The Job is Substantially Complete, the Subcontract was Never Signed, the Subcontractor Wants to be Paid—Now What?
July 28, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCA recent case in North Carolina illustrates the types of problems created when a general contractor accepts a subcontractor’s bid and then allows the subcontractor to perform the work without obtaining a signed subcontract.[i] In this case, the general contractor (Choate Construction Company – “Choate”) accepted a bid from a foundation subcontractor (Southeast Caissons, LLC – “SEC”). Choate sent the subcontract to SEC. SEC provided its changes in a “Proposed Addendum” to the subcontract stating, “[SEC] hereby accepts the terms of the attached Subcontract, subject to and conditioned upon Choate[’s] acceptance of the terms set forth in this Addendum[.]” After that, Choate called SEC and exchanged emails concerning the subcontract terms, but did not reach an agreement. SEC then performed its subcontract and sought payment, and acknowledged it had not signed the subcontract. Choate agreed it owed SEC something, but refused to pay because SEC did not have a signed subcontract, asserting the subcontract was not binding on Choate.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Do Change Orders Need to be in Writing and Other Things That Might Surprise You
June 02, 2016 —
Garret Murai – California Construction Law BlogYou’ve likely heard it before or maybe you’ve even said it yourself: “Go ahead and get started, we’ll get you a change order later.”
The only thing is, “later” never happens, and after you’ve finished performing the work you find yourself in a fight over whether you’re entitled to get paid for the work you performed.
So, do you need a written change order to get paid for extra work you performed? Read on, you may be surprised.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Real Estate & Construction News Round-Up 01/26/22
February 07, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThe future of traditional real estate skills for virtual land buys is questioned, China’s property sector might experience policy easing, U.S. commercial real estate sales set records in 2021, and more.
- As the platforms and business case for virtual land buys mature, the future of traditional real estate skills remains unclear when it comes to managing virtual ownership and development. (Patrick Sisson, Bisnow)
- China’s real estate sector is likely to see “significant easing” in the policies that govern it after stricter financing rules for property development set in 2020 were met with debt, causing a contraction in the market. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Charges in Kansas Water Park Death
March 28, 2018 —
David Suggs - CDJ STAFFCaleb Schwab, a 10-year old boy was killed by decapitation on a water slide at a Kansas City water park, Schlitterbahn in 2016. Thirteen other people had suffered injuries on the ride prior to Caleb’s death ranging in severity from broken toes to concussions. Schlitterbahn employees have since claimed that park officials covered up past occurrences of water slide injuries.
Three people have been indicted in this case according to a CNN report by Marlena Baldacci, Sheena Jones and Hollie Silverman. Jeffrey Henry, the co-owner of the Schlitterbahn water park, Tyler Austin Miles, the park’s former director of operations and John Schooley.
Charges include second-degree murder, involuntary manslaughter, aggravated battery and aggravated child endangerment. Caleb suffered a fatal injury when the raft that he and the two women who were riding with him became airborne and contacted the netting attached overhead.
Investigators have found maintenance issues and ride design flaws that violate safety standards leading to lack of prevention of rafts becoming airborne during the ride. Caleb’s family will receive nearly $20 million in the settlement. Caleb’s father Scott, released a statement about placing full trust in the Attorney General Derek Schmidt who is presiding over the investigation and indictments.
Read the court decisionRead the full story...Reprinted courtesy of
Water Damage Sub-Limit Includes Tear-Out Costs
June 06, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Florida Court of Appeals affirmed the trial court's ruling that the homeowner policy's sub-limit for water damage included tear-out costs. Sec. First Ins. Co. v. Vazquez, 2022 Fla. App. LEXIS 1205 (Fla. Ct. App. Feb. 18, 2022).
A discharge of water from the cast iron pipes caused damage to the home. The water escaped as a result of the failed cast iron pipes due to wear and tear, deterioration, and corrosion. The insurer acknowledged coverage for the water damage and paid $10,000 under the Limited Water Damage Endorsement (LWD Endorsement). The provision recited that "'[t]he limit of liability for all damage to covered property provided by this endorsement is $10,000 per loss." The insureds' suit argued they were entitled to additional benefits for the cost to tear out and replace a part of the concrete slab - an action necessary to reach the corroded pipes. The parties stipulated that the cost of the tear-out would be $40,000.
The parties agreed that the LWD Endorsement provided coverage of both water damage and tear-out costs. They also agreed that the cost to repair and/or replace the corroded pipes was not covered. They disagreed, however, over the proper interpretation of the limitation of liability provision in the LWD Endorsement. The insured argued that the $10,000 limit applied to both water damage and tear-out costs. The insureds argued that the $10,00 limit applied only to water damage to covered property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
“Details Matter” is the Foundation in a Texas Construction Defect Suit
March 01, 2012 —
CDJ STAFFThe Court of Appeals of Texas has ruled in the case of Barzoukas v. Foundation Design. Mr. Barzoukas contracted with Heights Development to build a house. He subsequently sued Heights Developments and “numerous other defendants who participated in the construction of his house.” Barzoukas eventually settled with all but two defendants, one who went bankrupt and Foundation Design, the defendant in this case. In the earlier phase, Barzoukas made claims of “negligence, negligent misrepresentation, fraud, fraudulent inducement, conspiracy, and exemplary damages in connection with the foundation.”
Foundation Design had been hired to install 15-foot piers to support the foundation. The engineer of record, Larry Smith, sent a letter to Heights Development noting that they had encountered hard clay stone when drilling. Smith changed the specifications to 12-foot piers. Initially, the City of Houston called a halt to work on the home when an inspector concluded that the piers were too shallow. Heights Development later convinced the city to allow work to continue. Subsequently, experts concluded that the piers were too shallow.
Foundation Design filed a motion for summary judgment. The trial court granted this, “without specifying the basis for its ruling.” Barzoukas contends the court was in error. Foundation Design contends that “Barzoukas failed to proffer competent evidence establishing that their conduct proximately caused damages.” Further, they did not feel that Smith’s letter gave “rise to viable claims for fraud and fraudulent inducement.”
One problem the court had was a lack of evidence. The court noted that “the purported subcontract is entirely missing” in the pleadings. The court has no contract between Bazourkas and Heights Development, nor one between Heights Development and either Foundation Design or Smith. The court underscored the importance of this, writing, “details matter.” They found that “the details are largely missing here.” Without the contract, the court found it impossible to determine if “Smith or an entity related to him agreed to indemnify Heights Development for damages arising from Smith’s negligent performance.”
As the material facts are in dispute, the appeals court found that there were no grounds for a summary judgment in the case. “Pointing to the existence of a contract between Heights Development and Barzoukas, or to the existence of a subcontract, is the beginning of the analysis ? not the end.”
Foundation Design and Smith also claimed that Barzoukas’s expert did not proffer competent evidence and that the expert’s opinions were conclusory. The trial court did not rule on these claims and the appeals court has rejected them.
Finally, Barzoukas made a claim that the trial court should not have rejected his argument of fraud and fraudulent inducement. Here, however, the appeals court upheld the decision of the lower court. “Barzoukas did not present evidence supporting an inference that Smith or Foundation Design made a purposeful misrepresentation.
The court remanded the case to the trial court for reconsideration. One member of the panel, Judge Charles Seymore, upheld the entire decision of the trial court. He dissented with the majority, finding that the economic loss rule foreclosed the claim of negligence.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Texas Construction Firm Officials Sentenced in Contract-Fraud Case
August 07, 2018 —
Tom Ichniowski – Engineering News-RecordTwo top officials of a Texas construction company—Honest, Experienced, Reliable Contracting Solutions LLC—have been sentenced to federal prison terms for defrauding the State Dept. through a plan to steer more than $1 million in contracts to the company, the Dept. of Justice says.
Read the court decisionRead the full story...Reprinted courtesy of
Tom Ichniowski, ENRMr. Ichniowski may be contacted at
ichniowskit@enr.com