relied on a two-year limitation in the policy that governed the period within which the policyholder must bring suit against the insurer.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Olivia G. Bushman, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Bushman may be contacted at obushman@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Lien Needs to Be Recorded Within 90 Days from Lienor’s Final Furnishing
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA lienor needs to record its construction lien within 90 days of its final furnishing date. This final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work. A lien recorded outside of the 90-day window will be deemed invalid.
The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window. This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor. The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid. The bankruptcy court was determining the validity of the lien.
In this matter, the owner hired a swimming pool contractor to construct a pool. On October 25, 2002, the pool contractor installed pavers around the pool. After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool. As a result, the pool contractor ceased doing any more improvements. But, neither the pool contractor nor the owner terminated the contract. Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris. On January 27, 2003, the pool contractor recorded its lien.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Time To “Construct” New Social Media Policies
March 28, 2022 —
Aaron C. Schlesinger, Lauren Rayner Davis & Jennifer Harris - ConsensusDocs1. The Social Media Dilemma
Social media has significantly impacted all facets of society, especially the way people communicate. Its impact and application to the construction industry is no different. TikTok, the video-sharing platform, is one of the world’s most popular platforms today, with over one billion active users monthly. From just one video, users can gain thousands—if not millions—of followers overnight. Social media has been used to present a narrative that the workplace can be fun, or that employees are enjoying working together. Social media can also, however, serve as a tool to document a perfect storm of events, such as a building collapse or crane malfunction, which can then be misconstrued and smeared throughout the internet, all with your company’s logo in the background.
So, what happens when an incident on your jobsite is branded across social media as a #constructionfail, and the project owner ultimately initiates legal action? Can this video be used against your company? Can employers limit or otherwise restrict employees’ social media activity to avoid potential liability? How does the existence of social media posts affect dispute resolution procedures?
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. (ConsensusDocs),
Lauren Rayner Davis, Peckar & Abramson, P.C. (ConsensusDocs) and
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs)
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Ms. Davis may be contacted at ldavis@pecklaw.com
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Federal District Court Issues Preliminary Injunction Against Implementation of the Fair Pay and Safe Workplaces Final Rule
November 03, 2016 —
Patrick J. Greene, Jr. & Lori Ann Lange – Peckar & Abramson, P.C. Client AlertOn July 31, 2014, President Barack Obama issued Executive Order 13673. As subsequently amended, the Executive Order purports to “increase efficiency and cost savings in the work performed by parties who contract with the Federal Government by ensuring that they understand and comply with labor laws.” On August 25, 2016 the Federal Acquisition Regulation (“FAR”) Council published the final FAR Rule and the United States Department of Labor (“DOL”) published its Guidance further implementing the Executive Order. The FAR final rule was scheduled to go into effect in stages, starting with solicitations with an estimated value of $50 million or more on October 25, 2016. The potential effect of these new regulations on government contractors has been the subject of prior alerts from this office and much ongoing discussion.
Reprinted courtesy of
Patrick J. Greene, Jr., Peckar & Abramson, P.C. and
Lori Ann Lange, Peckar & Abramson, P.C.
Mr. Greene may be contacted at pgreene@pecklaw.com
Ms. Lange may be contacted at llange@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of